Federal Courts Keep Chipping Away at the CDC Eviction Moratorium
March 22, 2021 —
Kriston Capps - BloombergIn a March 10 decision, a federal court in Cleveland blocked the national eviction moratorium, making it the second court to challenge the emergency measure implemented under President Donald Trump and extended by the Biden administration. The order clears the way for courts and landlords to resume evictions against tenants across much of Ohio. But the landlord groups who brought the suit believe that the decision could have a broader national application, setting the stage for an earlier-than-anticipated resumption of eviction activity before the ban expires on March 31.
The judge ruled that the Centers for Disease Control and Prevention, which introduced its ban on evictions in September, lacks the authority to enact such a policy. While the court stopped short of issuing an injunction against the CDC ban, its decision goes further than the Texas court that made a similar call late in February.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Is Privity of Contract with the Owner a Requirement of a Valid Mechanic’s Lien? Not for GC’s
January 04, 2021 —
Christopher G. Hill - Construction Law MusingsAs any reader of this construction law blog knows, mechanic’s liens make up much of the discussion here at Construction Law Musings. A recent case out of Fairfax County, Virginia examined the question of whether contractual privity between the general contractor and owner of the property at issue is necessary. As a reminder, in most situations, for a contract claim to be made, the claimant has to have a direct contract (privity) with the entity it sues. Further, for a subcontractor to have a valid mechanic’s lien it would have to have privity with the general contractor or with the Owner.
The Fairfax case, The Barber of Seville, Inc. v. Bironco, Inc., examined the question of whether contractual privity is necessary between the general contractor and the Owner. In Bironco, the claimant, Bironco, performed certain improvements for a barbershop pursuant to a contract executed by the two owners of the Plaintiff. We wouldn’t have the case here at Musings if Bironco had been paid in full. Bironco then recorded a lien against the leasehold interest of The Barber of Seville, Inc., the entity holding the lease. The Plaintiff filed an action seeking to have the lien declared invalid because Brionco had privity of contract with the individuals that executed the contract, but not directly with the corporate entity.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Natural Disasters’ Impact on Construction in the United States
December 14, 2020 —
Robert S. Peckar & Crystal T. Dang - Construction ExecutiveIn these times of easy and instant access to news from around the globe, the effects of major earthquakes in Indonesia and Mexico, cyclones in Southeast Asia, Tsunamis around the world, volcanoes in Europe in unexpected places and, of course, raging forest fires and hurricanes in the United States are frequently in the news. Accompanying each of these disasters are immediate threats to construction projects, both physical and those affecting the safety and health of personnel.
However, after the dust settles or the waters recede, myriad issues will become obstacles to the road to recovery for a contractor to navigate. In 2020 alone, the volume of strong storms and forest fires have focused so much attention on the impact of disasters. The purpose of this article is to provide guidelines in anticipation of disasters, for reviewing the impact of a disaster as it is happening, and developing a mitigation plan to limit losses.
Anticipating Disasters
The best time to prepare for a disaster on a project is before the project starts. Reviewing contract rights, insurance policies and company disaster response protocols while a category 3 hurricane is a day away is not a best practice. To avoid falling into that situation, a contractor should follow the following guidelines. Doing so facilitates proper action during the actual disaster itself and in the aftermath.
Reprinted courtesy of
Robert S. Peckar & Crystal T. Dang, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Peckar may be contacted at rpeckar@pecklaw.com
Ms. Dang may be contacted at cdang@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Another Reminder that Contracts are Powerful in Virginia
February 08, 2021 —
Christopher G. Hill - Construction Law MusingsRegular readers of this construction law blog are likely tired of my refrain that the contract is king here in Virginia. With few exceptions, some of which have been passed in the last few years, the contract can and does essentially set the “law” for the transaction. A recent opinion from the 4th Circuit Court of Appeals confirms this principle.
In Bracey v. Lancaster Foods, LLC, the Court looked at the question as to whether parties can contractually limit the statute of limitations in which a plaintiff or arbitration claimant can file its claim for relief. In Bracey, Michael Bracey, a truck driver, sued his former employer, Lancaster Foods, asserting various employment law claims. Lancaster moved to dismiss and compel arbitration based on the terms of an alternative dispute resolution agreement Bracey signed when he was hired, under which he consented to arbitration of any employment-related claim and waived all rights he may otherwise have had to a trial. Bracey challenged the arbitration clause, one that also included a 1-year limitation on the time in which Bracey was allowed to file any claim, as unconscionable. A federal judge in Maryland agreed and granted the motion to dismiss.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Changes to Va. Code Section 43-13: Another Arrow in a Subcontractor’s Quiver
November 02, 2020 —
Christopher G. Hill - Construction Law MusingsAs is always the case here in Virginia, our General Assembly has made some legislative changes that affect construction contracting. One of these changes is an amendment to Va. Code 43-13 found in the mechanic’s lien section of the Virginia Code.
This section of the code has always required that any money paid to a contractor must first go toward paying its subcontractors, suppliers and laborers prior to being used for any other purpose. Prior to 2020, the only remedy for violaiton of Va. Code 43-13 was to go to the local Commonwealth’s Attorney and request a prosecution of the wrongdoer. For various reasons, including that such action did not get the subcontractor or supplier that remained unpaid under this section paid, this remedy was not often pursued except in the most egrigious cases.
A key change in the statute occurred during the 2020 legislative session states as follows:
Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project. Any contract or subcontract provision that allows a contracting party to withhold funds due under one contract or subcontract for alleged claims or damages due on another contract or subcontract is void as against public policy.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
House of Digital Twins
March 08, 2021 —
Cristina Savian - AEC BusinessAs a vocal and passionate advocate for the adoption of Digital Twins for our built assets, I keep finding myself standing in, what feels like, the middle of a house of cards, observing its always rocky structure in constant danger of collapse. A wobbly system threatened by the tremors stressed by one of the most prominent digital revolutions that our construction industry has ever experienced.
DIGITAL TWINS FOR OUR BUILT ASSET.
This booming industry trend is gaining speed at a rate that the construction industry has never experienced before. Construction has always been slow at innovating and still holds its title as the least digitalised industry, but the Digital Twin revolution has now found our location and is ready to disrupt. I often witness how these forces attempt to pull down the cards, but, to my surprise, their resilience is what keeps holding the house together. Hold on, is this resilience or resistance?
Read the court decisionRead the full story...Reprinted courtesy of
Cristina Savian, AEC Business
Deadlines. . . They’re Important. Project Owner Risks Losing Claim By Failing to Timely Identify “Doe” Defendant
December 21, 2020 —
Garret Murai - California Construction Law BlogEarlier this year I filed a complaint in a court which I won’t identify other than to say that it wasn’t the San Francisco Superior Court. Immediately upon filing the complaint the Court gave notice of a trial date. As counsel for the party bringing the action, I appreciate this, as it eliminates the back and forth jostling that can sometimes occur when trying to get a trial date.
Here’s the kicker though. While I appreciate getting a trial date straight out of the gate. The date I got was . . . wait for it . . . not until 2022!
Those who litigate in California state courts know that the courts are understaffed and overworked. But you’ve got to give this un-named court credit for being upfront. Forget the “well, let’s see where this goes” niceties. Trial within a year? Fugetaboutit. Trial within a year and a half. Don’t even think about it. Trial within two years. It’s about as good as you’re going to get.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Additional Dismissals of COVID Business Interruption, Civil Authority Claims
December 29, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAmong the recent decisions dismissing complaints for business interruption and civil authority coverage due to closures caused by COVID-19 are Pappy's Barber Shops, Inc. v. Farmers Group, Inc., 2020 U.S. Dist. LEXIS 166808 (S.D. Calif. Sept. 11, 2020) and Sandy Point Dental v. Cincinnati Insurance Co., 2020 U.S. Dist. LEXIS 171979 (E.D. Ill. Sept. 21, 2020). The difficulty in proving "direct physical loss" was the downfall of both cases.
In Pappy's, claims were made for business income losses insured as a result of local and state closure orders. The policy required "direct physical loss of or damage to property at the described premises." Plaintiffs argued that "direct physical loss of" did not require a tangible damage or alteration to property and that the loss of the ability to continue operating their businesses as a result of the government orders met this requirement.
The court relied upon a prior decision, 10E, LLC v. Travelers Indem. Co. of Connecticut, 2020 U.S. Dist. LEXIS 165252 (C.D. Calif. Sept. 2, 2020) [post here], where the court noted that under California law, losses from inability to use property did not amount to "direct physical loss" within the meaning of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com