Empowering Success: The Advantages of Female Attorneys in Construction Defect Law
December 11, 2023 —
Alexa Stephenson, Hoosai Kabiri & Ivette Kincaid - Kahana FeldPer the most recent U.S. Census records, women make up 50.4% of the U.S. population. It should come as no surprise then that women currently outnumber men in U.S. law schools. Nevertheless, as of 2022, only 38% of attorneys, 30% of federal judges, 22% of equity partners, and 12% of managing partners nationwide are comprised of women. While great strides have been made in the last century to increase gender equality in the legal field, there is undoubtedly still a long way to go.
Studies have shown that women in the workforce lead to a number of benefits not only to the business itself, but to a business’ employees and culture. In the realm of construction defect law in particular, the presence and contributions of female attorneys have become increasingly impactful and essential. As the legal landscape evolves, the benefits of having female attorneys practicing in this specialized field are becoming more evident, offering a range of advantages that contribute to a more diverse, comprehensive, and successful legal environment. These advantages include:
1. Diverse Perspectives: Female attorneys bring a unique perspective to the practice of construction defect law, enriching the field with their insights and experiences. Their diverse backgrounds and viewpoints can lead to innovative strategies and fresh approaches when tackling complex legal issues.
Reprinted courtesy of
Alexa Stephenson, Kahana Feld,
Hoosai Kabiri, Kahana Feld and
Ivette Kincaid, Kahana Feld
Ms. Stephenson may be contacted at astephenson@kahanafeld.com
Ms. Kabiri may be contacted at hkabiri@kahanafeld.com
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Read the full story...
Construction Litigation Roundup: “Builder’s Risk Indeed”
October 24, 2023 —
Daniel Lund III - LexologyA contractor for a hotel in Seattle was tasked with constructing the hotel utilizing premanufactured modular hotel rooms. The modular unit portion of the project was the subject of a $15.8 million subcontract between the general contractor and the manufacturer. The manufacturer was also responsible to the GC for shipping and installing the modular units.
Shipping was to be “DDP,” or “Delivery Duty Paid” – which, according to a New York federal court, “is an international shipping term meaning that the seller assumes all responsibilities and costs for delivering property to the named place of destination, including export and import clearance, fees, duties, and taxes.” Additionally, per the subcontract, the manufacturer was responsible for “ensur[ing] all modular units [were] covered, secured[,] and protected from damage during the shipping process….” The modular units were shipped from Poland to Seattle. In the shipping process, the units spent some time in the Port of Everett in Washington state, where the units sustained water damage while sitting in port.
A related damage claim made by the subcontractor against the general contractor’s builder’s risk policy. On the face of the policy, the policy covered subcontractors as “additional insured” parties, covered all manner of materials and the like to be used on the project, and would provide that coverage in the process of transporting the materials insofar as “inland or coastal waters” were concerned. Yet, the builder’s risk insurer refused to cover the claim for the damages to the modular units which occurred while sitting in port in Everett.
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Court of Appeals Upholds Default Judgment: Serves as Reminder to Respond to Lawsuits in a Timely Manner
October 02, 2023 —
Anna Basnaw - Ahlers Cressman & Sleight PLLCIn
Cyrus Way Partners, LLC. (“Cyrus”) v. Cadman, Inc. (“Cadman”), the primary issue on appeal was whether the trial court erred in denying Cadman’s motion to vacate the default judgment under Civil Rules 55 and 60. A default judgment is a legal ruling that can be entered in favor of the plaintiff when the defendant fails to respond to a lawsuit. If that happens, the court may resolve the lawsuit without hearing from the other side. In Washington, a party typically has 20 days to appear in a suit before being at risk for default judgment. If a default judgment is entered for the plaintiff, the defendant can move to vacate the default judgment, meaning the defendant hopes the court will set aside the default judgment as if it never happened. In this case, Cadman, the defendant, presents several ultimately unsuccessful arguments for why the default judgment in favor of Cyrus, the plaintiff, should be vacated.
Cyrus and Orca Beverage Inc. (“Orca”) are under common ownership. In 2018, Cyrus began a project to build a warehouse for Orca, which included the construction of a large concrete slab. Cadman was hired to supply the concrete. Cyrus hired Olympic Concrete Finishing Inc. (“Olympic”) to finish the concrete. On April 1, 2018, Cadman poured the concrete, and Olympic finished the slab. The next day, Cyrus noticed several problems with the slab, which experts hired by both Cyrus and Cadman opined were caused by an abnormally high air content in the concrete.
Read the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Competent, Substantial Evidence Carries Day in Bench Trial
February 26, 2024 —
David Adelstein - Florida Construction Legal UpdatesA number of construction disputes, if tried, are tried through a bench trial meaning the judge is serving in the role of the jury in the construction trial. In a bench trial, two points are important. First, “the factual findings of the judge are entitled to the weight of a jury verdict.” Q.G.S. Development, Inc. v. National Lining Systems, Inc., 2024 WL 357984 (Fla. 3d DCA 2024) (internal quotation and citation omitted). Second, “[t]he appellate court is only authorized to reverse if such findings are not supported by competent, substantial evidence.” Id. These two points need to be appreciated when participating in any construction dispute that will be resolved through a bench trial.
A recent construction dispute highlights these two points. In Q.G.S. Development, a contractor was hired to refurbish a golf course which included constructing a lake. The contractor was going to construct the lake, prepare the subgrade, perform dewatering, and it hired a subcontractor to install a reservoir liner at the bottom of the lake.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Liquidated Damages Clause Not Enforced
October 02, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA liquidated-damages clause was not enforced in a recent case before the Georgia Court of Appeals. The clause did not contain standard provisions that would normally allow a trial court to enforce the clause as written. As a result, the trial court looked beyond the contract to determine whether the City satisfied the requirements for enforcement of the liquidated-damages clause. Below are the relevant excerpts.
City of Brookhaven v. Multiplex, LLC, A23A0843, 2023 WL 4779591 (Ga. Ct. App. July 27, 2023)
Here, the Contract provides for “Liquidated Damages at the rate of $1,000.00 per calendar day” in the last paragraph of the Scope of Work addendum. The Contract lacks, however, any language indicating that the liquidated damages were not intended to be a penalty. See Fuqua Const. Co. v. Pillar Dev., Inc., 293 Ga. App. 462, 466, 667 S.E.2d 633 (2008) (rejecting use of parol evidence where the parties “explicitly agreed” in “unambiguous contract language” that the liquidated damages were not a penalty). Absent such language, the court can look to parol evidence in the record to determine the effect the provision was intended to have. See J.P. Carey Enterprises, 361 Ga. App. at 391-392 (1) (b), 864 S.E.2d 588 (looking to “extrinsic evidence” such as emails, documents, and deposition testimony to determine whether the damages provision at issue was a penalty); see also Gwinnett Clinic, Ltd. v. Boaten, 340 Ga. App. 598, 602-603, 798 S.E.2d 110 (2017) (“Shah’s testimony also suggested that one purpose of the liquidated damages provision was to deter employees from breaching the agreement”).
Read the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
First Circuit Rejects Insurer’s “Insupportable” Duty-to-Cooperate Defense in Arson Coverage Suit
October 24, 2023 —
Geoffrey B. Fehling & Yaniel Abreu - Hunton Insurance Recovery BlogIn
Philadelphia Indemnity Insurance Co. v. BAS Holding Corp., the Court of Appeals for the First Circuit rejected an insurer’s “insupportable” defense that the insured company had breached its duty to cooperate by refusing the insurer’s request for an examination under oath of the company’s president. The decision is a reminder that, while examinations under oath can be effective tools to allow the insurer to properly investigate a claim, an insured’s duty to cooperate is not boundless and does not demand attendance at examinations that are not reasonably requested.
Background
BAS Holding involves the destruction of a landmark building in Boston by an arsonist. The owner, BAS Holding Corporation, submitted an insurance claim to its property insurer to recover insurance proceeds for the damage to the building. The insurer investigated the claim to determine whether the damage to the building was covered and issued a reservation of rights letter suggesting that the policy may not provide coverage for the fire. As part of its investigation, the insurer requested an examination under oath as a condition to coverage under the policy, which led to BAS presenting the property’s operations coordinator for an interview. Shortly after examining the operations coordinator, the insurer sought another examination of BAS’s president and owner, as well as five other employees. In response, BAS questioned whether the additional examinations were “reasonably required” and said that it would consider the requests if the insurer could explain why they were necessary.
Reprinted courtesy of
Geoffrey B. Fehling, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the full story...
Catching Killer Clauses in Contract Negotiations
January 29, 2024 —
James T. Dixon - Construction ExecutiveRisk-management personnel who are in the business of reviewing and negotiating construction contracts have some simple tools at their disposal to make sure their edits are addressing all of the killer risk-shifting clauses in those contracts. One of those is the index to that document. But not all authors of construction contract documents are kind enough to include an exhaustive index in their form agreements.
One of the most popular sets of general conditions, the A201 General Conditions published by the American Institute of Architects, includes one that is fairly comprehensive. It identifies the six terms that include a reference to indemnification, for example. On the other end of the spectrum are the innumerable custom forms created by public and private project owners, and these rarely have an index.
Even more powerful than an index is the search or find functions that are available in word processing applications and now in Adobe, the publisher of documents in portable document format, more commonly known as PDF. But with PDF documents, one must be careful to make sure the document under review is in fact searchable. Because every letter counts, it is important to have full confidence in the integrity of the search.
Reprinted courtesy of
James T. Dixon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Governmental Action Exclusion Bars Claim for Damage to Insured's Building
November 27, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe lower court's decision finding no coverage based upon the governmental action exclusion was affirmed by the Appellate Court of Illinois. McCann Plumbing, Heating & Cooling v. Pekin Ins. Co., 2023 Ill.App. LEXIS 300 (Ill. App. Ct. Aug. 23, 2023).
McCann purchased a building to use for its heating, ventilation, and air conditioning business. The building was surrounded by two unihhabited properties which often flooded. The city determined that a building on the adjacent property had to be demolished. In the course of destruction, the McCann's building was damaged, leaving a portion of their building open to the elements.
McCann sought coverage from Pekin for damage incurred in the demolition. The policy provided coverage for "direct physical loss of or damage to" the covered property. Pekin denied coverage under the policy's governmental action exclusion, which provided,
We will not pay for loss or damage caused directly or indirectly by any of the following:
. . .
c. Governmental Action
Seizure or destruction of property by order of governmental authority . . .
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com