Bridging the Gap at Alaska’s Juneau Creek
September 21, 2026 —
Tim Newcomb - Engineering News-RecordThe largest single-span steel plate girder bridge launch in the nation wasn’t about setting records. Alaska’s Juneau Creek Bridge design was a matter of necessity. The fully erected steel plate girder bridge, featuring a 440-ft main span hovering 285 ft above the Juneau Creek, was part of the larger Sterling Highway project. It offered a logistical challenge but was chosen among over a dozen bridge types due to the unique constraints brought by the mountainous site.
Read the full story...Reprinted courtesy of
Tim Newcomb, Engineering News-RecordENR may be contacted at
enr@enr.com
Differing Site Conditions Claim Requires a Misrepresentation
May 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesIf you are entertaining a
differing site conditions claim, consider this Third District Court of Appeals case from the mid-90s.
In Hendry Corp. v. Metropolitan Dade County, 648 So.2d 140 (Fla. 3d DCA 1995), a contractor was hired by Dade County to demolish the old Rickenbacker Causeway in Miami. The original 1941 plans of the causeway were made available to contractors. The lowest bidding contractor that was awarded the project based its bid “on its conclusion that the pilings supporting the old bridge were made of concrete.” Hendry, supra at 141. The contractor based this conclusion on the original plans, its visual observation, and experience.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Fraud Allegations Stymie Additional Insured’s Request for a Defense
May 14, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Federal District Court granted the insurer’s motion to dismiss the insured’s complaint seeking a defense of the underlying case alleging fraud. Renovation Realty, Inc. v. Colony Ins. Co., 2026 U.S. Dist. LEXIS 21409 (S.D. Cal. Jan. 30, 2026).
Mara Fortin sued Renovation Realty and others (“Fortin litigation”) from the fraudulent sale of a residence. The underlying complaint alleged Renovation “deliberately misrepresented of the residence as ‘completely remodeled’ and ‘meticulously maintained’.” The defendants, however, including Renovation, “knew from sources including a pre-renovation termite report documenting fungus and dry rot . . . that the Property harbored pre-existing material defects.”
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
White and Williams LLP Secures a Clean Sweep Dismissal of Architect's Professional Liability Coverage Lawsuit
August 16, 2026 —
Daniel E. Bryer & Brendaliz Minaya Ruiz - White and Williams LLPWhite and Williams LLP achieved a complete dismissal of professional liability coverage claims through a strategic defense led by Insurance Coverage and Bad Faith Practice Group attorneys Daniel E. Bryer, Partner and Brendaliz Minaya Ruiz, Associate.
In a nuanced action styled, Vincent Cusumano Architect P.C., et al. v. Berkshire Hathaway Direct Insurance Company, et al., decided in the U.S. District Court for the District of New Jersey, plaintiffs asserted twelve pre-contractual and contractual-based causes of action against their liability insurer, Berkshire Hathaway Direct Insurance Company, and its insurance agent (collectively, “Defendants”) for denying a professional liability claim arising from plaintiffs’ prior work.
Reprinted courtesy of
Daniel E. Bryer, White and Williams LLP and
Brendaliz Minaya Ruiz, White and Williams LLP
Mr. Bryer may be contacted at bryerd@whiteandwilliams.com
Ms. Ruiz may be contacted at minayaruizb@whiteandwilliams.com
Read the full story...
That’s a Wrap! Pennsylvania Court Holds Arbitration Clause in Online Agreement Unenforceable
May 14, 2026 —
Gus Sara - The Subrogation StrategistIn Duffy v. Tatum, 2026 Pa. Super. LEXIS 112, 2026 PA Super 41, the Superior Court of Pennsylvania (Superior Court) considered whether an arbitration provision contained in the online Terms of Service on the defendant’s website were enforceable. The plaintiff, Daniel Duffy (Duffy), visited the website of defendant, Dolly, Inc. (Dolly), to purchase moving services. Duffy selected the number of movers, items to be moved and the type of vehicle needed. To complete the booking, the website required Duffy to checkmark a box labeled “By checking this box I accept the Dolly Terms of Service.” Duffy did not have to open the link or scroll to the bottom of the agreement before being able to click on the checkmark box. The Terms of Service included an arbitration provision requiring that any dispute related to the moving services to be resolved by arbitration in accordance with the American Arbitration Association. The Terms of Service did not include any statement that the user was waiving the right to a jury trial. The Superior Court found the internet Terms of Service unenforceable.
During the moving process, an accident occurred and injured Duffy. In May 2024, Duffy and his wife sued Dolly and other related entities alleging negligence and loss of consortium. Dolly filed preliminary objections alleging that the parties agreed to alternative dispute resolution. The lower court overruled the preliminary objections, finding that Dolly’s website did not provide reasonably obvious notice of its Terms of Service to Duffy and, as such, Duffy never agreed to waive his constructional right to a jury trial. Dolly filed an appeal to the Superior Court.
Read the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Daily Journal Publishes Article by Brenda Radmacher on Proposed Overhaul of California Construction Defect Law
June 29, 2026 —
Brenda Radmacher - The Construction SeytDaily Journal (California) featured an article by Construction Law partner
Brenda Radmacher, “A new path for construction defects in California.” The piece, published on June 15, 2026, examines Assembly Bill 1903 and its potential to significantly reshape California’s construction defect framework, particularly for common interest properties.
The article highlights how AB 1903 would overhaul the state’s current right-to-repair system by mandating completion of prelitigation procedures, raising requirements for defect claims, strengthening developers’/builders’ rights to repair, and introducing a voluntary “certified building” program. The legislation aims to rebalance competing interests by reducing litigation-driven costs while preserving protections for homeowners.
Read the full story...Reprinted courtesy of
Brenda Radmacher, Seyfarth Shaw LLPMs. Radmacher may be contacted at
bradmacher@seyfarth.com
Nevada’s Mandatory Nonbinding Arbitration Law for Civil Cases is Going Through Changes
May 14, 2026 —
Brandon Wright & Manuel Gurule - Lewis BrisboisNevada currently operates an expedited litigation program designed to resolve civil disputes with a value up to $50,000 without incurring the “usual” expense of litigating these disputes. Over time, however, the number of civil cases that have been “exempted” from this program based on the claimed damages exceeding $50,000 has grown dramatically. In response, the Nevada Legislature recently enacted a number of rule changes designed to streamline Nevada’s arbitration process and include more cases. Among these changes are increasing the arbitration “cap” from $50,000 to $100,000.
By way of background, the Nevada’s Court Annexed Arbitration program is a mandatory, non-binding program for civil cases in judicial districts that have county populations of 100,000 or more [1]. Nevada’s Court Annexed Arbitration was born out of NRS 38.250, which was enacted in 1991 and went into effect in the summer of 1992. The newly enacted NRS 38.250 was regarded as a way to address the problem of increased court caseloads while promoting judicial economy and efficiency in civil cases having a probable jury award of less than $25,000 [2]. Initially, cases that were automatically exempt from the program included class actions, medical malpractice disputes, divorce proceedings, and other domestic relations matters [3].
Reprinted courtesy of
Brandon Wright, Lewis Brisbois and
Manuel Gurule, Lewis Brisbois
Mr. Wright may be contacted at Brandon.Wright@lewisbrisbois.com
Mr. Gurule may be contacted at Manuel.Gurule@lewisbrisbois.com
Read the full story...
Key Person Provisions in Construction Contracts: Because People, Not Companies, Build Projects
October 27, 2026 —
Nate Simon - Construction ExecutiveIn construction, the person running your job matters: the project manager who sat in your preconstruction meetings, who understands the phasing, who knows why the MEP coordination sequence was set up the way it was, who has relationships with your team and the owner’s team. That person is not interchangeable. And if they disappear six weeks into the job and get replaced by someone who’s never read the drawings, you have a problem.
This happens all the time. A contractor or consultant sells the A-team—the experienced project manager; the sharp superintendent; the people who won the job—during the proposal and interview. Then, once the contract is signed, those people quietly get moved to a larger project, not out of anything nefarious, but usually out of a necessity. A fire happens on another project and they are needed to put it out. By the time you realize those working on your project aren’t the ones you originally signed on, you’re three months in and the damage is already underway.
Reprinted courtesy of
Nate Simon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Mr. Simon may be contacted at
nate@simonlawky.com