Contract Interpretation – Determining What the Contract Requires
March 24, 2026 —
David Adelstein - Florida Construction Legal UpdatesA good ole dispute on contract interpretation in government contracting. Contract interpretation disputes happen all the time in every jurisdiction under the sun. Think about that. Now, what’s the best way to avoid a contract interpretation dispute? Naturally, invest in the contract language and fully understand the scope of work. Make all of this clear. But, of course, this isn’t foolproof meaning you could still be doing this and you could still find yourself in a contract interpretation dispute. Although, if you are doing this, and being proactive, the contract interpretation disputes should be minimal and more streamlined.
In Liberty Technical Services, LLC v. Department of Veterans Affairs, CBCA 8385, 2026 WL 407656 (CBCA 2026), the dispute centered on whether the government owed the contractor for certain, necessary equipment (largely controllers, but also tanks and pumps) not specified in the contract. The government countered that this should be a non-issue because the contractor always acknowledged it was responsible for furnishing the unspecified, necessary equipment, and the contractor did actually provide the equipment without direction from the government. Each party claimed the contract was unambiguous when construed in context.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Document Everything! Always! No Exceptions! (AKA, Help Your Lawyer Help You!)
April 14, 2026 —
Melissa Dewey Brumback - Construction Law in North CarolinaI had a case last year in which once again I found myself thinking: if only my client had better documented the verbal agreements, we would have had a much easier time defending his work.
I know this is often easier said than done— you are in the middle of building a project, and you get a call, and you need to keep the project moving. No time for written change directives or a special bulletin. And yet—it is simply amazing to me the number of people who develop “litigation amnesia” about things when a lawsuit is involved.
Your documentation system does not need to be perfect. You can use a simple Field notebook and handwritten notations. A text memo to yourself or, better yet, an email confirmation to the owner/contractor/whoever.
Read the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Congratulations to BWB&O’s 2027 Southern California Super Lawyers and Rising Stars Honorees!
September 08, 2026 —
Bremer Whyte Brown & O'Meara, LLPBremer Whyte Brown & O’Meara, LLP is proud to announce that Partners
Nicole Whyte,
Keith Bremer,
John Toohey, and
Tyler Offenhauser have been named to the 2027 Southern California Super Lawyers list. Notably, Nicole Whyte was also selected to the Top 50 Orange County Super Lawyers list, an honor reflecting her outstanding work, leadership, and impact in the legal community.
Associates
Kevin Moore,
Sukayna Jaidi, and
Andrew Mathews are also being recognized as 2027 Southern California Super Lawyers Rising Stars.
Our team is being honored for their distinguished service and dedication in Family Law, Civil, Business, Construction, and Personal Injury Litigation.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara, LLP
Snell & Wilmer Recognized Among the Top 10 Largest Law Firms in Orange County by the Orange County Business Journal for the Ninth Consecutive Year
April 27, 2026 —
Snell & WilmerORANGE COUNTY – Snell & Wilmer is pleased to announce that its Orange County office has been named the eighth largest law firm in Orange County on the Orange County Business Journal’s
2026 List of Law Firms. The office has been ranked among the top 10 largest law firms in the region by the Orange County Business Journal for nine consecutive years.
“We are proud to once again be recognized among the top law firms in Orange County,” said
Jonathan E. Frank, managing partner of the firm’s Orange County office. “This recognition is a testament to the outstanding attorneys and professionals in our Orange County office and the clients who trust us with their most important matters. Being ranked among the top 10 largest firms in the region for nine consecutive years reflects both the strength of our team and our deep commitment to serving the Orange County business community.”
Read the full story...Reprinted courtesy of
Snell & Wilmer
Introducing the Updated 2026 Pillsbury Guide to Data Centers
June 08, 2026 —
Gravel2Gavel Team - Gravel2Gavel Construction & Real Estate Law BlogSince the initial publication of the Pillsbury Guide to Data Centers in 2025, the market has continued to evolve—most notably with respect to power availability, energy strategy, tax and incentives planning, and investment activity across the sector. While many of the legal, commercial and regulatory frameworks addressed in the original Guide remain durable and relevant, recent developments warranted targeted updates and additions.
The
2026 edition expands and updates our energy-focused content to reflect the increasingly central role of power procurement, interconnection and long-term energy strategy in data center development. We have incorporated new materials addressing power purchase and interconnection agreements, solar and other renewable energy solutions, advanced reactor designs, and nuclear-powered data centers projects, including an updated project tracker. We have also added new analysis covering state and local tax considerations and incentive structures relevant to data center development and operations, as well as current M&A and private equity trends shaping investment in the sector.
Read the full story...Reprinted courtesy of
Gravel2Gavel Team
PJM’s Reliability Backstop Procurement Proposal—Fast-Track Capacity to Meet Rising Large-Load Demand
May 12, 2026 —
Stephen J. Humes, Alicia M. McKnight, Jason Drogin Atwood & Andrew H. Jacobs - Gravel2GavelIn January, we discussed the Statement of Principles jointly signed by the National Energy Dominance Council and governors across the mid-Atlantic region—framing accelerating demand (especially from large-scale data centers) as an emergency reliability issue for PJM Interconnection, L.L.C. (PJM), the nation’s largest power grid operator. That policy signal is now becoming a near-term, accelerated procurement and contracting exercise. On April 8, 2026, PJM notified stakeholders of a critical issue fast path reliability backstop procurement process. PJM subsequently released a request for information (RFI) with respect to a proposed Reliability Backstop Procurement (RBP)—a one-time mechanism intended to attract significant new capacity to address projected reliability shortfalls driven by large-load growth.
RBP compresses what is often a multiyear market and regulatory conversation into a fast-moving set of commercial choices. Developers, large loads, utilities and capital providers should be preparing now for (i) an accelerated bilateral contracting window and (ii) a standardized PJM-led backstop procurement if bilateral deals do not clear enough capacity.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury,
Jason Drogin Atwood, Pillsbury and
Andrew H. Jacobs, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Atwood may be contacted at jason.atwood@pillsburylaw.com
Mr. Jacobs may be contacted at andrew.jacobs@pillsburylaw.com
Read the full story...
What Massachusetts Contractors and Developers Can Learn from Cannistraro v. Columbia Construction
July 13, 2026 —
Anthony LaPlaca & Luke Marston - The Construction SeytIntroduction
On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.
[1]
Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a “factual and contractual basis for the rejection” and must be “certified as made in good faith.”
[2] In the absence of a timely certified notice, payment is “deemed to be approved” unless the payor properly rejects payment before it comes due.
[3]
Reprinted courtesy of
Anthony LaPlaca, Seyfarth Shaw LLP and
Luke Marston, Seyfarth Shaw LLP
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Mr. Marston may be contacted at lmarston@seyfarth.com
Read the full story...
For Urban Walkers, a Patchy Dilemma: Who Owns the Sidewalk?
July 06, 2026 —
Linda Poon – BloombergIn 2007, New York City’s sanitation department
threatened Natalie Shea with a $300 fine for defacing public property with graffiti. Her crime: drawing a blue flower in front of her family’s Park Slope home with sidewalk chalk. She was six years old.
The incident, which made
local and
national news at the time, captures the fraught role that sidewalks often play in US cities. These patches of pavement do more than carry pedestrians to their destinations: They’re also places for commerce, social interaction and childhood play, from chalking to learning how to ride a bike. Urbanist Jane Jacobs once likened the range of activities that city sidewalks attract to an “intricate ballet.”
In the new book
Sidewalk Nation: The Life and Law of America’s Most Overlooked Resource (Harvard University Press), author Michael Pollack explores the “tangled web of state and local regulation” that governs sidewalks, with cities often passing along responsibilities for tasks like clearing snow and keeping walkways safe. He paints a portrait of the American sidewalk a disorderly and often neglected network, filled with literal and metaphorical cracks that give rise to all sorts of conflict, from mundane clashes over maintenance to more consequential fights over accessibility and inequality.
Read the full story...Reprinted courtesy of
Linda Poon, Bloomberg