We Won’t Permit That Excuse!
June 23, 2026 —
Curt Martin & Richard Eiszner - ConsensusDocsA Texas appellate court recently ruled that a building permit wasn’t a condition precedent for a construction project. That caught our attention. Can you build a commercial project without a permit?
But as we read the case, we see the court’s reasoning. And it reminds us of an important legal principle that should inform our contract drafting and negotiation.
The case was a civil suit brought by the project owner against its tenant improvement contractor for work on a medical spa. The owner claimed that the contractor didn’t perform the work properly and didn’t finish construction. The contractor argued that delays and problems were caused by the owner, alleging numerous failures, including the owner’s failure to secure a building permit.
Reprinted courtesy of
Curt Martin, Peckar & Abramson, P.C. and
Richard Eiszner, Peckar & Abramson, P.C.
Mr. Martin may be contacted at cmartin@pecklaw.com
Mr. Eiszner may be contacted at reiszner@pecklaw.com
Read the full story...
Communication Gaps Can Cost Construction Firms in the Data Center Boom
June 02, 2026 —
Mike Lewis - Construction ExecutiveThe
data center construction boom is transforming the construction industry at a historic pace. Fueled by cloud computing, artificial intelligence and relentless demand for digital infrastructure, data centers have become one of the fastest-growing project types in the built environment. Billions of dollars are flowing into new facilities and expansions, creating unprecedented opportunities for construction firms positioned to deliver reliably.
But opportunity alone does not guarantee success. As competition intensifies, communication failures and poor information management are emerging as some of the most common (and costly) reasons firms lose margins, miss deadlines or fail to secure repeat work. In data center construction, where schedules are compressed and tolerance for error is minimal, even small breakdowns in communication can have outsized consequences.
Reprinted courtesy of
Mike Lewis, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Surety Requiring Collateral Security Under General Agreement of Indemnity
September 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn order to procure bonds (payment and performance bonds), you need to sign a General Agreement of Indemnity (referred to as the “GAI”) with the surety (bonding company). It does not matter the surety issuing the bonds, the terms and conditions in the General Agreement of Indemnity are largely consistent. These terms and conditions are one-sided written in favor of the surety. This is because bonds are not insurance. When a surety issues such bonds, it is doing so under the premise that it will get reimbursed every penny that it incurs relative to its exposure- whether incurred in attorney’s fees, consulting costs, or remediating a default or claim under the applicable bond. The General Agreement of Indemnity is one of the most powerful contracts in construction and is a contract that is not to be taken lightly. It provides the surety numerous rights in the event of a claim.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Beyond the Forecast: Managing Extreme Weather Risks on Construction Sites
November 02, 2026 —
Jordan Graustark - Construction ExecutiveConstruction leaders would never downplay or dismiss a fall, struck-by incident or equipment failure as “just part of the job.” Yet, some temperature-related conditions, such as heat exhaustion, frostbite and hypothermia, are often accepted as unavoidable consequences of working conditions. Temperature-related incidents likely won’t command the same attention as a crane collapse, but understating their seriousness can be a costly mistake. As extreme weather becomes more frequent and unpredictable, that mindset is becoming increasingly difficult to defend.
Extreme weather is not simply a seasonal inconvenience; it’s a serious occupational hazard. Heat waves, cold snaps and rapid temperature swings can contribute to serious injuries and fatalities—or SIFs—productivity losses and costly project disruptions. A single temperature-related incident can quickly become an OSHA recordable and project management challenge. Reduced physical and impaired cognitive performance from heat or cold stress can increase the risk of workplace incidents long before a medical emergency occurs.
Reprinted courtesy of
Jordan Graustark, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Texas Prepares to Restart Data Center Construction, with Around 300 Projects Under Review And 6,608 MW Awaiting Energization Approval, Driving Demand for Rapid-Response Lifting Operations
October 20, 2026 —
SarensTexas is experiencing an unprecedented increase in power demand. The ERCOT (Electric Reliability Council of Texas) power grid reached a record peak demand of 91.1 GW in summer 2026, 6% above the previous record, according to the U.S. Energy Information Administration (EIA). This is compounded by interconnection requests totaling around 474 GW, more than five times the record peak, with approximately 90% of these requests related to data centers, according to the Office of the Governor of Texas. Within this context, authorities have launched a comprehensive review process. In August , the Governor directed the Public Utility Commission of Texas (PUCT) and ERCOT to audit all data centers progressing toward grid connection, covering around 300 projects. ERCOT has also suspended approvals to energize data centers of 75 MW or more and has set December 10 as the date for the publication of its reports.
For the industry, this pause creates a valuable planning window. Goldman Sachs notes that it takes 18 to 24 months to build a data center once permits have been secured, while only 50% to 60% of planned capacity is delivered on schedule. Supply chain constraints and labor shortages are among the most common causes of delays. In this context, construction agility is becoming increasingly critical. A one-month delay at a typical 60 MW U.S. data center is estimated to cost up to $14.2 million in lost revenue, additional costs and penalties, according to STL Partners data. Against this backdrop, Sarens, which has operated in the U.S. since 2009 and is headquartered in Houston, with offices also in Odessa and Beaumont, positions as a logistics partner for developers and contractors preparing for the execution phase.
Read the full story...Reprinted courtesy of
Sarens
Global Insights Center: Monthly Newsletter
June 15, 2026 —
Global Insights Center Staff - The HartfordMay in Review
Last month, inflation moved higher, with Consumer Price Index (CPI) inflation rising to 3.8% year over year, up from 3.3% the prior month. The increase was driven primarily by energy prices, particularly gasoline, reflecting ongoing disruptions tied to the Middle East conflict.
Labor market data were broadly stable. The unemployment rate remained unchanged at 4.3%, wage growth increased modestly to 3.6%, while job growth continued to be geographically concentrated in the Southern states, particularly cities in Texas. On an occupational basis, healthcare once again led job gains, especially in home health services, a trend we have consistently highlighted. Business formations increased during the month, with notable strength in e commerce and digital services firms. Manufacturing activity also improved, particularly in semiconductors, IT equipment, and natural gas–related energy infrastructure.
Read the full story...Reprinted courtesy of
Global Insights Center Staff, The Hartford
New York Climate Superfund Rulings Put Vermont Law in Focus
October 20, 2026 —
Amanda G. Halter, Ashleigh K. Myers, Jillian Marullo & Marcus Manca - PillsburyA second federal judge has struck down New York’s
Climate Change Superfund Act and barred its enforcement. On September 23, 2026, Judge P. Kevin Castel of the U.S. District Court for the Southern District of New York issued a
decision granting summary judgment to the United States and the U.S. Environmental Protection Agency (EPA), declaring the Act unconstitutional, and permanently enjoining New York officials from enforcing it in United States v. New York, No. 1:25-cv-03656 (S.D.N.Y. Sept. 23, 2026).
Judge Castel’s decision closely tracks the Northern District of New York’s August 31
decision in West Virginia v. James, Case No. 1:25-cv-00168 (N.D.N.Y. Aug. 31, 2026). Both courts held that the Clean Air Act (CAA) preempts New York’s effort to impose strict liability through a climate attribution and cost recovery framework based on interstate greenhouse gas (GHG) emissions. Both also held that the foreign affairs doctrine preempts the Act as applied to fossil fuel activity outside the United States. On September 24, the Northern District entered Rule 54(b) judgment implementing its August 31 decision, enjoining Attorney General Letitia James and DEC Commissioner Amanda Lefton from implementing or enforcing the Act and permitting an immediate appeal of the preemption claims.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury,
Jillian Marullo, Pillsbury and
Marcus Manca, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Mr. Manca may be contacted at marcus.manca@pillsburylaw.com
Read the full story...
Building the Research and Healthcare Facilities of Tomorrow Without Impacting the Progress of Today
August 16, 2026 —
Jason Tobias - Construction ExecutiveResearch labs run experiments that can’t be paused. Hospitals treat patients around the clock. Yet these same facilities constantly need upgrades—new infrastructure, modernized systems, renovated spaces—to meet the demands of twenty-first century science and medicine. The challenge for construction teams isn’t just building. It’s building without ever turning the lights off.
This unique dynamic creates an environment where construction activities are happening adjacent to sensitive testing and treatment, a complex setting where disruptions can have serious consequences.
Skanska continues to successfully navigate these challenges across multiple sectors, including from occupied lab space at the
North Carolina Department of Environmental Quality’s (NCDEQ) Reedy Creek Laboratory in Raleigh to hospital corridors alongside staff and patients in various hospital locations across the country.
Reprinted courtesy of
Jason Tobias, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...