Delay Matters: Florida’s Fourth DCA Reverses Hurricane Irma Dismissal
June 08, 2026 —
Andrea DeField, Machaella Reisman & Cary D. Steklof - Hunton Insurance Recovery BlogThe mantra “delay, deny, defend” is frequently referenced in discussions of insurance claims handling, though insurers will invariably disavow these tactics. While it would be facially improper for an insurer to delay a coverage decision to gain a tactical advantage, empirical examples nonetheless exist. This very dynamic was addressed by Florida’s Fourth District Court of Appeals when it handed policyholders a win in
Hypoluxo Mariner’s Cay Condo. Assoc’n, Inc. v. Underwriters at Lloyd’s London, No. 4D2024‑2250 (Fla. 4th DCA Apr. 1, 2026), reversing a trial court order dismissing a condominium association’s Hurricane Irma coverage lawsuit against its property insurer.
Delay to Run the Statute of Limitations
Following Hurricane Irma, a condominium association suffered roof and exterior envelope damage, reported an insurance claim, and submitted a sworn proof of loss to its property insurer in compliance with Florida Statute § 627.70132 (2020). The statute establishes a timeframe within which a policyholder must submit a claim for hurricane damage.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth LLP,
Machaella Reisman, Hunton Andrews Kurth LLP and
Cary D. Steklof, Hunton Andrews Kurth LLP
Ms. DeField may be contacted at adefield@hunton.com
Ms. Reisman may be contacted at reismanm@hunton.com
Mr. Steklof may be contacted at csteklof@hunton.com
Read the full story...
Louisiana Legislature Enacts Act 932 – Significant Changes to Insurer Bad-Faith Exposure for Failure to Settle
July 13, 2026 —
Tabitha R. Durbin & Jennifer E. Michel - Lewis BrisboisThe Louisiana Legislature has enacted Act 932 (formerly House Bill 1162), which became law this week without the Governor's signature pursuant to the Louisiana Constitution, after expiration of the applicable constitutional review period. Act 932 makes several important amendments to Louisiana's insurer bad-faith statute and appears intended, at least in part, to address issues arising from the Louisiana Supreme Court's decision in Kelly v. State Farm Fire & Casualty Co., 169 So.3d 328 (La. 2015). The Act also makes changes regarding claim payments involving licensed contractors. The Act takes effect on August 1, 2026.
Key Takeaways
Act 932:
- Limits certain bad-faith causes of action (bad faith failure to settle) involving personal injury and bodily injury claims where good-faith disputes exist or where an insurer has not been afforded sufficient opportunity to respond to a settlement demand.
- Requires insurers and adjusters to verify a contractor's Louisiana license status before issuing claim payments when a contractor is named as a payee on a check for repair or restoration of immovable property.
- Creates a statutory safe harbor protecting insurers from bad-faith penalties and attorney fees when payment delays result from an inability to verify a contractor's license, provided specified documentation and notice requirements are met.
Reprinted courtesy of
Tabitha R. Durbin, Lewis Brisbois and
Jennifer E. Michel, Lewis Brisbois
Ms. Durbin may be contacted at Tabitha.Durbin@lewisbrisbois.com
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Read the full story...
Seattle Team Obtains Summary Judgment in Real Estate Broker Professional Liability Action
July 20, 2026 —
Lewis BrisboisSeattle Partner Kathleen A. Nelson and Associate Synova M. L. Edwards prevailed on a hotly contested motion for summary judgment in Whatcom County, Washington court in a real estate broker professional liability action.
The plaintiff filed an action against Lewis Brisbois' clients, a real estate agent and brokerage firm, among several others, including the title company, purchasers and others related to the sale of real property following his complicated and long running divorce action. These claims primarily arose out of the clients’ reliance on an order signed by the court in the underlying divorce action. The order allowed the clients to execute the purchase and sale agreement, as the plaintiff was non-cooperative.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Utah’s Emerging Framework for Responsible Data Center Development
September 08, 2026 —
Denise A. Dragoo & Josh Miller - Snell & WilmerUtah is establishing itself as one of the nation’s most attractive jurisdictions for large-scale data center development, with a structured, defensible regulatory pathway that gives developers and investors the clarity needed to deploy capital at scale. The cornerstone is Executive Order 2026-03, “Establishing a Higher Bar for Data Center Development in Utah,” signed by Governor Spencer J. Cox on May 29, 2026.
The Executive Order creates an actionable compliance framework letting developers demonstrate stewardship across water, air quality, energy, wildlife, and community engagement – reducing regulatory and reputational risk. Recent enactments on energy self-supply and water rights operationalize these principles, while a few counties have adopted short-term local moratoria to update zoning; understanding how these interact with the state framework matters for site selection.
Reprinted courtesy of
Denise A. Dragoo, Snell & Wilmer and
Josh Miller, Snell & Wilmer
Ms. Dragoo may be contacted at ddragoo@swlaw.com
Mr. Miller may be contacted at jmiller@swlaw.com
Read the full story...
Pursuing Claims for Loss Caused by Recent Kona Low Storms for Homeowners and Businesses
May 12, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe recent Kona Low storms that hit all islands were devastating, causing significant property damage. Homeowners and businesses will be seeking coverage under their insurance policies to recover for their losses. Here is a brief look at what may be covered and which exclusions may be troublesome in homeowners’ and commercial property policies.
Typically, both a homeowners’ policy and a commercial property policy include a grant of coverage for “direct physical loss of or damage to Covered Property.” Covered perils are listed, including such events as fire, lightning, or windstorm. Covered Property includes dwellings, other structures on the property and personal property. Additional coverages are usually provided. This includes debris removal after a peril insured against or collapse of a structure. In a homeowners’ policy, additional living expenses are likely covered when the damaged home is not fit to live in.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
How Engineers Will Determine Why NYC's Pfizer HQ Conversion Buckled
July 13, 2026 —
Bryan Gottlieb - Engineering News-RecordConstruction crews have stabilized the former Pfizer headquarters redevelopment in Midtown Manhattan after two load-bearing structural columns buckled on the 21st floor July 7.
The focus has now shifted from emergency response to determining what caused the office-to-residential conversion to suffer a major structural failure.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
Did You Know: Unique Legal Considerations for Animal Care Facilities
August 24, 2026 —
Hannah Skidmore - Construction ExecutiveAnimal care facilities are highly specialized environments that require expertise far beyond traditional commercial or even standard medical construction. Whether designing and building animal shelters, doggy daycares, veterinary clinics or full-service animal hospitals, these facilities operate under conditions that introduce unique challenges related to sanitation, durability, animal behavior and operational workflows.
Because of these complexities, projects that fail to account for animal care requirements adequately often encounter costly issues—many of which result in litigation. Below are real-world examples drawn from expert witness work, followed by proactive best practices construction professionals should apply to future animal care projects.
Reprinted courtesy of
Hannah Skidmore, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Insufficient Notice of Commencement and Construction Lien Rights
August 03, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice to Owner company will typically rely on the Notice of Commencement to serve Notices to Owners from lower tiers not in contract with the owner. However, when it comes to preparing the lien, a lienor should look beyond just the Notice of Commencement and also look to the property appraiser’s website as a backstop.
In a recent case, a window company had the homeowner sign the Notice of Commencement and then filled in the information. The company naturally did this for the convenience of the homeowner that probably was unfamiliar with the Notice of Commencement process. Regardless, information in the Notice of Commencement was inaccurate. It failed to include all the real property owners. Thus, when a payment dispute arose and a construction lien was prepared, it did not identify all of the real property owners. All of the real property owners were added later during the pendency of a lien foreclosure lawsuit. The trial court denied the lien because of the defective / insufficient Notice of Commencement — the lienor assumed the risk of error by filling out the information in the Notice of Commencement. The trial court further denied the lien holding that because the work did not commence within 90 days of the Notice of Commencement, the Notice of Commencement is void.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at