Inaccurate Representations Can Lead to Differing Site Conditions Claim
May 26, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn the
prior posting, I discussed a case dealing with a differing site condition. In that case, the owner did not have an affirmative duty to make a representation and there was no inaccurate representation made by the owner that misled the contractor.
Well, what about when there is an inaccurate misrepresentation regarding the site? This was the circumstance in an older Florida case where a dredging contractor had a successful differing site conditions claim. See Jacksonville Port Authority v. Parkhill-Goodloe, Co., Inc., 362 So.2d 1009 (Fla. 1st DCA 1978).
The government provided inaccurate information as to the lack of rock that would be encountered during the dredging that was relied on by the dredging contractor. But the government had â
superior knowledgeâ that there was rock in an adjacent location based on a prior claim from a contractor, yet the government did not disclose the possibility that rock could be encountered.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Wilke Fleury Attorneys Recognized by 2026 Northern California Super Lawyers and Rising Stars!
July 20, 2026 —
Wilke FleuryWilke Fleury is pleased to announce that 18 of the firmâs attorneys have been selected for inclusion on the 2026 Northern California Super Lawyers and Rising Stars lists.
The annual Super Lawyers and Rising Stars selections recognize attorneys across a wide range of practice areas. This yearâs honorees reflect the depth of Wilke Fleuryâs litigation, business, healthcare, employment, bankruptcy, appellate, real estate, construction, and estate planning practices.
Read the full story...Reprinted courtesy of
Wilke Fleury
Predict Risk, Not Incidents: A New Analytics Framework for Your Construction Safety Data
August 03, 2026 —
Tabrez Zahoor - Construction ExecutiveBehind every âzero-incidentsâ company report, hidden hazards may already be accumulatingâ
risks that could become serious injuries tomorrow. The question every executive should be asking is not, âDid anything go wrong last month?â It is: âWhere is risk building on my projects right now?â
Most construction organizations cannot answer that question. Not because the data does not existâit does. Every active project generates daily inspection findings, labor records, near-miss reports and audit results. The problem is that standard safety systems collect this data and then report it in ways that make it operationally useless for prevention. They describe the past. They predict nothing.
The predictive safety analytics framework (PSAF) is a practical, deployable system developed from years of applying data science to large-scale construction portfolio operations that takes the safety data construction organizations already collect and transforms it into a forward-looking risk signal. The result? A single weekly score that tells executives where risk is concentrating across their portfolio before anyone gets hurt.
Reprinted courtesy of
Tabrez Zahoor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Introducing the Updated 2026 Pillsbury Guide to Data Centers
June 08, 2026 —
Gravel2Gavel Team - Gravel2Gavel Construction & Real Estate Law BlogSince the initial publication of the Pillsbury Guide to Data Centers in 2025, the market has continued to evolveâmost notably with respect to power availability, energy strategy, tax and incentives planning, and investment activity across the sector. While many of the legal, commercial and regulatory frameworks addressed in the original Guide remain durable and relevant, recent developments warranted targeted updates and additions.
The
2026 edition expands and updates our energy-focused content to reflect the increasingly central role of power procurement, interconnection and long-term energy strategy in data center development. We have incorporated new materials addressing power purchase and interconnection agreements, solar and other renewable energy solutions, advanced reactor designs, and nuclear-powered data centers projects, including an updated project tracker. We have also added new analysis covering state and local tax considerations and incentive structures relevant to data center development and operations, as well as current M&A and private equity trends shaping investment in the sector.
Read the full story...Reprinted courtesy of
Gravel2Gavel Team
Presumption of Prejudice Applies to All Affirmative Defenses Regarding Insuredâs Failure to Comply with Post-Loss Policy Conditions
June 23, 2026 —
David Adelstein - Florida Construction Legal Updatesn a recent property insurance coverage dispute, an issue on appeal pertained to the âprejudiceâ jury instruction associated with the insuredâs failure to comply with post-loss policy conditions. The trial court found that the prejudice only pertained to prompt notice and not other post-loss policy conditions. This was reversed on appeal as prejudice applied to ALL the post loss policy conditions that the insured failed to comply with, not just the prompt notice requirement. The prejudice presumption applies to all affirmative defenses regarding an insuredâs failure to comply with post-loss policy conditions.
Consider this discussion when dealing with an insurer raising prejudice as an affirmative defense to do an insuredâs failure to comply with post-loss policy conditions, and the associated burdens of proof:
On appeal, [the insurer] contends the trial court erred by instructing the jury that the presumption of prejudice was inapplicable to all of its post-loss obligation defenses except prompt notice. We agree.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
DOI Finalizes Long-Awaited Modernization of Type A Natural Resource Damage Assessment Regulations
August 03, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogFor nearly three decades, the U.S. Department of the Interiorâs (DOI) simplified âType Aâ Natural Resource Damage Assessment (NRDA) regulations were available more in theory than in practice, constrained by dated models, narrow geographic applicability and a $100,000 cap that rarely matched the economics of modern environmental claims. DOI has now finalized revisions to the Type A natural resource damages assessment procedures under 43 C.F.R. Part 11 for hazardous substance releases under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Clean Water Act (CWA), with the final rule published in the
Federal Register on July 13, 2026 and scheduled to become effective August 12, 2026.
As discussed
previously, DOI has sought to modernize what it views as an âinefficient and inflexibleâ process and restore the Type A procedure to its intended role as a more streamlined pathway for smaller, less contentious NRD claims. The final rule adopts a $5 million default damages threshold, allows use above that amount if all parties agree, clarifies that Type A may be used in all environments and for all natural resource types, and removes legacy model appendices that had tethered the process to outdated formulas.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
Location, Location, Location â But Which One? The Few Words in Your Construction Contract that Pick Where You Fight
June 29, 2026 —
Brad Sands - ConsensusDocsMost professionals know the old real estate line: location, location, location. It turns out to be just as true for construction contracts as it is for property.
Consider a recent case involving a project owner that hired two design firms for a project. When issues arose during construction, the owner sued the design firms in state court in Brazoria County, Texas, pursuant to the forum selection clause in the partiesâ contracts. The defendants then removed the case to the federal district court in Galveston, a courthouse in a different county. But the owner wanted the case back in Brazoria County state court. Whether it got its wish came down to two words in the contract: âsituated in.â This article is about words like those.
A construction contractâs forum selection clause names the place for the fight nobody plans to have, and where that fight happens can shape how it goes. This article explains why the wording in your forum selection clause deserves careful reading before you sign a construction contract. It is not a deep dive into the mechanics of federal removal jurisdiction, and it is not an academic comparison of the terms âforumâ and âvenue.â Instead, it is a practical look at how courts actually read these clauses, so the location of a future fight is the one you intended.
Read the full story...Reprinted courtesy of
Brad Sands, Jones Walker, LLPMr. Sands may be contacted at
bsands@joneswalker.com
Voluntary Dismissal of an Indemnity Claim Does Not Make the Subcontractor a âPrevailing Party,â Washington Court of Appeals Holds
September 21, 2026 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIn
King County v. Walsh Construction Company II, LLC, No. 86503-0-I (Wash. Ct. App. Aug. 4, 2025), an unpublished decision from Division I of the Washington Court of Appeals, the Court affirmed the denial of a subcontractorâs request for prevailing-party attorney fees under an indemnity clause after the general contractor voluntarily dismissed its indemnity claims. Because the indemnity claim was no longer live and no determination of fault had occurred, the Court held that the trial court did not err in denying the request. ACS represented Walsh, the general contractor, in securing the denial of the fee request at the trial court that the Court of Appeals affirmed.
A Pass-Through Indemnity Claim That Ended Before Fault Was Decided
The dispute arose out of a public works contract under which King County hired Walsh Construction Company II, LLC (âWalshâ) to construct and install a conveyance pipeline. After the pipeline broke, King County sued Walsh for breach of contract and warranty, expressly identifying both Walsh and its subcontractor, Mears Group Inc., (âMearsâ) as responsible. Walsh tendered defense and indemnity to Mears under the subcontract.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com