Owner Taking Assignment of General Contractorâs Claims Against a Subcontractor(s)
September 21, 2026 —
David Adelstein - Florida Construction Legal UpdatesHereâs a scenario that occurs in construction defect cases. An owner sues a general contractor and subs for construction defects. The owner settles with a number of parties and takes an assignment of the general contractorâs claims against some or all of the subs and pursues the remaining parties for indemnity based on the assignment of the general contractorâs claims.
This was the scenario in Craftsman Plastering and Lath, Inc. v. Rath Mor, LLC, 2026 WL 2328032 (Fla. 4th DCA 2026). The owner settled with the general contractor and all subs except one. The owner took an assignment of the general contractorâs claim against the sub, and really the indemnity claim. The owner was then substituted as the real party in interest as it relates to the general contractorâs claims against the sub. The owner sought roughly $780,000 in attorneyâs fees and costs in connection with the dispute claiming the sub was liable for such fees. The jury didnât buy the argument and awarded the owner about $55,000. Basically, the jury seemingly prorated the fees by the number of parties, at least, thatâs how the math worked out. The owner didnât like that and moved for an additur to increase the juryâs verdict which the trial court granted. This was reversed on appeal despite the fact that a trial court has broad discretion to grant a motion for additur.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Sausage-Making Often Relies on the Good Sense of the Chef Rather than the Recipe
June 23, 2026 —
Garret D. Murai - California Construction Law BlogEven for lawyers, the rules governing litigation can get complex and convoluted. Does something need to be filed? What needs to be filed? When is the deadline for filing?
Simple questions with not always with straightforward answers.
This was the case in
R & J Sheet Metal, Inc. v. W.E. OâNeil Construction Co. of California, 111 Cal.App.5th 878 (2025), which involved sheet metal panels lost when they fell into the Port of Long Beach harbor.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
At the Frontier of Change: Howâor Whereâto Rebuild as Alaska's Permafrost Disappears
September 28, 2026 —
Pam McFarland - Engineering News-RecordIn some areas of the tiny subsistence coastal village of Kwigillingok along the Bering Sea in western Alaska, pockets of ground feel squishy, almost gelatinous, rather than solid. Itâs an odd sensation, as if there is only a thin layer of muddy soil preventing people from falling into the water beneath their feet.
Read the full story...Reprinted courtesy of
Pam McFarland, Engineering News-RecordMs. McFarland may be contacted at
mcfarlandp@enr.com
Wisconsin Supreme Court Finds Coverage Under Ensuing Loss Provisions
September 29, 2026 —
Tred R. Eyerly - Insurance Law HawaiiReversing the trial courtâs grant of summary judgment to the insurer, the Wisconsin Supreme Court determined that genuine issues of material fact existed on whether ensuing losses as defined in the policy were covered. Cincinnati Ins. Co. v. Ropicky, 2026 Wisc. LEXIS 302 (Wis. July 7, 2026).
The insured suffered damage during a storm on May 11, 2018, when rainwater poured into the home. The insureds gave notice to their insurer, Cincinnati. Upon inspection, Cincinnati determined that water intrusion resulted from multiple construction defects in the home. In the front of the home, water entered through a gap in the stone veneer. The inspector also concluded that the damage from rainwater was not just from the May 11, 2018, storm, but damage had occurred from prior storm events.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ball Janik LLP Strengthens Miami Construction Defect Team with Litigator Nicolas Aixala
October 26, 2026 —
Ball Janik LLPMIAMI, FL, October 22, 2026 â
Ball Janik LLP has added Nicolas Aixala to its Construction Defect Practice Group as an associate in the firm's Miami office. Aixala brings experience in construction and civil litigation, along with a perspective many litigators don't have: a view from the public side of development, gained researching land use and zoning matters for the City of Miami.
"Construction disputes in South Florida rarely stay inside the four walls of a building. Zoning, permitting, and local regulation are often part of the story," said James C. Prichard, Managing Partner of Ball Janik LLP. "Nicolas has seen that landscape from the city's side of the table, and he pairs it with solid litigation training. That combination helps us quickly size up the development and regulatory issues our clients face. We're glad to have him on our Miami team."
Before joining Ball Janik, Aixala clerked at Miami-area law firms, supporting attorneys in construction litigation and a range of civil matters through legal research, motion practice, discovery, deposition preparation, and trial preparation. He also interned with the City of Miami, assisting with legal research and opinions on land use and zoning matters, including the City of Miami Zoning Code, known as Miami 21. That work gave him a close look at how local policy shapes development, and how it affects the neighborhoods and property owners who live with the results.
"A building is one of the biggest investments a property owner will ever make, and when construction goes wrong, they need advocates who understand both the courtroom and the local landscape," said Aixala. "Ball Janik handles complex construction litigation with a practical, client-focused approach. I'm excited to bring my litigation experience and local knowledge to this team and to the property owners it serves across South Florida."
Aixala earned his J.D. from the University of Miami School of Law, where he was a member of the Yvette Ostolaza Mock Trial Team and the Cuban American Bar Association. He received his B.S. in Business Administration from the University of Central Florida, with a minor in Legal Studies and a certificate in Entrepreneurship.
About Ball Janik LLP
Ball Janik LLP is a Florida-based law firm offering construction defect, construction law, insurance recovery, and commercial litigation counsel, to its local and national clients. The firm was founded in 1982 and has expanded its capabilities, professionals, and geographic footprint. What started as a small firm focused on real property, land use, and litigation (known then as Ball Janik & Novack) has grown to a team of 70-plus attorneys and paralegals in five offices in Florida, with centuries of combined experience and capabilities. The firm has been recognized by Chambers USA, including for its construction law capabilities in Florida, U.S. News & World Report and Best LawyersŸ, The Best Lawyers in America©, Super Lawyers, and Corporate International. Read more at
www.balljanik.com.
Court Finds Potential Conflicts In Denying Insurerâs Motion to Dismiss Claim for Independent Counsel
October 12, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe District Court denied the insurerâs motion to dismiss the additional insuredâs claim that the appointment of independent counsel was required. S. Cal. Edison Co. v. Travelers Prop. Cas. Co of Am., 2025 U.S. DIst. LEXIS 148495 (C.D Calif. July 15, 2025).
Southern California Edison Company (SCE) entered a Master Services Agreement with its contractor, SASCO whereby SASCO agreed to provide services concerning electrical pole repair and replacement. SASCO was required to obtain primary and excess general liability policies and to name SCE as an additional insured. SASCO obtained such policies from Travelers, naming SCE as an additional insured. The policies limited coverage for SCE to covered damages arising from SASCOâs work.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Building the Research and Healthcare Facilities of Tomorrow Without Impacting the Progress of Today
August 16, 2026 —
Jason Tobias - Construction ExecutiveResearch labs run experiments that canât be paused. Hospitals treat patients around the clock. Yet these same facilities constantly need upgradesânew infrastructure, modernized systems, renovated spacesâto meet the demands of twenty-first century science and medicine. The challenge for construction teams isnât just building. Itâs building without ever turning the lights off.
This unique dynamic creates an environment where construction activities are happening adjacent to sensitive testing and treatment, a complex setting where disruptions can have serious consequences.
Skanska continues to successfully navigate these challenges across multiple sectors, including from occupied lab space at the
North Carolina Department of Environmental Qualityâs (NCDEQ) Reedy Creek Laboratory in Raleigh to hospital corridors alongside staff and patients in various hospital locations across the country.
Reprinted courtesy of
Jason Tobias, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
One Year In: A Look at the Initial Impacts of LEED v5 on the Built Environment
October 20, 2026 —
Eric Haggstrom - Construction ExecutiveAs federal
climate policies shift, the built environment has entered a period of uncertainty where developers, designers and owners need to find pragmatic, forward-looking approaches to sustainability. A year after its launch on April 28, 2025,
LEED v5 is helping lead that charge by pushing the industry toward a stronger long-term focus on carbon reduction, climate resilience and building performance. The framework of this certification provides a snapshot of the current state of the industry and an indication of where it may be headed in the future.
LEED v5âs introduction has helped to begin reframing and informing the approaches of both mission-driven and cost-conscious clients, providing a framework to align their decisions more closely with sustainable priorities by emphasizing carbon reduction, energy efficiency and electrification. These standards can help teams make investments strategically by phasing in upgrades, planning for future technologies and demonstrating how the rating system is influencing long-term decision-making across projects.
Reprinted courtesy of
Eric Haggstrom, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...