Doctrine of Substantial Performance When It Comes to Payment
July 27, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent non-construction case touches upon the doctrine of substantial performance when it comes to payment. In this case, a club was to make two payments to secure a rapperâs attendance. The first payment was made. The second payment was made but was a few hundred dollars short of the agreed amount. The rapper did not show up. The club claimed it substantially performed its obligations. At first glance, the argument makes sense because the second payment fell only a few hundred dollars short. But that wasnât the case when it comes to pre-commencement payment obligations:
Substantial performance applies only when the variance from the contract terms âis inadvertent or unintentional and unimportant so that the work actually performed is substantially what was called for in the contract.â However, when one party agrees to pay the other on or before a specific date, time is of the essence, and the payor is required to pay the payee on or before that date. âThere is almost always no such thing as âsubstantial performanceâ of payment between commercial parties when the duty is simply the general one to pay. Payment is either made in the amount and on the date due, or it is not.â
Big Gate Records, LLC v. Washington, 51 Fla.L.Weekly D1281a (Fla. 2nd DCA 2026) (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Could Your Project-Level AI Prompt Become the Other Sideâs Smoking Gun?
October 20, 2026 —
Ryan Glass - ConsensusDocsA dispute is brewing on the project. Wanting a quick assessment, the project manager opens ChatGPT, Claude, or another generative artificial intelligence (âAIâ) platform. The project manager types the dispute background into the prompt, including concerns, explanations, and a frank discussion of what may have gone wrong on the contractor-side. The AI response identifies potential weaknesses in the contractorâs position, including possible failures to meet contractual obligations. Unhappy with the answer, the project manager starts a new chat, revises the prompt, and tries again. If the dispute escalates to arbitration or litigation, can the owner force the contractor to provide these prompts and the resulting responses?
Frustratingly, the answer is: it depends. Courts have reached different conclusions. For now, the safest course is to involve your counsel before using AI to evaluate a demand letter, default notice, or threatened lawsuit, or before using AI to draft dispute-related emails, claim letters, or other communications that contain project-specific facts. Otherwise, what feels like a private conversation may later become key evidence for the opposing party.
Read the full story...Reprinted courtesy of
Ryan Glass, Jones Walker LLCMr. Glass may be contacted at
rglass@joneswalker.com
Ahlers Cressman & Sleight leads in recognized Construction Litigation Attorneys
September 01, 2026 —
Ahlers Cressman & Sleight PLLCAhlers Cressman & Sleight is pleased to announce its leading recognition in the 2026 Washington Super Lawyers magazine. With ten members named, ACS has more recognized Construction Litigation attorneys than any other firm on the 2026 Washington Super Lawyers list, compared to three at the next closest firm. Two ACS members were also recognized on the 2026 Washington Rising Stars list.
Super Lawyers selects these recognized lawyers by using a patented multiphase selection process. First, lawyers enter the candidate pool by being nominated by their peers or by being identified by managing partner surveys, third-party feedback, or the Super Lawyersresearch team. Next, Super Lawyersconducts an independently researched evaluation using twelve indicators of professional achievement and peer recognition: verdicts/settlements, transactions, representative clients, experience, honors/awards, special licenses/certifications, position within a law firm, bar and/or professional activity, pro bono and community service, scholarly lectures/writings, education/employment background, and other outstanding achievements. Then, candidates with the highest point totals serve on a Blue Ribbon panel, evaluating other candidates within their primary practice area. Finally, only 5% of attorneys are selected for the Super Lawyers list, and 2.5% of attorneys are selected for the Rising Stars list. More information about the Super Lawyers Selection Process can be found
here.
Read the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about âlicense to operateâ for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of âlicense to operateâ more literallyânamely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, âIf you can make it there, you can make it anywhere.â) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regimeâin our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...
The Grenfell & Champlain Towers: Risk Management Considerations in the Wake of Catastrophic Loss â A UK/US Comparison
June 02, 2026 —
Eric M. Clarkson - Saxe Doernberger & Vita, P.C.1. Introduction
As part of the multinational collaborative relationship between Saxe Doernberger & Vita, P.C. and Fenchurch Law, we continually find ourselves in conversations about the sometimes subtle but sometimes drastic differences between risk management and coverage considerations from one country to the next. These differences are often highlighted by the fallout from large catastrophic losses that are widely publicized and illuminate sometimes widespread risks and perils that many others may be facing in the coming years.
The response of governments and their subdivisions to the needs of victims and/or commercial parties, and insurance marketsâ evaluation of and reactions to catastrophic losses vary widely from country to country and jurisdiction. In this article, we discuss these responses and reactions in the cases of the Grenfell Tower Fire in London, England, and the Champlain Tower collapse in Surfside, Florida, within the United States. These two widely publicized losses involved different risk management and insurance considerations based on where they occurred. They also saw substantially different government responses and raised varied questions about what the next steps are for their respective commercial and insurance markets.
Read the full story...Reprinted courtesy of
Eric M. Clarkson, Saxe Doernberger & Vita, P.C.Mr. Clarkson may be contacted at
EClarkson@sdvlaw.com
Colorado Is Pricing Itself Out of Prosperity: Housing Affordability, Government Policy, and the Cost of Building
November 16, 2026 —
David McLain - Colorado Construction Litigation BlogColorado built its reputation on opportunity. For decades, the state attracted families, workers, entrepreneurs, and employers who saw a place to build a future. Its mountains and quality of life remain extraordinary, but the economics of living here have changed. Increasingly, the question is not whether people want to live in Colorado. It is whether they can afford to do so.
Housing is at the center of that question. Building homes is difficult even under favorable conditions. Interest rates, material prices, labor availability, and financing costs are formidable obstacles that state and local governments cannot simply decree away. Yet governments do influence other costs, including development fees, land-use restrictions, permitting delays, and construction defect liability. When public policy adds cost and uncertainty to an already difficult business, the result can be fewer projects, fewer attainable homes, and diminished economic competitiveness.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
The Architects Who Dream of a New Stone Age
October 26, 2026 —
Jennifer Hahn â BloombergMost of the worldâs longest-standing buildings have one thing in common: They are made from stone. Still, youâd be hard-pressed to find this civilization-outlasting material as a structural element in modern construction. Many stone buildings are imposters: thin veneers of limestone or granite disguising concrete and steel skeletons.
In its day job as Earthâs crust, stone is currently holding up entire cities, countries and continents. But itâs rarely used to its full potential as a load-bearing material that can be stronger than concrete.
Read the full story...Reprinted courtesy of
Jennifer Hahn, Bloomberg
The Firm Turns 16!
July 20, 2026 —
Christopher G. Hill - Construction Law MusingsI have always found it appropriate that my jump to solo practice and Independence Day are so close in time. Today marks the 16th anniversary of
my first day as a solo practitioner of construction law at
The Law Office of Christopher G. Hill, PC. Time sure has flown by thanks to the great clients and friends who followed me to solo practice and whom I have met since the firmâs founding on July 1, 2010. I also could not have made the transition and had the fun and success I have enjoyed over the past 16 years without the support of the best wife and family that any construction lawyer could want.
Since the firmâs last anniversary, my youngest child (who was 7 when this journey began!) has graduated from N. C. State University with a fisheries and wildlife biology degree and is currently in Casper, Wyoming working for
Wyoming Game & Fish, my second oldest is an assistant director of admissions at
Appalachian State University in Boone, NC, and has celebrated his second wedding anniversary, and my oldest has celebrated her fifth marriage anniversary. Our home in Captiva, Florida continues its recovery from from Hurricane Ian and subsequent hurricanes.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. Hill