Arizona Court of Appeals Clarifies Homeowners Association Open Meeting Requirements
June 29, 2026 —
Jill Casson Owen, Benjamin J. Hawkins & Stephen Wright - Snell & WilmerA Z N H Revocable Trust v. Sunland Springs Village Homeowners Association, No. 1 CA-CV 25-0424 (Ariz. Ct. App. Apr. 28, 2026)
OVERVIEW
The Arizona Court of Appeals issued an opinion clarifying how homeowners associations must conduct meetings under A.R.S. § 33-1804. The decision reinforces the legislative policy favoring transparency in association governance, bringing association meeting requirements more in line with the open meeting standards applicable to public bodies under A.R.S. § 38-431 et seq. (Arizona’s Open Meeting Law).
KEY HOLDINGS
1. All Voting and Formal Actions Must Occur in Open Meetings
The Court affirmed that association boards cannot vote or take formal action during closed (executive) sessions. Under A.R.S. § 33-1804(A), associations may close portions of meetings only for “consideration” of certain enumerated topics, such as legal advice, pending litigation, or personal/financial information about individual members. The Court interpreted “consideration” to mean discussion and deliberation, not voting. The Court noted that dictionaries define “consider” as “spending time thinking about a possibility” and “formulating an opinion,” which are processes that precede formal action. This interpretation mirrors how Arizona’s Open Meeting Law (A.R.S. § 38-431.03(D)) prohibits public bodies from voting in executive session.
Reprinted courtesy of
Jill Casson Owen, Snell & Wilmer,
Benjamin J. Hawkins, Snell & Wilmer and
Stephen Wright, Snell & Wilmer
Ms. Owen may be contacted at jowen@swlaw.com
Mr. Hawkins may be contacted at bhawkins@swlaw.com
Mr. Wright may be contacted at swright@swlaw.com
Read the full story...
GRSM Trial Team Holds Alameda County Asbestos Verdict to $900,000 Against $50 Million Demand
July 27, 2026 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani Partners John Katerndahl and Vincent Gunter recently obtained an outstanding trial result for a manufacturer of asbestos-containing electrical cable, holding a jury verdict to $900,000 against a $50 million demand following an eight-week trial in Alameda County Superior Court, which is among the most challenging asbestos venues in the country. The GRSM team also included Associate Brandon Sanchez, on-site trial Paralegal Laura Vitanova, and Paralegal Kerrie Lease.
The plaintiffs, the surviving spouse and four children of a former painter who died of mesothelioma, alleged that the decedent was exposed to asbestos from the company’s electrical cable during construction of a California nuclear power facility. GRSM’s client was the sole remaining defendant at trial. The plaintiffs asked the jury for $50 million and called 15 witnesses across their case-in-chief and rebuttal.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Agent Not Liable for Loss Given Insured’s Vague Instructions for Coverage
April 08, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Appellate Court affirmed the district court’s grant of summary judgment to the insured’s agent because there was no breach of duty. Jon Van Order v. Hauk, et al., 2025 Ill. App. Unpub. LEXIS 2378 (Ill. Ct. App. Dec. 23, 2025).
The insured began renovating a vacant home in October 2018. He met with agent Joseph Hauk and explained the property was vacant and would be going through renovations for the next several months. Hauk then procured a policy through Shelter Insurance Company insuring the vacant property against several specified perils. The policy provided coverage for water damage if “[t]he exterior of the building sustained a covered loss” and “that loss created an opening through which the water entered.” Damage caused by escaping water from within a plumbing system was excluded if: (1) the damage was caused by a “continuous or repeated leakage over a period of fourteen days or more” or (2) the insured premises had been vacant for 30 consecutive days immediately preceding the loss.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
GRSM Partner Debra Ellwood Meppen Recognized as 2026 Legal Visionary by Los Angeles Times
June 02, 2026 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani proudly congratulates Partner Debra Ellwood Meppen on being named a 2026 Legal Visionary by the Los Angeles Times. The LA Times Studios 2026 Legal Visionaries List recognizes lawyers in Southern California who “exemplify a forward-thinking approach to the law, elevating both their profession and the people who depend on it.” Meppen is recognized for helping shape the future of the legal profession through her leadership, professionalism, and integrity.
Published as part of the May 2026 issue highlighting Southern California’s leading law firms and attorneys, the Legal Visionaries section honors attorneys making a significant impact on the legal industry and the broader business community.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Vacant Building Negates Coverage for Broken Pipe
September 01, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Michigan Court of Appeals found the insured was not covered for water damage because the commercial space was left vacant. Cherry Hill Recreation Center, Inc. v. Conifer Ins Co., 2026 Mich, App. LEXIS 5099 (Mich Ct. App. June 18, 2026).
Alan Abbas purchased a bowling alley. Due to the onset of the COVID-19 pandemic and executive orders issued by the governor, Abbas was unable to operate the bowling center for several months. During the winter, Abbas allowed the thermostat to drop significantly, with the building expected to be around 43 degrees Fahrenheit. He later admitted the sprinkler system’s pipes were not protected against freezing.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
IRMI Expert Commentary: NY Highest Court Confronts Downstream Risk Transfer for Subcontractor Bodily Injury Claims
March 17, 2026 —
Gregory D. Podolak & Alexander G. Hopkins - Saxe Doernberger & Vita, P.C.Originally published on IRMI.com, copyright 2026 International Risk Management Institute, Inc.
Subcontractor employee bodily injury claims (so-called action over claims) are a staple of construction risk management in the Empire State—so much so that the phrase “labor law” instinctively invites a shudder among the most experienced general contractors. The savvy among them intensely monitor case law developments and the evolution of the insurance market to ensure a cutting-edge, meticulously developed downstream risk transfer plan. And when guidance arrives from an appellate-level court, it’s a moment to take note.
This is one of those moments.
In late 2025, New York’s highest court—the NY Court of Appeals—had the rare opportunity to examine an all-too-routine bodily injury fact pattern and took the opportunity to closely examine the scope of contractual indemnity and its interplay with additional insured coverage in Dibrino v. Rockefeller Center N., Inc., 2025 N.Y. Slip Op. 07077, 2025 WL 3670593 (Ct. App. Dec. 18, 2025).
Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C. and
Alexander G. Hopkins, Saxe Doernberger & Vita, P.C.
Mr. Podolak may be contacted at GPodolak@sdvlaw.com
Mr. Hopkins may be contacted at AHopkins@sdvlaw.com
Read the full story...
SDV Celebrates 30th Anniversary Press Release
April 08, 2026 —
Saxe Doernberger & Vita, P.C.Trumbull, Connecticut – Saxe Doernberger & Vita, P.C. (SDV) is proud to announce the celebration of its 30th anniversary.
Founded in 1996 by three attorneys in a small New Haven, Connecticut office, SDV was built on a clear and focused mission: representing policyholders in insurance coverage matters. Three decades later, that commitment remains at the core of the firm’s identity and has been instrumental in its continued success and reputation nationwide.
Today, SDV is a nationally recognized boutique firm with 50 attorneys serving policyholders across the United States. Building on its longstanding reputation for excellence and client advocacy, the firm is pleased to announce the opening of its newest office in Massachusetts—an exciting milestone that reflects SDV’s continued growth. The new office is led by Managing Partner Anna Perry.
Read the full story...Reprinted courtesy of
Saxe Doernberger & Vita, P.C.
U.S. Supreme Court Decision Alters Course of $745M Louisiana Coastal Damage Judgment
June 15, 2026 —
Jennifer Kretschmann & Jennifer E. Michel - Lewis BrisboisThe U.S. Supreme Court has issued a unanimous decision allowing oil and gas companies to move Louisiana coastal erosion lawsuits from state court to federal court under the federal officer removal statute. While the ruling is procedural, it carries significant implications for environmental- and energy-related risks. The case,
Chevron U.S.A. Inc. v. Plaquemines Parish, Louisiana, Slip Op. 24-813 (April 17, 2026), addressed a threshold jurisdictional question but has broader significance for environmental and climate related litigation. State courts are often viewed as more favorable forums for plaintiffs asserting environmental damage claims, particularly those brought by governmental entities.
The opinion issued on April 17, 2026 is the latest development in long-running Louisiana coastal litigation that began more than a decade ago. Starting in 2013, Louisiana parishes filed 42 lawsuits against oil and gas companies alleging environmental damage related to historic oil field operations. The parishes alleged that oil and gas companies violated state coastal management laws by failing to properly restore impacted areas. Chevron sought to remove the cases from state court under 28 U.S.C. § 1442(a)(1), known as federal officer removal, which provides federal jurisdiction over “any person acting under [an] officer” of the United States "for or relating to any act under color of such office." The Fifth Circuit rejected the argument and remanded the case, and others like it, to state court. Trial began in March 2025 in Point à la Hache, Louisiana. On April 4, 2025, the jury awarded a total of $745 million to compensate for land loss, contamination and abandoned equipment. On June 16, 2025, the U.S. Supreme Court agreed to review the question of whether a federal contractor can remove to federal court when sued for oil-production activities undertaken to fulfill a federal oil-refinement contract.
Reprinted courtesy of
Jennifer Kretschmann, Lewis Brisbois and
Jennifer E. Michel, Lewis Brisbois
Ms. Kretschmann may be contacted at Jennifer.Kretschmann@lewisbrisbois.com
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Read the full story...