Builders Risk/Construction All Risks and Delay in Start-Up Coverage for Large Energy Projects: Protecting Revenue Before Operations Begin
September 21, 2026 —
Will Bennett - SDV FenchurchThe Most Significant Loss May Be the Delay, Not the Damage
Power and energy projects are uniquely vulnerable to losses during construction. Whether the project involves a utility-scale solar facility, battery storage installation, a wind farm, transmission project, LNG terminal, or conventional generation facility, loss events in this sector often have consequences far more impactful than the actual cost of repairing damaged property.
Any number of construction losses can delay commercial operation of the facility by months, triggering lost revenues, financing impacts, contractual penalties, and investor concerns. In many cases, those delay-related losses significantly exceed the underlying repair costs.
Construction All Risk (“CAR”) insurance and Delay in Start-Up (“DSU”) coverage are designed to respond to these exposures. However, recovering delay-related losses is far more complicated than many insureds anticipate, particularly when projects involve international stakeholders, global supply chains, and London market insurance placements.
Read the full story...Reprinted courtesy of
Will Bennett, SDV FenchurchMr. Bennett may be contacted at
will.bennett@sdvfenchurch.us
“The Superintendent Told Us to Do It:” Why Verbal Approval May Not Be Enough
June 02, 2026 —
Andrew Lintner - Colorado Construction Litigation BlogIn construction defect litigation, one scenario appears repeatedly: a subcontractor installs work in a manner that differs from the plans, specifications, manufacturer instructions, or industry standards after being verbally directed to do so by the general contractor, superintendent, architect, or owner’s representative.
At the time, the decision may seem minor. The project is moving quickly, the field team wants to maintain progress, and nobody wants to stop working over what appears to be a small issue. The subcontractor may trust the superintendent or project manager and assume the conversation will be remembered later if questions arise.
Years later, however, when the project experiences problems, the people involved may deny the conversation occurred, remember it differently, or simply no longer remember the project. Without written documentation, the subcontractor can find itself defending claims for defective work, even though it performed the installation exactly as directed.
Read the full story...Reprinted courtesy of
Andrew Lintner, Higgins, Hopkins, McLain & Roswell, LLCMr. Lintner may be contacted at
alintner@hhmrlaw.com
Judge's Order Halts Google Data Center Project in Minnesota
July 27, 2026 —
Annemarie Mannion - Engineering News-RecordConstruction of a $1-billion Google data center planned by
Ryan Cos. on 485 acres in southeastern Minnesota was expected to start in July but is now halted under a judge’s order.
Read the full story...Reprinted courtesy of
Annemarie Mannion, Engineering News-RecordMs. Mannion may be contacted at
manniona@enr.com
Not All Warranty E-Mails Are Notices of Claim
October 20, 2026 —
David McLain - Colorado Construction Litigation BlogThere is a frustrating tendency in some Colorado construction defect litigation to treat virtually any written complaint about construction work as a statutory notice of claim under the Construction Defect Action Reform Act (“CDARA”). An e-mail complaining about cracked concrete. A request for warranty service. A message asking a builder to come inspect a leaking window. Years later, when the homeowner faces a statute-of-limitations defense, these routine communications are suddenly characterized as statutory notices of claim, with the convenient consequence that an otherwise untimely lawsuit becomes timely.
Enough is enough.
A warranty complaint is not a statutory notice of claim simply because a homeowner complains about construction. Courts and arbitrators should stop treating the two as interchangeable.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
The GKN Aerospace Chemical Release and the Laws Designed to Address It
July 06, 2026 —
Sean M. Sherlock - Snell & WilmerOn May 21, 2026, a 34,000-gallon storage tank at the GKN Aerospace facility in Garden Grove, California began leaking methyl methacrylate (MMA), a volatile and highly flammable industrial chemical used to manufacture high-strength acrylic plastics. GKN Aerospace makes advanced military and commercial transparencies, such as aircraft canopies, windshields, cabin windows, bullet-resistant glass, and spacecraft windows.
In polymer chemistry lingo, MMA is known as a monomer. Monomers are like individual links to a chain. Under the right conditions they link up (react) with each other to form long-chained polymers, or plastics. MMA is an unstable monomer that requires controlled storage conditions to avoid setting off a polymerization (chain) reaction.
According to early reports, the MMA tank at GKN Aerospace overheated. The cause of the overheating is not yet clear, but the overheating may have created conditions enabling the MMA to initiate polymerization, which in turn generated heat, which in turn generated pressure, activating the tank’s pressure-relief system and releasing MMA vapor into the atmosphere. Concerns about a runaway reaction, massive release, and explosion led the Orange County Fire Authority to order evacuation of approximately 40,000 residents and closure of thirteen schools.
Read the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
Delay Matters: Florida’s Fourth DCA Reverses Hurricane Irma Dismissal
June 08, 2026 —
Andrea DeField, Machaella Reisman & Cary D. Steklof - Hunton Insurance Recovery BlogThe mantra “delay, deny, defend” is frequently referenced in discussions of insurance claims handling, though insurers will invariably disavow these tactics. While it would be facially improper for an insurer to delay a coverage decision to gain a tactical advantage, empirical examples nonetheless exist. This very dynamic was addressed by Florida’s Fourth District Court of Appeals when it handed policyholders a win in
Hypoluxo Mariner’s Cay Condo. Assoc’n, Inc. v. Underwriters at Lloyd’s London, No. 4D2024‑2250 (Fla. 4th DCA Apr. 1, 2026), reversing a trial court order dismissing a condominium association’s Hurricane Irma coverage lawsuit against its property insurer.
Delay to Run the Statute of Limitations
Following Hurricane Irma, a condominium association suffered roof and exterior envelope damage, reported an insurance claim, and submitted a sworn proof of loss to its property insurer in compliance with Florida Statute § 627.70132 (2020). The statute establishes a timeframe within which a policyholder must submit a claim for hurricane damage.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth LLP,
Machaella Reisman, Hunton Andrews Kurth LLP and
Cary D. Steklof, Hunton Andrews Kurth LLP
Ms. DeField may be contacted at adefield@hunton.com
Ms. Reisman may be contacted at reismanm@hunton.com
Mr. Steklof may be contacted at csteklof@hunton.com
Read the full story...
Emerging Issues in Construction CGL Insurance Part 2: The Separation of Insureds and Additional Insured Interests
September 29, 2026 —
Eric M. Clarkson - SDV FenchurchMany coverage disputes hinge on first principles—the fundamentals of insurance —rather than the minutiae. Unfortunately, the basic anatomy of insurance policies can get lost sometimes when parties are laser-focused on a particular term or set of circumstances. This is true not just in disputes, but also when writing coverage. One of the fundamentals that is commonly misunderstood and overlooked—but which is absolutely critical to the intended operation of insurance coverage—is what is commonly known as the “separation of insureds.”
The “separation of insureds” is the concept that each “insured” under a policy are referred to and treated differently, and most of all that the distinctions matter. The concept is usually included as a condition in the policy. It embodies the requirement that the policy applies to each insured distinctly from how it applies to other insureds. The ISO Form CGL policies specifically state that they apply “[s]eparately to each insured against whom a claim is made or ‘suit’ is brought.” The separate and distinct treatment of insureds is more critical in construction operations than anywhere else. This distinction is essential to ensure coverage works as intended, especially when contracted operations are involved, because the policy must insure the subcontractor that purchased the policy, the general contractor who hired the subcontractor, and the owner that hired the general contractor. Even small modifications can easily frustrate the intent of the parties.
Read the full story...Reprinted courtesy of
Eric M. Clarkson, SDV FenchurchMr. Clarkson may be contacted at
eric.clarkson@sdvfenchurch.us
Court Finds Potential Conflicts In Denying Insurer’s Motion to Dismiss Claim for Independent Counsel
October 12, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe District Court denied the insurer’s motion to dismiss the additional insured’s claim that the appointment of independent counsel was required. S. Cal. Edison Co. v. Travelers Prop. Cas. Co of Am., 2025 U.S. DIst. LEXIS 148495 (C.D Calif. July 15, 2025).
Southern California Edison Company (SCE) entered a Master Services Agreement with its contractor, SASCO whereby SASCO agreed to provide services concerning electrical pole repair and replacement. SASCO was required to obtain primary and excess general liability policies and to name SCE as an additional insured. SASCO obtained such policies from Travelers, naming SCE as an additional insured. The policies limited coverage for SCE to covered damages arising from SASCO’s work.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com