New Law Prompts ABC Minnesota/North Dakota to Design New Telecommunications Safety Training Program
June 29, 2026 —
Grace Calengor - Construction ExecutiveOn the first day of the year, a
Minnesota law requiring installers of underground telecommunication infrastructure broadband, fiber or phone lines (when projects utilize directional drilling, and/or work is being conducted within 10 feet of existing utilities) to undergo a 40-hour certification went into effect.
Originally passed in mid-2024 and proposed to go into effect in July 2025, the law’s requirements were postponed until January 2026, giving
ABC Minnesota/North Dakota—in partnership with
NCCER and the
Minnesota Cable Communications Association—time to roll out their
Safety Qualified Underground Telecommunications Installer training program, which would ensure the workforce of their contractor members were certified.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Federal Court Finds that Master Agreement Bestows Additional Insured Coverage
November 09, 2026 —
Craig Rokuson - Traub LiebermanIn the recent case Triborough Scaffolding & Hoisting Servs. v. Sw. Marine & Gen. Ins. Co., 2026 U.S. Dist. LEXIS 226876, Judge P. Kevin Castel, who was also operating as finder of fact, held that a subcontractor master agreement covered a subcontractor’s work at a specific project, such that an obligation to name the prime contractor Triborough as well as the undefined Owner, bestowed additional insured coverage to Triborough and the Owner under policies issued to the subcontractor.
The agreement at issue was dated December 15-16, 2017 and the accident at issue occurred in 2018. The trial evidence includes testimony from both Triborough and the subcontractor that the agreement was intended to apply annually, and the subcontractor could not recall the parties ever signing a project-specific agreement. Further, Triborough assigned work to the subcontractor by telephone call or texts on several projects, and without a project-specific contract. Moreover, no other operative indemnity or insurance agreement between Triborough and the subcontractor, other than a backdated agreement that was not applicable. Finally, the court did not find plausible that the subcontractor would enter into an agreement meant only to cover the final two weeks of 2017, such that the agreement extended into work occurring in 2018.
Read the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
The “Pay When Paid” Clause in California Construction—Strategies as the Battle Continues
August 03, 2026 —
William L. Porter - Porter Law GroupIt is well known in California Construction circles that the “Pay If Paid” clause is illegal in this state. There is a great distinction, though, between this clause and a similar clause, known as a “Pay When Paid” clause. A pay if paid clause allows a contractor to tell a subcontractor that if the contractor is unpaid for the subcontractor’s work, then the contractor has no legal obligation to pay the subcontractor, ever. For a great variety of reasons, the California Supreme Court, in the case of Wm. R. Clarke Corp v. Safeco Ins. Co. of America (1997) 15 Cal.4th 882, declared this type of clause illegal in California Construction.
Although the pay if paid clause is illegal in California, the pay when paid clause is still perfectly legal and is found in many subcontracts that contractors issue to their subcontractors. The pay when paid clause allows a contractor to delay paying its subcontractors until the dispute between the contractor and the property owner over payment has been resolved and the contractor is paid by the property owner. Although seemingly reasonable (since it merely delays payment until the contractor is paid by the owner, thereby providing a funding source to pay subcontractors), significant problems still arise.
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Don’t Forget to Include Termination Language in Your Contract
November 02, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent case explains why termination language or a basis to withhold contract sums is important in your contract. Don’t neglect this language or the negotiation that goes into having this language.
In a recent dispute, GSD Contracting, LLC v. All American Builders & Debris Removal, Inc., 2026 WL 3068422 (Fla. 4th CA 2026), a subcontract included language that said that 10% retainage would be paid 90 days after final completion of the project. The subcontract did NOT include termination for cause language; it only included termination for convenience language. Towards the end of the project, mold was discovered warranting mold remediation. The subcontractor refused to perform until the mold was remediated. The general contractor claimed it was remediated but the subcontractor argued the remediation was insufficient because the contractor did not engage an industrial hygienist. After the subcontractor refused to complete its work, the general contractor terminated the subcontractor for cause. The subcontractor then sued the general contractor for its 10% retainage claiming the general contractor breached the subcontract. The trial court, as affirmed by the appellate court, agreed. The appellate court found that the contract required the general contractor to pay the subcontractor’s retainage 90 days after final completion and the project had long been completed. “Significantly, the subcontract does not contain a termination for cause provision or any pertinent provision permitting [the general contractor] to withhold or retain [the subcontractor’s] retainage following a termination…Nothing in the subcontract provides that [the general contractor] may thereafter withhold the retainage based on an alleged default by [the subcontractor].” GSD Contracting, supra, at *2.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
The GKN Aerospace Chemical Release and the Laws Designed to Address It
July 06, 2026 —
Sean M. Sherlock - Snell & WilmerOn May 21, 2026, a 34,000-gallon storage tank at the GKN Aerospace facility in Garden Grove, California began leaking methyl methacrylate (MMA), a volatile and highly flammable industrial chemical used to manufacture high-strength acrylic plastics. GKN Aerospace makes advanced military and commercial transparencies, such as aircraft canopies, windshields, cabin windows, bullet-resistant glass, and spacecraft windows.
In polymer chemistry lingo, MMA is known as a monomer. Monomers are like individual links to a chain. Under the right conditions they link up (react) with each other to form long-chained polymers, or plastics. MMA is an unstable monomer that requires controlled storage conditions to avoid setting off a polymerization (chain) reaction.
According to early reports, the MMA tank at GKN Aerospace overheated. The cause of the overheating is not yet clear, but the overheating may have created conditions enabling the MMA to initiate polymerization, which in turn generated heat, which in turn generated pressure, activating the tank’s pressure-relief system and releasing MMA vapor into the atmosphere. Concerns about a runaway reaction, massive release, and explosion led the Orange County Fire Authority to order evacuation of approximately 40,000 residents and closure of thirteen schools.
Read the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
Additional Insureds Obligated to Meet Self-Insured Retention
October 20, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found that the additional insureds had to meet the policy’s self-insured retention before a duty to defend was triggered. Amerisure Ins. Co. v. Premier Design & Build Group, LLC, 2026 U.S. Dist. LEXXIS 170741 (N.D. Ill. July 31, 2026).
Amerisure issued CGL and umbrella policies to Premier Design & Build Group, LLC. Amerisure had the right and duty to defend in certain suits for property damage under both policies.
Premier contracted with MG East, LLC (MGE) to build three buildings. After the buildings were constructed, MG filed suit against Premier in state court, seeking recovery for allegedly defective installation of the roof, flashing, and gutters on each of the buildings. Premier had subcontracted with Tecta American Sough Florida, Inc. to install the flashing.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Endra Rethinks MEP Design with AI
July 06, 2026 —
Aarni Heiskanen - AEC BusinessNiklas Lindgren, co-founder and CEO of Endra, joins the
AEC Business Podcast to discuss why his Stockholm-based startup is rebuilding MEP design from the ground up with AI. Endra recently raised $50 million in Series A funding and counts some of the world’s largest engineering consultancies as customers.
Niklas explains why Revit’s underlying data model is too coarse to support deep automation, and why Endra built its own granular 3D data model instead of working as a plugin. He describes Endra’s “spatial AI” approach to routing conduit and ductwork without clashes, and how the platform models entire electrical systems, from receptacle to transformer, inside a single source of truth.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Partner Bryan Stofferahn and Our Walnut Creek Team Secure Summary Judgment in a $28 Million Premises Liability Case!
September 15, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBWB&O is proud to announce that Partner
Bryan Stofferahn and the Walnut Creek Team secured a Summary Judgment on behalf of the firm’s clients, resulting in a complete dismissal of a negligence and premises liability claim.
Plaintiff, a teenager, was riding his bicycle on private commercial property when he was struck by a vehicle. Plaintiff was in a coma for 6 weeks and developed major neurocognitive dysfunction from a traumatic brain injury.
BWB&O’s clients are a commercial property owner and property management company, who Plaintiff contended were liable for his injuries based on the design, condition, operation, and management of the premises. Plaintiff had demanded $28 million in settlement of the claims against all defendants.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara, LLP