Arizona Court Enters $323 Million Judgment Against ZOM Living Following Unanimous Jury Verdict
May 26, 2026 —
Gray Development GroupPHOENIX, May 19, 2026 /PRNewswire/ -- A Maricopa County court has entered a $323 million compensatory damages judgment in favor of Gray Development Group against ZOM Holding Inc., doing business as ZOM Living, following a 12-day trial, a unanimous jury verdict and post-trial proceedings related to a proposed business transaction.
The jury found ZOM liable on claims of breach of contract and breach of the implied covenant of good faith and fair dealing stemming from a proposed joint venture tied to a planned pipeline of luxury multifamily and commercial projects in Phoenix and Scottsdale.
The lawsuit centered on a 13-project, $1.4 billion development pipeline originated and planned by Gray Development Group over more than a decade. In 2019, Gray invited Florida-based ZOM to participate in a joint venture involving the completion of five projects, which would have marked ZOM's entry into the Arizona market.
According to court findings presented at trial, the companies entered into a mutual confidentiality and non-circumvention agreement before Gray shared extensive sensitive and proprietary information related to the projects, including planning, market analysis, costs, financial data, local business relationships and operational strategies developed by Gray over decades in Arizona.
Evidence presented during trial showed that over a 10-month period while under contract, ZOM made hundreds of requests for confidential project and market information before circumventing Gray and pursuing the projects independently, ultimately displacing Gray from projects it spent years planning and developing.
ZOM Living, headquartered in Orlando, develops multifamily and senior housing communities across the United States and operates regional offices in Boston, Dallas, Fort Lauderdale, Nashville, Phoenix, and Raleigh. ZOM is owned by Timeless Investments, the Amsterdam-based family office of Dutch businessman Hans van Veggel, which acquired the company in 1997.
About Gray Development Group
Gray Development Group was founded by architect Bruce Gray in 1991. The Phoenix-based company was the top-ranked multifamily developer in Arizona for more than a decade. The company designed and developed more than 15,000 apartment and condominium units throughout metropolitan Phoenix. Two Gray-designed developments — a Tempe midrise and a San Diego high-rise — received National Apartment Community of the Year awards.
EPA Steps Back, Arizona Moves Forward
May 12, 2026 —
Patrick J. Paul, John Habib & Sukhmani K. Singh - Snell & WilmerIn a significant development for Arizona’s business community and environmental policymakers, the U.S. Environmental Protection Agency (EPA) has paused its planned reclassification of Maricopa County from “Moderate” to “Serious” ozone nonattainment status pursuant to the Clean Air Act’s National Ambient Air Quality Standards (NAAQS).
This decision marks a shift in federal air policy — one that recognizes the unique challenges faced by regions like metro Phoenix, where environmental conditions beyond local control are often key contributors to air quality readings.
The EPA’s move follows a series of meetings between EPA Administrator Lee Zeldin, Arizona elected officials, and business and civic leaders, including a recent roundtable in Phoenix convened by U.S. Senator Mark Kelly. In announcing the pause, Zeldin acknowledged the need for flexibility and fairness in the application of Clean Air Act standards, especially when emissions from other states, nations, and natural events significantly influence local air quality.
Reprinted courtesy of
Patrick J. Paul, Snell & Wilmer,
John Habib, Snell & Wilmer and
Sukhmani K. Singh, Snell & Wilmer
Mr. Paul may be contacted at ppaul@swlaw.com
Mr. Habib may be contacted at jhabib@swlaw.com
Ms. Singh may be contacted at ssingh@swlaw.com
Read the full story...
Building in Arizona’s Data Center Boom: How Federal Executive Orders, State Regulation, and National-Security Policy Are Reshaping the Rules for Developers
June 02, 2026 —
Ryan J. Regula - Snell & WilmerDevelopers and practitioners evaluating data center projects in Arizona face a regulatory environment shifting on three fronts simultaneously. Federal executive orders are opening new land, streamlining permitting, and channeling financial incentives toward qualifying projects — but they are not preempting the state and local rules that most directly affect project economics. A carve-out in the December 2025 Artificial Intelligence (AI) Framework Executive Order preserves Arizona’s authority over data center infrastructure, meaning the Arizona Corporation Commission’s (ACC) rate-classification docket, municipal zoning restrictions, water-use ordinances, and pending grid cost-allocation legislation remain the binding constraints on project feasibility. Understanding where federal tailwinds end and state and local headwinds begin is essential for any developer sizing risk or selecting sites in the state.
The Federal Landscape: An Interlocking Framework of Executive Orders
Five interlocking executive orders are accelerating data center development nationally, but none overrides Arizona’s authority over siting energy, or infrastructure.
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
Federal Court Highlights the Strategic Value of Additional Insured Coverage
June 22, 2026 —
Michael S. Levine - Hunton Insurance Recovery BlogA recent decision from the District of Maryland underscores a recurring—but often underutilized—opportunity for policyholders: securing and enforcing additional insured coverage under another party’s liability policy. In Charter Oak Fire Insurance Co. v. Builders Premier Insurance Co., the court held that an equipment lessor qualified as an additional insured under the lessee’s policy and was entitled to a primary defense.
The decision is a useful reminder that additional insured coverage can fundamentally shift defense obligations and materially reduce a policyholder’s exposure. We build on the decision to highlight the practical steps policyholders should take to ensure that all potentially available insurance is identified and pursued.
Read the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth LLPMr. Levine may be contacted at
mlevine@hunton.com
Data Center Construction and the AEC Partner of the Future
April 14, 2026 —
Aarni Heiskanen - AEC BusinessDuring my involvement in designing mobile phone production facilities, the speed of design and construction was critical. Any delay could directly translate into lost revenue. That same logic now applies to data centers, though the stakes are much higher. Instead of optimizing physical production lines, we are constructing infrastructure for digital production.
The global data center capacity is expected to nearly double by 2030, and with this level of demand, the traditional project-by-project delivery model begins to show its limitations.
Data centers are no longer isolated projects in the traditional sense. They are evolving into repeatable, scalable production systems, making them ideal environments for AEC process and business model innovation.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
SDV Celebrates 30th Anniversary Press Release
April 08, 2026 —
Saxe Doernberger & Vita, P.C.Trumbull, Connecticut – Saxe Doernberger & Vita, P.C. (SDV) is proud to announce the celebration of its 30th anniversary.
Founded in 1996 by three attorneys in a small New Haven, Connecticut office, SDV was built on a clear and focused mission: representing policyholders in insurance coverage matters. Three decades later, that commitment remains at the core of the firm’s identity and has been instrumental in its continued success and reputation nationwide.
Today, SDV is a nationally recognized boutique firm with 50 attorneys serving policyholders across the United States. Building on its longstanding reputation for excellence and client advocacy, the firm is pleased to announce the opening of its newest office in Massachusetts—an exciting milestone that reflects SDV’s continued growth. The new office is led by Managing Partner Anna Perry.
Read the full story...Reprinted courtesy of
Saxe Doernberger & Vita, P.C.
The Most Expensive Signature to Not Get: Why Change Orders Matter
August 16, 2026 —
Kathryne E. Baldwin - Wilke FleuryGeorge Bernard Shaw has a quote we use a lot in my family: “The single biggest problem in communication is the illusion that it has taken place.” This is pertinent to contractors and homeowners alike because the cost of failing to get proper signatures on documents like construction contracts, and particularly, change orders, is heavy. Both contractors and homeowners are in the same boat as far as wanting to complete a job as swiftly as possible: contractors go on to their next job and homeowners can return to peace in their home. This is prime territory for either party to suggest the work be completed today and the contract or change order executed tomorrow, or even later. However, without a contract, there is no memorialization of the communication between the parties, which can lead to confusion and missed expectations on both sides.
Construction plans are rarely as neat and tidy as they originally seem to be. A contractor may uncover unforeseen conditions, an owner may request additional work or changes that require additional work, or weather interferes with project schedules or the work itself. Unfortunately, the signature that never gets collected can become one of the most expensive omissions on a project – for both sides.
Read the full story...Reprinted courtesy of
Kathryne E. Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com
Introducing the Updated 2026 Pillsbury Guide to Data Centers
June 08, 2026 —
Gravel2Gavel Team - Gravel2Gavel Construction & Real Estate Law BlogSince the initial publication of the Pillsbury Guide to Data Centers in 2025, the market has continued to evolve—most notably with respect to power availability, energy strategy, tax and incentives planning, and investment activity across the sector. While many of the legal, commercial and regulatory frameworks addressed in the original Guide remain durable and relevant, recent developments warranted targeted updates and additions.
The
2026 edition expands and updates our energy-focused content to reflect the increasingly central role of power procurement, interconnection and long-term energy strategy in data center development. We have incorporated new materials addressing power purchase and interconnection agreements, solar and other renewable energy solutions, advanced reactor designs, and nuclear-powered data centers projects, including an updated project tracker. We have also added new analysis covering state and local tax considerations and incentive structures relevant to data center development and operations, as well as current M&A and private equity trends shaping investment in the sector.
Read the full story...Reprinted courtesy of
Gravel2Gavel Team