Settlement Agreements and Contracts Require a Meeting of the Minds
July 20, 2026 —
David Adelstein - Florida Construction Legal UpdatesA settlement agreement does not need to be executed for it to be enforceable as long as there was a MEETING OF THE MINDS. The same rings true for any contract regardless of whether the contract is signed – THERE NEEDS TO BE A MEETING OF THE MINDS.
In a recent case dealing with the settlement agreement on a construction lien, the essential settlement terms (money and mutual release) were memorialized in an e-mail exchange between the parties (owner and subcontractor). The settlement required the owner to pay the principal amount plus some attorney’s fees and then a mutual general release would be prepared. In response to the confirmatory email, the owner sent a check, which the subcontractor deposited, but the owner refused to sign the release signed and sent by the subcontractor. The owner further claimed it doesn’t need to pay the attorney’s fees because the lien amount was paid in full. The subcontractor sued arguing the owner breached the terms of the settlement. The appellate court agreed.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Newmeyer Dillion Ranked in Chambers Spotlight California 2026 Guide
May 26, 2026 —
Newmeyer DillionNEWPORT BEACH, Calif. – May 14, 2026 - Prominent business and real estate law firm Newmeyer Dillion has been ranked in Chambers Spotlight California 2026 guide and recognized as a leading firm in Litigation: General Commercial for Orange County.
Newmeyer Dillion was selected based on an independent and in-depth market analysis, coupled with an assessment of the firm’s experience, expertise and caliber of talent where the firm stood out for its exceptional work and is recognized in Litigation: General Commercial.
Managing Partner Paul Tetzloff expressed the firm's gratitude: “It is an honor for our firm to be recognized by Chambers and Partners in their Spotlight California 2026 guide. This acknowledgment reflects our commitment to providing high quality legal services tailored to the unique needs of our clients.”
Read the full story...Reprinted courtesy of
Newmeyer Dillion
A Couple of Mechanic’s Lien Bills in VA [UPDATED]
February 23, 2026 —
Christopher G. Hill - Construction Law MusingsWell, its that time of year again, the Virginia General Assembly is in session and looking to make changes to all kinds of things here in the Commonwealth. While most of those changes are well outside of the subject of Construction Law Musings, changes to the
mechanic’s lien statutes certainly are not. This year, the Virginia General Assembly is poised to make some big changes if certain legislation gets out of committee and passes the legislature, a description and some comments on these follow:
HB752 – Mechanics’ liens; liens attaching to property; memorandum of lien. [Original Description] Removes the exclusion of the attachment of a mechanic’s lien to property improved or repaired when the lien is based on a claim for repairs or existing structures. The bill further removes (i) the ability of a lien claimant to file any number of memoranda of lien including the details relating to the lien and (ii) the provisions of the Code specifying that no memorandum filed shall include sums due for (a) labor or materials furnished more than 150 days prior to the last day labor was performed or (b) material furnished to the job preceding the filing of such memorandum.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Can Anything Supersede Excel in AEC?
April 27, 2026 —
Aarni Heiskanen - AEC BusinessIf there’s one piece of software that dominates the business world across industries, it’s Microsoft Excel. Can AI finally dethrone the mighty spreadsheet?
Memorable Spreadsheet Moments
Everyone has memorable spreadsheet moments. I have a few. For example, my then-architecture firm was involved in more than a dozen housing developments abroad. I developed an Excel workbook that took the required number of households as input and automatically generated a breakdown of buildings and their apartment types for AutoCAD. This was urban planning and architectural design done with a spreadsheet.
I also developed business software using Excel for project portfolio management. The prototype was later scaled into a commercial SaaS that is now used globally.
Another memorable moment was when a property owner told me their Excel file grew so large that it ran out of rows and columns. That must have been before 2007, when the maximum number of columns on a sheet was still just 256 and the maximum number of rows was 65,536. The current limits are 1,048,576 rows and 16,384 columns, which I hope no one will exceed.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Arizona Court Enters $323 Million Judgment Against ZOM Living Following Unanimous Jury Verdict
May 26, 2026 —
Gray Development GroupPHOENIX, May 19, 2026 /PRNewswire/ -- A Maricopa County court has entered a $323 million compensatory damages judgment in favor of Gray Development Group against ZOM Holding Inc., doing business as ZOM Living, following a 12-day trial, a unanimous jury verdict and post-trial proceedings related to a proposed business transaction.
The jury found ZOM liable on claims of breach of contract and breach of the implied covenant of good faith and fair dealing stemming from a proposed joint venture tied to a planned pipeline of luxury multifamily and commercial projects in Phoenix and Scottsdale.
The lawsuit centered on a 13-project, $1.4 billion development pipeline originated and planned by Gray Development Group over more than a decade. In 2019, Gray invited Florida-based ZOM to participate in a joint venture involving the completion of five projects, which would have marked ZOM's entry into the Arizona market.
According to court findings presented at trial, the companies entered into a mutual confidentiality and non-circumvention agreement before Gray shared extensive sensitive and proprietary information related to the projects, including planning, market analysis, costs, financial data, local business relationships and operational strategies developed by Gray over decades in Arizona.
Evidence presented during trial showed that over a 10-month period while under contract, ZOM made hundreds of requests for confidential project and market information before circumventing Gray and pursuing the projects independently, ultimately displacing Gray from projects it spent years planning and developing.
ZOM Living, headquartered in Orlando, develops multifamily and senior housing communities across the United States and operates regional offices in Boston, Dallas, Fort Lauderdale, Nashville, Phoenix, and Raleigh. ZOM is owned by Timeless Investments, the Amsterdam-based family office of Dutch businessman Hans van Veggel, which acquired the company in 1997.
About Gray Development Group
Gray Development Group was founded by architect Bruce Gray in 1991. The Phoenix-based company was the top-ranked multifamily developer in Arizona for more than a decade. The company designed and developed more than 15,000 apartment and condominium units throughout metropolitan Phoenix. Two Gray-designed developments — a Tempe midrise and a San Diego high-rise — received National Apartment Community of the Year awards.
Arbitration in Construction Disputes: Process and Best Practices
July 27, 2026 —
Construction ExecutiveArbitration in construction disputes is a private process where owners, contractors, subcontractors, designers or suppliers present claims to one or more neutral arbitrators instead of taking the dispute through court. The arbitrator reviews evidence, hears testimony and issues a decision that is usually binding.
Construction arbitration is common because project disputes are technical, document-heavy and time-sensitive. Claims may involve schedule delays, disputed change orders, defective work, differing site conditions, payment, termination, indemnity, surety issues or professional liability.
Arbitration can be faster and more specialized than litigation, but speed is not guaranteed. Poor contract language, broad discovery, weak records and unclear damages can make arbitration expensive.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Are Robotic Coworkers Soon a Reality in Construction?
March 24, 2026 —
Aarni Heiskanen - AEC BusinessGeneral-purpose humanoid robots are in the headlines, but is the hype justified? What’s the point of having a robot home assistant when it still needs a “guy behind the curtain” to control it remotely?
Despite the challenges, robots, even those that look like humans, are seriously considered as future coworkers in business environments.
According to the McKinsey report
‘Will embodied AI create robotic coworkers?‘ the idea that AI-powered robots will become general-purpose coworkers is grounded in real technological progress, but not an overnight reality.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Insured General Contractor Prevails on Motion for Summary Judgment to Establish Builder’s Risk Coverage
July 06, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe general contractor’s motion for partial summary judgment successfully established that damage to footings in place before the policy period was covered after the collapse of a building. Big D Builders, Inc. v. Am Zurich Ins. Co., 2026 U.S. Dist. LEXIS 72012 (D. Idaho March 31, 2026).
Big D was the general contractor for building a new airplane hangar by erecting a 38,000 square foot structure. Before Big D began construction, the site of the hangar did not contain any pre-existing structures or buildings. Before completion of the hangar, it collapsed and caused extensive property damage.
The builder’s risk policy issued by Zurich covered certain aspects of the construction project for the policy period December 28, 2023, to December 28, 2024. Zurich accepted coverage for most of the damage but not for damage to footings and columns installed prior to the start date of the policy.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com