GRSM Trial Team Holds Alameda County Asbestos Verdict to $900,000 Against $50 Million Demand
July 27, 2026 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani Partners John Katerndahl and Vincent Gunter recently obtained an outstanding trial result for a manufacturer of asbestos-containing electrical cable, holding a jury verdict to $900,000 against a $50 million demand following an eight-week trial in Alameda County Superior Court, which is among the most challenging asbestos venues in the country. The GRSM team also included Associate Brandon Sanchez, on-site trial Paralegal Laura Vitanova, and Paralegal Kerrie Lease.
The plaintiffs, the surviving spouse and four children of a former painter who died of mesothelioma, alleged that the decedent was exposed to asbestos from the company’s electrical cable during construction of a California nuclear power facility. GRSM’s client was the sole remaining defendant at trial. The plaintiffs asked the jury for $50 million and called 15 witnesses across their case-in-chief and rebuttal.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Fight for Your Right: Effects of FAR Final Rule on Construction
October 12, 2026 —
Michael Altman - Construction ExecutiveSince the Federal Acquisition Regulation final rule Use of Project Labor Agreements for Federal Construction Projects took effect, contractors seeking to compete for federal projects of $35 million or more must “negotiate or become a party to a project labor agreement with one or more labor organizations.” While this requirement significantly reduces competition for covered procurements, contractors may seek to restore competition on individual solicitations by filing a bid protest with the U.S. Court of Federal Claims.
Bid protests through the COFC become possible once a federal agency posts a solicitation that includes contract provisions mandating a PLA. (In some cases, a presolicitation notice that a PLA mandate will be applied may be sufficient.)
Reprinted courtesy of
Michael Altman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Mr. Altman may be contacted at
altman@abc.org
Mark Cronenwett Obtains Appellate Ruling Vacating Default Judgment Against Mortgage Lender Client
October 12, 2026 —
Lewis BrisboisDallas Partner Mark Cronenwett recently secured a decision from the Dallas Court of Appeals that vacated a default judgment against his mortgage lender client, on the grounds that the client was never properly served with the complaint.
In prior litigation, a real property investor purchased a Texas residential property for pennies on the dollar at an HOA foreclosure sale. That investor then filed a frivolous lawsuit against Lewis Brisbois' mortgage-lender client to invalidate its lien, contending that mortgage lender had abandoned the debt because it failed to respond to the investor’s alleged requests for information about the amounts owed on the loan.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Insureds’ Altering Dates for Hailstorm Damage Justifies Denial of Claim
June 02, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Firth Circuit affirmed the district court’s grant of summary judgment to the insurer due to the insureds’ failure to establish the date of loss after a hailstorm. Cutchall v. Chubb Lloyds Ins. Co. of Texas, 2026 WL 625633 (5th Cir. March 5, 2026).
In September 2021, the Cutchalls made a claim on their policy for interior water damage due to a hailstorm that breached their roof. Chubb retained two engineers to inspect the home, but neither found evidence that a hailstorm caused the damage. Instead, the engineers concluded a variety of other causes, such as poor ventilation and as-built defects, caused the damage. Because Chubb concluded that some of these other causes were covered by the policy, it paid only for the covered portions.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Nevada’s Mandatory Nonbinding Arbitration Law for Civil Cases is Going Through Changes
May 14, 2026 —
Brandon Wright & Manuel Gurule - Lewis BrisboisNevada currently operates an expedited litigation program designed to resolve civil disputes with a value up to $50,000 without incurring the “usual” expense of litigating these disputes. Over time, however, the number of civil cases that have been “exempted” from this program based on the claimed damages exceeding $50,000 has grown dramatically. In response, the Nevada Legislature recently enacted a number of rule changes designed to streamline Nevada’s arbitration process and include more cases. Among these changes are increasing the arbitration “cap” from $50,000 to $100,000.
By way of background, the Nevada’s Court Annexed Arbitration program is a mandatory, non-binding program for civil cases in judicial districts that have county populations of 100,000 or more [1]. Nevada’s Court Annexed Arbitration was born out of NRS 38.250, which was enacted in 1991 and went into effect in the summer of 1992. The newly enacted NRS 38.250 was regarded as a way to address the problem of increased court caseloads while promoting judicial economy and efficiency in civil cases having a probable jury award of less than $25,000 [2]. Initially, cases that were automatically exempt from the program included class actions, medical malpractice disputes, divorce proceedings, and other domestic relations matters [3].
Reprinted courtesy of
Brandon Wright, Lewis Brisbois and
Manuel Gurule, Lewis Brisbois
Mr. Wright may be contacted at Brandon.Wright@lewisbrisbois.com
Mr. Gurule may be contacted at Manuel.Gurule@lewisbrisbois.com
Read the full story...
Steel Cooling: Steel Costs Steadily Decline After Pandemic Price Shock
May 12, 2026 —
Construction ExecutiveSteel prices have continued trending downward after several years of volatility, according to Gordian’s latest analysis based on RSMeans Data. After dramatic spikes during the pandemic-era supply disruptions, the market has gradually stabilized as supply chains improve and demand softens in some construction segments. However, selective volatility and tariff uncertainty continue to influence pricing across the sector.
Key findings from the report include:
- Steel prices declining: The national average price of structural steel fell to about $2,343.93 per ton in January 2026, down 5.38% from the previous quarter and 7.18% year over year.
- Longer-term price correction: Steel costs have been trending downward since 2024 after earlier volatility driven by inflation, supply shortages and global demand swings.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Real Estate & Construction News Roundup (8/12/26) – Data Center Momentum Increases, Multifamily Construction Projects Decline, CRE Returns as Top Investor Preference
September 01, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, office vacancies fall, fair housing advocacy groups sue HUD, foreign buyers reduce purchases of U.S. residential real estate, and more!
- After a brief slowdown to begin the summer, data center construction planning momentum picked up in July, again shining as the brightest sector in building. (Zachary Phillips, Construction Dive)
- The number of finished multifamily construction projects declined last year — welcome news for multifamily operators eager to work through the recent supply wave — and a record share of new apartments were high-density. (Julie Strupp, Multifamily Dive)
- Fair housing advocacy groups sued the U.S. Department of Housing and Urban Development, claiming the agency’s funding restructuring drastically reduces their ability to receive funds from the Fair Housing Initiatives Program. (Ryan Kushner, Multifamily Dive)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Arizona Court of Appeals Clarifies Homeowners Association Open Meeting Requirements
June 29, 2026 —
Jill Casson Owen, Benjamin J. Hawkins & Stephen Wright - Snell & WilmerA Z N H Revocable Trust v. Sunland Springs Village Homeowners Association, No. 1 CA-CV 25-0424 (Ariz. Ct. App. Apr. 28, 2026)
OVERVIEW
The Arizona Court of Appeals issued an opinion clarifying how homeowners associations must conduct meetings under A.R.S. § 33-1804. The decision reinforces the legislative policy favoring transparency in association governance, bringing association meeting requirements more in line with the open meeting standards applicable to public bodies under A.R.S. § 38-431 et seq. (Arizona’s Open Meeting Law).
KEY HOLDINGS
1. All Voting and Formal Actions Must Occur in Open Meetings
The Court affirmed that association boards cannot vote or take formal action during closed (executive) sessions. Under A.R.S. § 33-1804(A), associations may close portions of meetings only for “consideration” of certain enumerated topics, such as legal advice, pending litigation, or personal/financial information about individual members. The Court interpreted “consideration” to mean discussion and deliberation, not voting. The Court noted that dictionaries define “consider” as “spending time thinking about a possibility” and “formulating an opinion,” which are processes that precede formal action. This interpretation mirrors how Arizona’s Open Meeting Law (A.R.S. § 38-431.03(D)) prohibits public bodies from voting in executive session.
Reprinted courtesy of
Jill Casson Owen, Snell & Wilmer,
Benjamin J. Hawkins, Snell & Wilmer and
Stephen Wright, Snell & Wilmer
Ms. Owen may be contacted at jowen@swlaw.com
Mr. Hawkins may be contacted at bhawkins@swlaw.com
Mr. Wright may be contacted at swright@swlaw.com
Read the full story...