The Chambers USA 2026 Guide recognized attorneys Tim Davis, Managing Partner, and Nancy Frantz, Chair of the Real Estate Group, for Real Estate: Finance in the state of Pennsylvania. Randy Maniloff, Partner, Patricia Santelle, Chair Emeritus/Former Managing Partner, and Robert Walsh, Partner were ranked for Insurance in Pennsylvania, and Thomas Pinney, Partner, was ranked in Pennsylvania for Bankruptcy/Restructuring. In the state of Maryland, Partners David Gilliss and Eric Korphage were recognized for their work in Construction.
Read the full story...Reprinted courtesy of
White and Williams LLP
Achieving Sustainability Through Design Build Delivery: Part II – A Framework for Managing Sustainability Objectives on Private Commercial Construction
October 06, 2026 —
Jennifer Harris, Tiffany Harrod & Joshua Pruett - ConsensusDocsPart I of this series traced the history and development of sustainability in construction and explained why design-build (“DB”) contracting is particularly well suited to achieve sustainability objectives. But selecting DB contracting does not by itself ensure a sustainable outcome. The parties must define their sustainability objectives with precision, establish measurable performance criteria and identify who will measure compliance with the criteria, and also draft contract terms that clearly and fairly allocate the associated responsibilities and risks. Otherwise, the completed project may fall short of its sustainability objectives and expose the parties to claims, disputes, and litigation. Part II offers a non-exhaustive list of practical guidance for addressing these issues and reducing those risks.
This article references the ConsensusDocs 310 Green Building Addendum, in conjunction with an agreement between the Owner and the Design-Builder (e.g., ConsensusDocs 415)
[1],
[2] and AIA Document E204–2017 Sustainable Projects Exhibit,
[3] together with AIA A141,
[4] as its contractual baseline. The five-part framework that follows is a roadmap for allocating sustainability risk between private owners and design-builders: define the requirements, identify hidden performance guarantees, map out the sustainable objective, address third-party certification risk, and track performance against agreed benchmarks.
Reprinted courtesy of
Jennifer Harris, Peckar & Abramson, P.C.,
Tiffany Harrod, Peckar & Abramson, P.C. and
Joshua Pruett, Peckar & Abramson, P.C.
Ms. Harris may be contacted at jharris@pecklaw.com
Ms. Harrod may be contacted at tharrod@pecklaw.com
Mr. Pruett may be contacted at jpruett@pecklaw.com
Read the full story...
Insurer’s Motion to Dismiss Bad Faith Claim Denied
November 02, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer’s motion to dismiss the insured’s claim for breach of the covenant of good faith and fair dealing, but granted the motion to dismiss the claim for declaratory judgment. Jimenez v. State Farm Fire & Cas. Co., 2026 U.S. Dist. LEXIS 182079 (D. Conn. Aug. 15, 2026).
The insured owned a two-family property which was insured by State Farm. After a fire damaged the property, the insured submitted a claim to State Farm. The policy provided for Fair Rental Value coverage “[w]hen a loss insured causes that part of the residence premises rented to others or held for rental by you to become uninhabitable.”
Before the fire, the insured alleged that he rented part of the property under an oral lease agreement. In support of his claim for Fair Rental Value, the insured alleged that he provided State Farm with bank deposit receipts demonstrating that he collected rent in cash. The insured further alleged that his rental ledger was destroyed in the fire.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Southwest Super Lawyers Recognizes 50 Snell & Wilmer Attorneys in 2026 Rankings
June 15, 2026 —
Snell & WilmerPHOENIX (April 22, 2026) – Snell & Wilmer is pleased to announce that 50 attorneys in the Phoenix and Tucson offices have been selected for inclusion in the 2026 Southwest Super Lawyers publication. Of those 50, four were recognized for the first time and 24 were recognized as Southwest Rising Stars. Super Lawyers is a listing of lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The selection process is multi-phased and includes independent research, peer nominations, and peer evaluations. Super Lawyers was first published in 1991 by Law & Politics and was acquired by Thomson Reuters, Legal in February 2010. Thomson Reuters is a leading source of information for businesses and professionals. The below Snell & Wilmer attorneys have been selected for inclusion in the 2026 Southwest Super Lawyers rankings.
Read the full story...Reprinted courtesy of
Snell & Wilmer
Prefatory Contract Language Cannot Be Used to Create an Ambiguity with Operative Provisions
May 12, 2026 —
David Adelstein - Florida Construction Legal UpdatesContract drafting and interpretation matters.
A case dealt with the potential conflict with prefatory language in an agreement compared with operative provisions in the agreement. The trial court held that the operative provisions control. I discussed this case
here where the appellate court reversed based on the prefatory language.
But, through a motion for rehearing, the appellate court reconsidered its position and affirmed the trial court based on the operative provisions, mainly that the prefatory language cannot be used to create an ambiguity with operative provisions. Consider this explanation in affirming the trial court:
Because the trial court correctly found that the initial language in the contract was prefatory and could not be used to create an ambiguity in the remainder of the contract, we affirm the final judgment.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Appeals Court Upholds Skanska, Granite Win in ‘I-4 Ultimate’ JV Dispute
June 15, 2026 —
Bryan Gottlieb - Engineering News-RecordA federal appeals court has upheld a lower court’s decision requiring The Lane Construction Corp. to pay roughly $79 million in damages, plus interest, to joint venture partners Skanska USA Civil Southeast and Granite Construction for work on Florida’s I-4 Ultimate highway megaproject in Orlando, which was completed in 2022.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
Federal Court Strikes Down New York’s Climate Superfund Act: What It Means for the “Polluter Pays” Movement
September 28, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogA federal judge in the Northern District of New York has struck down New York’s
Climate Change Superfund Act, ruling that the “polluter pays” climate law is preempted by federal law and “simply beyond the limits of state law.” The court concluded that the Clean Air Act (CAA) does not authorize New York’s compensation scheme, which calculates liability based on greenhouse gas (GHG) emissions attributable to worldwide fossil fuel extraction and refining. It separately held that any cost-recovery demand against a foreign producer would be preempted under the constitutional foreign affairs doctrine, which limits state intrusion into matters committed predominantly to the federal government. The court directed the parties to file a status report by September 14, leaving the form of further relief unresolved. In practical terms, the court has decided that the Act is preempted and cannot be enforced but has not yet determined the precise terms of its final order, including whether to formally enjoin its enforcement.
The
decision in West Virginia v. James, Case No. 1:25-cv-00168 (N.D.N.Y. Aug. 31, 2026), issued by Chief U.S. District Judge Brenda K. Sannes, who was appointed by President Obama, marks the first judicial invalidation of a state climate superfund statute and carries significant implications for the
climate superfund landscape and the three remaining
lawsuits challenging these laws.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
Conditional Payment Bond Consideration-Make Sure There Is Pay-If-Paid Provision
June 29, 2026 —
David Adelstein - Florida Construction Legal UpdatesIf a general contractor is going to have a conditional payment bond, it needs to ensure it subcontracts contain pay-if-paid or pay-when-paid provisions. This conditional payment language in subcontracts is the general contractor’s defense that it doesn’t have to pay a subcontractor UNTIL owner has paid the general contractor for the subcontractor’s work.
The general contractor (and the surety) can look at the conditional payment bond with the s. 713.245 legend stamped on its face designating the conditional nature of the bond, and assume the conditional structure is locked in against the bond: no payment from the owner, no obligation to the subcontractors under the bond. But what happens when the subcontracts contain no express conditional payment language despite having a valid conditional payment bond?
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at