The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Your AEC Firm Has a Memory Problem. Here Is How to Fix It
June 01, 2026 —
Aarni Heiskanen - AEC BusinessAEC companies trying to operationalize AI often find they lack the data foundation on which to build. There may be an abundance of data hidden in documents, but you can’t reliably use it for AI.
The lack of data quality was a key topic discussed at the AI in AEC 2026 conference. During the event, I met many experts working to solve this problem, including
Pavlina Nikolova,
Egnyte‘s EMEA AEC Practice Lead. The chat and her presentation highlighted the challenges and ways to overcome them.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
U.S. Supreme Court Decision May Negate State Law Requirement to File a Certificate of Merit with the Complaint in a Federal Action Against a Design Professional
April 27, 2026 —
Christopher Olsen & Phillip Boldt - ConsensusDocsTo deter frivolous and unfounded claims against design professionals, states throughout the country have enacted statutes which generally require litigants to furnish a formal certification of merit (“COM”) from a qualified expert or face potential dismissal of their lawsuit. These COM statutes can impose a significant front-end burden on claimants who must pay an expert to review project records, interview the project team, and prepare a formal report before the lawsuit can be filed—often regardless of the amount in controversy. However, in light of a recent U.S. Supreme Court decision in a medical malpractice case, most, if not all of these statutes, may no longer be enforceable in federal court. This article examines the recent decision in Berk v. Choy, 146 S. Ct. 546 (2026), the decisions thus far which have applied Berk to invalidate COM statutes, and other categories of statutes applicable to the construction industry which may face a similar fate.
The U.S. Supreme Court Decision (Berk v. Choy)
In Berk, the plaintiff, Harold Berk, sued a doctor for medical malpractice under Delaware law in Delaware federal court. 146 S. Ct. at 551. Under Del. Code, Tit. 18, § 6853(a)(1), an affidavit of merit (like a COM) must accompany a complaint alleging medical malpractice. Id. Berk failed to include an affidavit of merit with his complaint. Id. at 552. Applying Delaware state law, the federal court dismissed Berk’s medical malpractice claim. Berk appealed to the Third Circuit, arguing that the affidavit of merit required by § 6853(a)(1) is unenforceable in federal court because it is more onerous than the Federal Rules of Civil Procedure. The Third Circuit affirmed the District Court’s ruling, finding § 6853(a)(1) enforceable in federal court.
Reprinted courtesy of
Christopher Olsen, Peckar & Abramson, P.C. and
Phillip Boldt, Peckar & Abramson, P.C.
Mr. Olsen may be contacted at colsen@pecklaw.com
Mr. Boldt may be contacted at pboldt@pecklaw.com
Read the full story...
Inaccurate Representations Can Lead to Differing Site Conditions Claim
May 26, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn the
prior posting, I discussed a case dealing with a differing site condition. In that case, the owner did not have an affirmative duty to make a representation and there was no inaccurate representation made by the owner that misled the contractor.
Well, what about when there is an inaccurate misrepresentation regarding the site? This was the circumstance in an older Florida case where a dredging contractor had a successful differing site conditions claim. See Jacksonville Port Authority v. Parkhill-Goodloe, Co., Inc., 362 So.2d 1009 (Fla. 1st DCA 1978).
The government provided inaccurate information as to the lack of rock that would be encountered during the dredging that was relied on by the dredging contractor. But the government had “
superior knowledge” that there was rock in an adjacent location based on a prior claim from a contractor, yet the government did not disclose the possibility that rock could be encountered.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
The GKN Aerospace Chemical Release and the Laws Designed to Address It
July 06, 2026 —
Sean M. Sherlock - Snell & WilmerOn May 21, 2026, a 34,000-gallon storage tank at the GKN Aerospace facility in Garden Grove, California began leaking methyl methacrylate (MMA), a volatile and highly flammable industrial chemical used to manufacture high-strength acrylic plastics. GKN Aerospace makes advanced military and commercial transparencies, such as aircraft canopies, windshields, cabin windows, bullet-resistant glass, and spacecraft windows.
In polymer chemistry lingo, MMA is known as a monomer. Monomers are like individual links to a chain. Under the right conditions they link up (react) with each other to form long-chained polymers, or plastics. MMA is an unstable monomer that requires controlled storage conditions to avoid setting off a polymerization (chain) reaction.
According to early reports, the MMA tank at GKN Aerospace overheated. The cause of the overheating is not yet clear, but the overheating may have created conditions enabling the MMA to initiate polymerization, which in turn generated heat, which in turn generated pressure, activating the tank’s pressure-relief system and releasing MMA vapor into the atmosphere. Concerns about a runaway reaction, massive release, and explosion led the Orange County Fire Authority to order evacuation of approximately 40,000 residents and closure of thirteen schools.
Read the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
Real Estate & Construction News Roundup (3/11/25) – An AI Inflection Point for Hotels, Investor Pivot in Build-to-Rent and Looming Legislation for Single-Family Investors
March 24, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, lodging demand for World Cup brings growth, commercial property management firms use of AI becomes firmer, construction industry shows slow start to the year, and more!
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Anti-Concurrent Causation Clause Prevents Coverage for Collapse
April 27, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court affirmed the decision of the trial court granting summary judgment to the insurer after agreeing that the policy’s anti-concurrent causation clause barred coverage. Lido Hospitality, Inc. v. AIX Specialty Ins. Co., 2026 Iii. App. Unpub. LEXIS 133 (Ill. Ct. App. Jan. 27, 2026).
One of the brick veneer walls of the Lido Motel collapsed during a windstorm. Lido reported the loss it its insurer, AIX. AIX investigated and determined that the brick veneer collapsed due to pervasive wear and tear and corrosion of the underlying infrastructure that secured the veneer- specifically the components that anchored or tied the masonry veneer to the underlying wooden substrate.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Massachusetts Construction Industry Continues to Wait While Prompt Payment Law Is Put to the Test
March 31, 2026 —
Catherine Maronski - Construction Law ZoneEarlier this month, the Massachusetts Supreme Judicial Court (SJC) heard argument in J.C. Cannistraro, LLC v. Columbia Construction Co. et al., a dispute concerning the state’s Prompt Payment Act (PPA). Although a decision has yet to be issued, it could potentially pose widespread implications for high-value private construction projects moving forward – and perhaps backwards.
The PPA, G. L. c. 149, § 29E, enacted by the Massachusetts Legislature in 2010, has become a keystone in the construction industry. It was enacted to address, in part, downstream cash flow issues that tend to pervade construction projects by mandating a series of strict guidelines for submitting, and responding to, payment applications for private projects valued over $3,000,000. Amongst these requirements are set timeframes to respond to an application, as well as what must be contained in an application rejection. Critically, if an owner or upper-tier contractor fails to fully comply with all the statutory requirements in response to a proper payment application, the application is automatically “deemed to be approved” and payable. Significantly, however, this is not always the end of the line.
Read the full story...Reprinted courtesy of
Catherine Maronski, Robinson ColeMs. Maronski may be contacted at
cmaronski@rc.com