Florida’s Proposed HB 255: A Quiet Shift That Could Reshape Condo Defect Liability
January 21, 2026 —
Matt Maranges - ConsensusDocsIn Florida, developers and contractors work under strict clocks. Section 95.11(3)(b), Florida Statutes, sets two firm deadlines for construction claims: a four-year statute of limitations and a seven-year statute of repose. Those timelines govern when an owner or condominium association may pursue claims for alleged defects. Once the repose period ends, the claim is barred regardless of when the problem surfaced.
Condominium law complicates that scheme. Section 718.124 delays the start of the limitation and repose periods on association claims until control of the board shifts from the developer to the unit owners. The logic is simple: a developer-controlled board cannot be expected to sue the developer. The practical effect is more sweeping. If turnover occurs late in the life of a project, the repose period may remain tolled for years, extending exposure far beyond the seven years that apply everywhere else.
Read the full story...Reprinted courtesy of
Matt Maranges, Jones WalkerMr. Maranges may be contacted at
mmaranges@joneswalker.com
Course of Conduct Can Serve as Waiver or Modification of Parties’ Contract
December 22, 2025 —
David Adelstein - Florida Construction Legal UpdatesWhen you enter into a contract, the language in the contract means something. And if you don’t follow what the contract says, it will be used against you. It can be used to support the argument that you breached the contract. Or it can be used to demonstrate your lack of compliance with the contract does not entitle you to the recourse you are seeking. However, this does not mean under certain circumstances the language of the contract cannot be waived or modified by the parties’ course of conduct.
In a recent dispute, an owner and contractor sued each other under a cost-plus contract. The contractor recorded a construction lien and moved to foreclose its construction lien. The owner claimed it was over-charged and claimed the contractor breached the contract. The contractor also claimed it was not timely paid with improperly withheld payment applications. The trial court granted summary judgment in favor of the contractor, which was affirmed on appeal based on the parties’ course of dealing:
The trial court concluded that, although the parties’ cost-plus contract required that all change orders be approved in writing, the summary judgment record established that this provision was routinely waived by the parties’ course of dealing: [owner] would orally request changes to the project; [contractor] would perform those changes; and [owner] would pay the invoices for those changes.
Moscato Corp. v. Mutchnik Construction Group, Inc., 411 So.3d 570 (Fla. 3d DCA 2025)
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Lost in Translation: AEC Tech’s Missing Role
May 12, 2026 —
Aarni Heiskanen - AEC BusinessI once visited a construction site where the contractor’s headquarters had commissioned a tech company to build an on-site quality-inspection application. The developer had admitted to the site engineer that they had never set foot on a construction site before. The engineer showed me what he was actually using: his own phone camera and an Excel sheet. The new app did not map to how work actually happened on site.
This is not an isolated story. The vendor builds something technically coherent but operationally disconnected. The client, somewhere up the chain, had fallen in love with the idea of the solution before anyone had built an honest business case for it.
The result is a tool that gets demonstrated at a board meeting but isn’t used in the field.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Louisiana Enacts Important Tort Reform Legislation
May 12, 2026 —
Lee M. Peacocke & Benjamin Perkins - Lewis BrisboisThe Louisiana legislature enacted tort reform legislation in 2025 to address the increasing cost of insurance in Louisiana and to provide some predictability to the Louisiana legal system. While our colleagues, Jenny Michel and Jennifer Kretschmann, have provided an excellent and comprehensive analysis of the legislation in their article entitled “Louisiana State Legislature 2025 Regular Session: Tort Reform - Acts & Vetoed Insurance Bill,” which can be found
here, this article examines the anticipated impact of the tort reform legislation on personal injury trials in federal and state courts in Louisiana.
The most significant reform involves the institution of a modified defense of contributory negligence, which went into effect on January 1, 2026. Since 1996, Louisiana had operated as a pure comparative fault state; the liability of each party whose fault caused damages was to be allocated among the respective parties based upon their appropriate percentage of fault, regardless of the legal theory of liability asserted against each party. Thus, a plaintiff 55 percent at fault could recover 45 percent of their damages from the liable defendants. The 2025 Tort Reform Amendments now prohibit a plaintiff in a personal injury action from recovering any damages if they are found to be 51 percent or more at fault for their damages. The 55 percent at-fault party in the example above is now prohibited from recovering any damages from any party. Importantly, this new legislation now requires the trial court to instruct the jury that if they find a plaintiff to be more than 50 percent at fault, then the plaintiff will not recover any damages.
Reprinted courtesy of
Lee M. Peacocke, Lewis Brisbois and
Benjamin Perkins, Lewis Brisbois
Mr. Peacocke may be contacted at Lee.Peacocke@lewisbrisbois.com
Mr. Perkins may be contacted at Benjamin.Perkins@lewisbrisbois.com
Read the full story...
A New Vision for Safety: Construction Safety Week’s Five-Year Plan
February 17, 2026 —
Adam Jelen - Construction ExecutiveConstruction Safety Week has long been a powerful show of force—a catalyst for bringing the industry together and focusing on the critical importance of health and safety. Over the last decade, we’ve made meaningful strides: advancing best practices, transitioning from hard hats to helmets, shedding light on vital issues such as mental health, fostering a culture of care and accountability and creating partnerships and initiatives that improve jobsite safety.
Building on the progress we’ve made, we’ve launched a bold five-year vision to bring everyone together with trust and respect and to drive alignment in how safety is understood, owned and engineered at every step of the project. This is an industrywide effort to further deepen the culture of care centered around respect for the skilled craft and through all aspects of a project where all team members share this responsibility, this respect, across every phase: design, planning, construction and beyond.
Reprinted courtesy of
Adam Jelen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
IEEPA Tariff Refunds: CBP Launches CAPE Process
April 27, 2026 —
David J. Creagan, Guido Antolini, Bruce W. MacLennan & Gary P. Biehn - White and Williams LLPOn April 20, 2026, U.S. Customs and Border Protection (CBP) launched the first phase of the Consolidated Administration and Processing of Entries (CAPE) tool in the Automated Commercial Environment (ACE) portal to administer refunds of duties imposed under the International Emergency Economic Powers Act (IEEPA) through a streamlined electronic filing process.
Background
In February 2026, the U.S. Supreme Court held that certain tariffs imposed under IEEPA were unlawful. Subsequent proceedings before the U.S. Court of International Trade required CBP to develop a scalable refund process applicable not only to litigants but also to non-plaintiffs. According to CBP and court filings, approximately 330,000 importers paid or deposited an estimated $166 billion in IEEPA duties across more than 53 million entries. In response, CBP developed CAPE as an electronic, consolidated refund mechanism within ACE.
Reprinted courtesy of
David J. Creagan, White and Williams LLP,
Guido Antolini, White and Williams LLP,
Bruce W. MacLennan, White and Williams LLP and
Gary P. Biehn, White and Williams LLP
Mr. Creagan may be contacted at creagand@whiteandwilliams.com
Mr. Antolini may be contacted at antolinig@whiteandwilliams.com
Mr. MacLennan may be contacted at maclennanb@whiteandwilliams.com
Mr. Biehn may be contacted at biehng@whiteandwilliams.com
Read the full story...