Insured’s Bad Faith Claim Survives Summary Judgment
July 13, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer’s motion for partial summary judgment to dispose of the insured’s bad faith claim was unsuccessful. Page v. State Farm Lloyds, 2026 U.S. Dist. LEXIS 102293 (E.D. Texas March 18, 2026).
Plaintiff insured alleged that hail and a windstorm caused damage to his property. The damage was reported to the defendant insurer. A claims adjuster inspected the property. Defendant then paid plaintiff $24,493.06, which was the total of the estimated damage minus depreciation and the deductible.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contractor Dispute Resolution Framework and Prevention
July 06, 2026 —
Construction ExecutiveWHAT DEFINES A CONTRACTOR DISPUTE RESOLUTION FRAMEWORK
A contractor dispute resolution framework is a structured system of contractual terms, governance processes and escalation pathways designed to prevent, manage and resolve conflicts between contracting parties with minimal disruption to cost, schedule and performance.
The framework operates as both a preventive control and a corrective mechanism. Preventive elements establish clarity in scope, expectations and accountability before work begins. Corrective elements define how disagreements are identified, documented, escalated and resolved once they arise.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Introducing the Updated 2026 Pillsbury Guide to Data Centers
June 08, 2026 —
Gravel2Gavel Team - Gravel2Gavel Construction & Real Estate Law BlogSince the initial publication of the Pillsbury Guide to Data Centers in 2025, the market has continued to evolve—most notably with respect to power availability, energy strategy, tax and incentives planning, and investment activity across the sector. While many of the legal, commercial and regulatory frameworks addressed in the original Guide remain durable and relevant, recent developments warranted targeted updates and additions.
The
2026 edition expands and updates our energy-focused content to reflect the increasingly central role of power procurement, interconnection and long-term energy strategy in data center development. We have incorporated new materials addressing power purchase and interconnection agreements, solar and other renewable energy solutions, advanced reactor designs, and nuclear-powered data centers projects, including an updated project tracker. We have also added new analysis covering state and local tax considerations and incentive structures relevant to data center development and operations, as well as current M&A and private equity trends shaping investment in the sector.
Read the full story...Reprinted courtesy of
Gravel2Gavel Team
Segal McCambridge Recognized in 2026 Chambers USA Rankings
June 15, 2026 —
Segal McCambridgeLos Angeles, CA, June 8, 2026 -
Segal McCambridge is pleased to announce that the firm has been recognized as a leader by Chambers USA in California. The firm is listed in the Chambers-ranked department, receiving a
Band 5 ranking for construction in California. The ranking further reinforces the firm's commitment to supporting California's construction market, from owners to developers and contractors, in high-stakes disputes statewide.
"Chambers' research-driven process and independence make this acknowledgment especially meaningful. We're proud of this ranking and grateful to our clients and colleagues whose consistent trust and collaboration make our work possible," said Jason P. Eckerly, Managing Shareholder of Segal McCambridge.
Chambers and Partners is widely regarded as one of the legal industry's most respected and independent ranking organizations. Operating across 200 jurisdictions and relied on in more than 70 countries, Chambers has, since 1990, conducted rigorous research to identify leading lawyers and law firms through a methodology that combines analysis of firm capability, achievement, and market presence through interviews and assessment of recent matters across more than 1,400 U.S. ranking tables, covering all 50 states, Washington, DC, and nationwide.
About Segal McCambridge
Segal McCambridge has built a reputation as a national law firm of accomplished trial attorneys for almost four decades. Founded in 1986, the firm has grown from a four-lawyer shop in Chicago to a firm with more than 20 offices nationwide. The firm routinely counsels and defends clients, including Fortune 500 companies, corporations, and individuals, across the United States in complex litigation matters, including, but not limited to: asbestos, class action, construction, employment, environmental, food and beverage, insurance coverage and bad faith, life sciences, product liability, professional liability, technology and cyber risk, transportation, and warranty. For more information, visit: www.segalmccambridge.com.
Doctrine of Substantial Performance When It Comes to Payment
July 27, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent non-construction case touches upon the doctrine of substantial performance when it comes to payment. In this case, a club was to make two payments to secure a rapper’s attendance. The first payment was made. The second payment was made but was a few hundred dollars short of the agreed amount. The rapper did not show up. The club claimed it substantially performed its obligations. At first glance, the argument makes sense because the second payment fell only a few hundred dollars short. But that wasn’t the case when it comes to pre-commencement payment obligations:
Substantial performance applies only when the variance from the contract terms “is inadvertent or unintentional and unimportant so that the work actually performed is substantially what was called for in the contract.” However, when one party agrees to pay the other on or before a specific date, time is of the essence, and the payor is required to pay the payee on or before that date. “There is almost always no such thing as ‘substantial performance’ of payment between commercial parties when the duty is simply the general one to pay. Payment is either made in the amount and on the date due, or it is not.”
Big Gate Records, LLC v. Washington, 51 Fla.L.Weekly D1281a (Fla. 2nd DCA 2026) (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
A Nuclear Power Hangover: Controversies Plague New York's Indian Point Plant Cleanup
November 02, 2026 —
Richard Korman - Engineering News-RecordMichael Tromblee was in for a late night. Of the many after-business-hour duties he performs as superintendent of the Hendrik Hudson school district about 25 miles north of New York City, attending meetings of a board overseeing cleanup of the Indian Point nuclear power plant, located in Buchanan, N.Y., was an infrequent but necessary chore. Since the plant shut down in 2021 and gradually stopped paying taxes to support the school district's students, between one-fourth and one-third of its annual budget funding vanished, and state transitional funds provided to bridge that gap will expire after the 2027-28 school year. Last year, Tromblee described the lost power plant tax revenue, about $25 million annually, as “a financial hit that no school district is built to withstand.”
Read the full story...Reprinted courtesy of
Richard Korman, Engineering News-RecordMr. Korman may be contacted at
kormanr@enr.com
One Building, Six Owners, One Defective Stucco System: How Do You Coordinate Repairs?
November 02, 2026 —
David McLain - Colorado Construction Litigation BlogThe Problem: Six Homes, One Building Envelope
Consider a hypothetical six-unit townhome building in Colorado. Each residence is individually owned. There is no homeowners association responsible for maintaining the building’s exterior, no commonly owned building envelope, and no association empowered to pursue construction defect claims on behalf of all six homeowners. Instead, the development relies on individual ownership, recorded easements, and party wall agreements to govern relationships among neighboring owners.
Although the residences are separately owned, they share a continuous exterior stucco system, including interconnected flashing, waterproofing, and architectural transitions.
One homeowner discovers water intrusion and retains an expert who identifies defects in the stucco installation. The expert recommends removing and replacing the stucco on the homeowner’s residence. However, because the exterior cladding and waterproofing systems are interconnected, the proposed repair may require work extending beyond the boundaries of that homeowner’s property.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Sometimes a General Damages Assessment is Enough. . .
July 06, 2026 —
Christopher G. Hill - Construction Law MusingsIt has been a while since I last posted here at
Construction Law Musings. Life, law practice, and “blogger’s block” have taken their toll on the posting schedule. Hopefully this will be one of several upcoming posts now that the litigation schedule has lightened a bit over the summer.
Today’s post is about damages. Specifically damage to a homeowner’s roof and her legal damages therefor. That last is of course a sentence that only a
construction attorney (or other litigator) could possibly craft and have it make sense. Now, on with the case. . .In
Hardesty Construction, Inc. v. Weedon, the facts are as follows:
Ms. Weedon had hail damage to the roof of her home. She hired Hardesty Construction to repair and replace the roof. After the first roof was installed and failed inspection, a second roof was installed. The issue was that the first roof had a warranty and the second roof, installed similarly to the first (and allegedly with the same construction issues according to Ms. Weedon’s expert), was not provided with the promised warranty. As one may expect, Weedon sued Hardesty and Hardesty Construction for fraudulent inducement and breach of contract. At trial, Weedon testified, without objection, that her home was worth $40,000 less because of Hardesty Construction’s work, which was based partially on quotes Weedon received to fix the roof. The Circuit Court granted Hardesty Construction’s motion to strike Weedon’s fraudulent inducement claim, but not her other claims. A jury awarded Weedon $30,253.30 on her breach of contract claim. Hardesty Construction appealed, arguing the Circuit Court erred in (a) allowing the jury to consider Weedon’s valuation testimony because it was not based on her personal knowledge and (b) denying its motion to strike based on insufficient evidence as to damages. Weedon assigned cross-error in the Circuit Court’s decision to grant the motion to strike her fraudulent inducement claim against Samual Hardesty.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at