Wisconsin Supreme Court Finds Coverage Under Ensuing Loss Provisions
September 29, 2026 —
Tred R. Eyerly - Insurance Law HawaiiReversing the trial court’s grant of summary judgment to the insurer, the Wisconsin Supreme Court determined that genuine issues of material fact existed on whether ensuing losses as defined in the policy were covered. Cincinnati Ins. Co. v. Ropicky, 2026 Wisc. LEXIS 302 (Wis. July 7, 2026).
The insured suffered damage during a storm on May 11, 2018, when rainwater poured into the home. The insureds gave notice to their insurer, Cincinnati. Upon inspection, Cincinnati determined that water intrusion resulted from multiple construction defects in the home. In the front of the home, water entered through a gap in the stone veneer. The inspector also concluded that the damage from rainwater was not just from the May 11, 2018, storm, but damage had occurred from prior storm events.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Chambers USA Recognizes Hunton’s Insurance Coverage Practice in 2026 Guide
June 29, 2026 —
Hunton Insurance Recovery BlogHunton is pleased to announce that its insurance coverage practice was recognized nationally for Insurance: Dispute Resolution – Policyholder in the recently released 2026 Chambers USA guide. The team also received state rankings in Florida (Insurance: Dispute Resolution), Georgia (Insurance), the District of Columbia (Insurance: Policyholder), and Massachusetts (Insurance).
In addition to the insurance team’s group recognition across multiple states, the 2026 guide included individual rankings for
Lorelie “Lorie” S. Masters (USA Nationwide and District of Columbia),
Latosha M. Ellis (District of Columbia),
Michael S. Levine (District of Columbia),
Koorosh “KT” Talieh (District of Columbia),
Walter J. Andrews (Florida),
Andrea DeField (Florida),
Cary D. Steklof (Florida),
Lawrence J. Bracken II (Georgia), and
Geoffrey B. Fehling (Massachusetts).
Read the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
We’re Burning Tokens to Clean Up Bad PDFs
August 24, 2026 —
Aarni Heiskanen - AEC BusinessLast Thursday, researchers from Tampere and Aalto universities reported on preliminary results of two AI- and digitalization-related projects. One project demonstrated how AI can automate the Bill of Materials process; the other tried to quantify the impact of data-driven construction and AI. The conclusion was that AI-powered automation can dramatically increase productivity, but unevenly. However, the substantial benefits may come from better outcomes rather than project efficiency.
Various standards, company-specific practices, project-specific schemas, and traditions are designed for humans to comprehend. 2D drawings and text documents as PDF files, Excel sheets, and design and planning software have the information, but not the data in ideal form for automation.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Turnover Traps for Community Associations: Investigate First, Release Claims Later
April 14, 2026 —
Nicholas B. Vargo - Ball Janik LLPTurnover of a community association from developer control to owner control is a uniquely vulnerable moment. Developers are increasingly presenting Florida condominium and homeowners’ associations with “standard” settlement or release agreements at turnover, often being framed as routine steps to finalize the transition of control. In reality, these agreements can have sweeping consequences, including the release of construction-defect claims before the association has conducted any meaningful independent evaluation.
The developer has years of project knowledge and access to plans, subcontractors, and internal records. The newly elected board is just beginning to organize, obtain documents, and understand the property’s condition. Many defects, especially those involving roofing, waterproofing, windows, or structural components, are latent and not yet visible. Signing a release at this stage means the association is making a binding decision under conditions of uncertainty, without full information, to release all future potential claims.
Over the last few years, there has been a rise in reports of developers offering a packaged deal: they agree to complete certain repairs, often minor punch-list or cosmetic items, and to “forgive” an alleged financial deficit (often around $50,000) supposedly owed by the association from the developer-control period. In exchange, the association is asked to sign a broad release covering all claims, including known and unknown construction defects. To a new HOA board that received their community with limited operating and reserve funds, they are left with a difficult decision to either accept the developer’s offer or assess their owners to pay this alleged debt.
These agreements are occasionally presented through community management companies, which may describe them as “standard” or "routine.” Whether due to misunderstanding or influence from the developer, management companies can unintentionally reinforce the idea that signing is expected. Any recommendation provided to HOAs about whether to sign these releases could open community management to liability down the road. The best practice for both associations and community managers is to refer any agreements to be reviewed by general counsel for the association.
The following two case studies illustrate the real-world consequences:
Case Study One: A newly transitioned board relies on its management company to negotiate with the developer-builder to resolve irrigation issues, pond concerns, and signage deficiencies, along with forgiving an asserted financial shortfall. In exchange, the board signs a broad release covering all claims, including latent defects.
Within a year, several punch-list items remain incomplete, and more serious issues arise. When the association demands completion, the developer delays, prompting the association to seek advice on how to enforce the settlement agreement. The association hires counsel to hold the developer responsible for both the previously agreed-upon items and newly identified construction defects. However, when the association brings claims against the developer, the developer points to the release of all potential construction defects in the community. Thus, the only remaining remedy is limited to enforcement of the specific punch-list terms. The community, still relatively new, has no viable claims against the developer-builder for the construction defects. With warranties expired and the release, the association must fund repairs through special assessments, despite defects that would otherwise have been actionable.
Case Study Two: A community is presented with a similar agreement as above. The management company encourages execution, suggesting it is standard and even telling the board to “name your price.” The developer also pressures the newly elected board to sign.
Instead of signing, the board consults with their attorney. Counsel advises the board not to sign the release and recommends further investigation. Engineers are retained and identify early indicators of broader issues, including stucco cracking, water intrusion, and irrigation deficiencies. Based on this information, the association declines to sign the release. Subsequent evaluation reveals potentially significant construction-defect claims, allowing the community to pursue recovery that would have been lost under the proposed agreement.
These scenarios underscore a fundamental point: signing a release at turnover is not an administrative formality—it is a major legal decision. Board members act in a fiduciary capacity on behalf of their community, and their decisions can bind all current and future owners. At turnover, an association’s right is to investigate and pursue claims. Preserving that right until a full and independent evaluation is completed is not adversarial—it is responsible governance.
Accordingly, associations should retain independent evaluations of the property and consult qualified legal counsel before signing any “standard” agreements, especially ones involving a release of future claims.
Nicholas B. Vargo is a partner in Ball Janik LLP’s Construction Practice Group. He may be reached at nvargo@balljanik.com.
Flatiron Said Disputed Concrete Mix Cost Millions on Large Caltrans Project
June 22, 2026 —
Elaine Silver & Richard Korman - Engineering News-RecordFor awhile in 2023, part of the California Dept. of Transportation's (Caltrans) Fix 50 HOV lane and resurfacing project in Sacramento itself needed to be fixed.
Reprinted courtesy of
Elaine Silver, Engineering News-Record and
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story...
Court Denies Cross Summary Judgment Motions on Coverage for Odors in Newly Purchased Home
October 06, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court denied cross motions seeking to establish whether the policy covered damage due to smells in the insureds’ newly purchased home. Akina v. State Farm Fire & Cas. Ins. Co., 2026 U.S Dist. LEXIS 162817 (W. D. Wash. July 22, 2026).
Plaintiffs bought a home in May 2024 but never conducted an inspection before purchasing the property. Before moving in, plaintiffs secured a homeowners’ polilcy from State Farm.
After moving in, plaintiffs began noticing smells in the house and started suffering from health symptoms. Plaintiffs learned from neighbors that the prior occupants had been witnessed in “drug activity.” Plaintiffs moved out of the house and had testing done. The home tested positive for methamphetamine pollution.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
4th Department Narrowly Interprets Professional Services
August 11, 2026 —
Craig Rokuson - Traub LiebermanIn the recent case of Cty. of Erie v. Selective Ins. Co. of Am., 2026 NY Slip Op 04092 (App. Div. 4th Dept.), New York’s Appellate Division, Fourth Department held that a general liability carrier for a construction manager owed additional insured coverage to the County of Erie, notwithstanding an exclusion in the construction manager’s policy for injuries arising out of professional services.
The underlying case involved injuries sustained when the underlying plaintiff fell off of her bicycle at a park owned by the County when she transitioned from the pavement edge to grass.
Read the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
The Most Expensive Signature to Not Get: Why Change Orders Matter
August 16, 2026 —
Kathryne E. Baldwin - Wilke FleuryGeorge Bernard Shaw has a quote we use a lot in my family: “The single biggest problem in communication is the illusion that it has taken place.” This is pertinent to contractors and homeowners alike because the cost of failing to get proper signatures on documents like construction contracts, and particularly, change orders, is heavy. Both contractors and homeowners are in the same boat as far as wanting to complete a job as swiftly as possible: contractors go on to their next job and homeowners can return to peace in their home. This is prime territory for either party to suggest the work be completed today and the contract or change order executed tomorrow, or even later. However, without a contract, there is no memorialization of the communication between the parties, which can lead to confusion and missed expectations on both sides.
Construction plans are rarely as neat and tidy as they originally seem to be. A contractor may uncover unforeseen conditions, an owner may request additional work or changes that require additional work, or weather interferes with project schedules or the work itself. Unfortunately, the signature that never gets collected can become one of the most expensive omissions on a project – for both sides.
Read the full story...Reprinted courtesy of
Kathryne E. Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com