Supply Chain Is a Legal Exposure—Not Just a Force Majeure Problem
September 08, 2026 —
Owen Newman - Construction ExecutiveThis is not another force majeure article. The supply-chain related legal exposure that contractors are carrying today—in sanctions risk, specification non-compliance, warranty exposure and regulatory volatility—extends well beyond what even a well-drafted force majeure clause protects.
An engineering, procurement and construction contractor on a gas-fired power plant discovers during commissioning that transformer oil in a critical unit contains Russian-origin naphthenic base oil, which is a prohibited source under Office of Foreign Assets Control sanctions. The contractor didn’t source it. A subsupplier two tiers below made the substitution when disruptions in the Strait of Hormuz tightened the primary supply chain for this specialty product and no one in the purchase-order chain flagged it. The procurement decision is long done and the documentation trail that should have caught it doesn’t exist.
Reprinted courtesy of
Owen Newman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Mr. Newman may be contacted at
oknewman@duanemorris.com
Court Denies Cross Summary Judgment Motions on Coverage for Odors in Newly Purchased Home
October 06, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court denied cross motions seeking to establish whether the policy covered damage due to smells in the insureds’ newly purchased home. Akina v. State Farm Fire & Cas. Ins. Co., 2026 U.S Dist. LEXIS 162817 (W. D. Wash. July 22, 2026).
Plaintiffs bought a home in May 2024 but never conducted an inspection before purchasing the property. Before moving in, plaintiffs secured a homeowners’ polilcy from State Farm.
After moving in, plaintiffs began noticing smells in the house and started suffering from health symptoms. Plaintiffs learned from neighbors that the prior occupants had been witnessed in “drug activity.” Plaintiffs moved out of the house and had testing done. The home tested positive for methamphetamine pollution.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insufficient Notice of Commencement and Construction Lien Rights
August 03, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice to Owner company will typically rely on the Notice of Commencement to serve Notices to Owners from lower tiers not in contract with the owner. However, when it comes to preparing the lien, a lienor should look beyond just the Notice of Commencement and also look to the property appraiser’s website as a backstop.
In a recent case, a window company had the homeowner sign the Notice of Commencement and then filled in the information. The company naturally did this for the convenience of the homeowner that probably was unfamiliar with the Notice of Commencement process. Regardless, information in the Notice of Commencement was inaccurate. It failed to include all the real property owners. Thus, when a payment dispute arose and a construction lien was prepared, it did not identify all of the real property owners. All of the real property owners were added later during the pendency of a lien foreclosure lawsuit. The trial court denied the lien because of the defective / insufficient Notice of Commencement — the lienor assumed the risk of error by filling out the information in the Notice of Commencement. The trial court further denied the lien holding that because the work did not commence within 90 days of the Notice of Commencement, the Notice of Commencement is void.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Real Estate & Construction News Roundup (8/19/26) – Single-Family Housing Investors Worry, Confidence in Multifamily REITs and Construction Backlog Falls
September 08, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, U.S. Chamber of Commerce creates Housing Advisory Council, a legal battle develops over new federal rules related to mortgage escrow accounts, hospitality dealmakers pursue ‘bigger, higher-conviction’ M&A, and more!
- In the wake of the 21st Century ROAD to Housing Act becoming law, the U.S. Chamber of Commerce has created a Housing Advisory Council with the goal of advancing market-driven policies that help increase housing supply and promote affordability. (Julie Strupp, Multifamily Dive)
- Investors in the single-family housing market are increasingly concerned about interest rates, rising insurance and home costs, and the ongoing war with Iran. (Diana Olick, CNBC)
- A legal battle is brewing over new federal rules related to accounts that hold money to pay homeowners’ property taxes and insurance payments. (Sarah Agostino, CNBC)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Insured General Contractor Prevails on Motion for Summary Judgment to Establish Builder’s Risk Coverage
July 06, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe general contractor’s motion for partial summary judgment successfully established that damage to footings in place before the policy period was covered after the collapse of a building. Big D Builders, Inc. v. Am Zurich Ins. Co., 2026 U.S. Dist. LEXIS 72012 (D. Idaho March 31, 2026).
Big D was the general contractor for building a new airplane hangar by erecting a 38,000 square foot structure. Before Big D began construction, the site of the hangar did not contain any pre-existing structures or buildings. Before completion of the hangar, it collapsed and caused extensive property damage.
The builder’s risk policy issued by Zurich covered certain aspects of the construction project for the policy period December 28, 2023, to December 28, 2024. Zurich accepted coverage for most of the damage but not for damage to footings and columns installed prior to the start date of the policy.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Connecticut Expands Construction Wage-Theft Liability and Prevailing Wage Recordkeeping Requirements
June 29, 2026 —
Anand Gupta & Guest Contributor - Construction Law ZoneThis post was co-authored by Labor + Employment group lawyer Christopher Costain, Hayden Eckblom (Summer Intern), and Pasqualina Fox-Mina (Summer Associate). Hayden and Pasqualina are not admitted to practice law.
On May 11, 2026, Connecticut Governor Ned Lamont signed into law Public Act 26-12, a wide-ranging bill centered around employee rights. Our colleagues in Robinson+Cole’s Labor, Employment, Benefits + Immigration group recently published a
legal update summarizing the key components of Public Act 26-12. Here, we focus on the Wage Theft and Prevailing Wage concepts in the bill that directly relate to the construction industry.
Wage Theft
With exceptions for public works and small residential projects, general contractors will be jointly and severally liable for any unpaid wages owed to an employee of a subcontractor of any tier on private construction projects, beginning with contracts entered into on or after January 1, 2027. As we know, there is a separate regime for public works projects involving payment bonds.
Read the full story...Reprinted courtesy of
Anand Gupta, Robinson & Cole LLPMr. Gupta may be contacted at
agupta@rc.com
Not All Warranty E-Mails Are Notices of Claim
October 20, 2026 —
David McLain - Colorado Construction Litigation BlogThere is a frustrating tendency in some Colorado construction defect litigation to treat virtually any written complaint about construction work as a statutory notice of claim under the Construction Defect Action Reform Act (“CDARA”). An e-mail complaining about cracked concrete. A request for warranty service. A message asking a builder to come inspect a leaking window. Years later, when the homeowner faces a statute-of-limitations defense, these routine communications are suddenly characterized as statutory notices of claim, with the convenient consequence that an otherwise untimely lawsuit becomes timely.
Enough is enough.
A warranty complaint is not a statutory notice of claim simply because a homeowner complains about construction. Courts and arbitrators should stop treating the two as interchangeable.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
GRSM Team Obtains Defense Verdict for Homeowners’ Association in Orange County Superior Court
August 11, 2026 —
Gordon Rees Scully MansukhaniA Gordon Rees Scully Mansukhani multi-state team, including Partners Christine Barker, Sean Ferron, and Keith Cramer, obtained a defense verdict on behalf of a homeowners’ association (HOA) in an Orange County Superior Court bench trial spanning two months.
The case began in 2022 when a homeowner sued after the Architectural Review Committee and HOA Board of Directors declined his teardown-and-rebuild plans due to view and aesthetic concerns. After a motion for summary judgment ruling in which the court found that the existing covenants, conditions, and restrictions (CC&Rs) did not protect views, the HOA held a special election to add explicit view protections to the CC&Rs. At the February 2025 trial call, the plaintiff sought leave to file a third amended complaint challenging the validity of that vote, drastically reframing the case from CC&R enforcement to one of election validity. A second plaintiff then filed a parallel action toward the end of the limitations period, and the two cases were consolidated.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani