What Massachusetts Contractors and Developers Can Learn from Cannistraro v. Columbia Construction
July 13, 2026 —
Anthony LaPlaca & Luke Marston - The Construction SeytIntroduction
On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.
[1]
Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a “factual and contractual basis for the rejection” and must be “certified as made in good faith.”
[2] In the absence of a timely certified notice, payment is “deemed to be approved” unless the payor properly rejects payment before it comes due.
[3]
Reprinted courtesy of
Anthony LaPlaca, Seyfarth Shaw LLP and
Luke Marston, Seyfarth Shaw LLP
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Mr. Marston may be contacted at lmarston@seyfarth.com
Read the full story...
Endra Rethinks MEP Design with AI
July 06, 2026 —
Aarni Heiskanen - AEC BusinessNiklas Lindgren, co-founder and CEO of Endra, joins the
AEC Business Podcast to discuss why his Stockholm-based startup is rebuilding MEP design from the ground up with AI. Endra recently raised $50 million in Series A funding and counts some of the world’s largest engineering consultancies as customers.
Niklas explains why Revit’s underlying data model is too coarse to support deep automation, and why Endra built its own granular 3D data model instead of working as a plugin. He describes Endra’s “spatial AI” approach to routing conduit and ductwork without clashes, and how the platform models entire electrical systems, from receptacle to transformer, inside a single source of truth.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
New Survey Reveals Overwhelmingly Optimistic Results on the Use of AI in Construction
May 14, 2026 —
Construction ExecutiveOn December 5, 2025,
CMiC and
Dodge released a
survey asking over 6,000 companies across various sectors of the construction industry their stance on artificial intelligence—whether they use it or not; whether they like it or not; whether they have or are planning to implement it or not; and so on. Considering its reputation for skepticism and reluctance when it comes to adopting new forms of technology, the construction industry pleasantly surprised CMiC and Dodge with its answers to these questions, with 87% of contractors believing AI will have a meaningful impact on construction.
“The research indicates the construction industry is nearing a tipping point for AI adoption,” says Steve Jones, senior director of industry insights at Dodge Construction Network, who sat down with Construction Executive to delve further into the survey questions and answers and what the industry’s current position on them means for AI’s future role in construction.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Water Reuse Emerges as a Critical Strategy for Data Center Development
June 22, 2026 —
Ashleigh Myers, Jillian Marullo & Jason Drogin Atwood - Gravel2Gavel Construction & Real Estate Law BlogAs demand for data centers continues to accelerate, water availability is emerging as a critical factor in project development and long-term operations. Although power supply and transmission access have historically dominated siting discussions, increasing water constraints in many regions are placing greater focus on the substantial volumes of water required to support data center cooling systems. As we
covered previously, data centers are frequently located in areas already experiencing water stress and require substantial volumes of water to operate—roughly 228 billion gallons in 2023 in the United States alone—with water use projected to
increase by up to 170% by 2030.
Alternative cooling options, such as free-air cooling or mechanical chillers, can reduce direct water consumption but introduce their own tradeoffs. Free-air cooling is climate-dependent and often ineffective in hotter regions, while mechanical chillers increase energy demand, potentially shifting water consumption upstream through increased electricity generation.
Reprinted courtesy of
Ashleigh Myers, Pillsbury,
Jillian Marullo, Pillsbury and
Jason Drogin Atwood, Pillsbury
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Mr. Atwood may be contacted at jason.atwood@pillsburylaw.com
Read the full story...
The “Pay When Paid” Clause in California Construction—Strategies as the Battle Continues
August 03, 2026 —
William L. Porter - Porter Law GroupIt is well known in California Construction circles that the “Pay If Paid” clause is illegal in this state. There is a great distinction, though, between this clause and a similar clause, known as a “Pay When Paid” clause. A pay if paid clause allows a contractor to tell a subcontractor that if the contractor is unpaid for the subcontractor’s work, then the contractor has no legal obligation to pay the subcontractor, ever. For a great variety of reasons, the California Supreme Court, in the case of Wm. R. Clarke Corp v. Safeco Ins. Co. of America (1997) 15 Cal.4th 882, declared this type of clause illegal in California Construction.
Although the pay if paid clause is illegal in California, the pay when paid clause is still perfectly legal and is found in many subcontracts that contractors issue to their subcontractors. The pay when paid clause allows a contractor to delay paying its subcontractors until the dispute between the contractor and the property owner over payment has been resolved and the contractor is paid by the property owner. Although seemingly reasonable (since it merely delays payment until the contractor is paid by the owner, thereby providing a funding source to pay subcontractors), significant problems still arise.
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Newmeyer Dillion Partner Jeff Masters Recognized by Chambers USA for Representation of Insurance Policyholders
June 08, 2026 —
Newmeyer DillionNEWPORT BEACH, Calif. – June 4, 2026 – Newmeyer Dillion is proud to announce that litigation partner Jeffrey D. Masters has been ranked among a select group of California lawyers representing insurance policyholders in the 2026 edition of Chambers USA.
This marks two consecutive years of recognition for Masters by this prestigious international attorney rating resource.
"This recognition by Chambers and Partners is a testament to Jeff’s dedication to our clients," said Managing Partner, Paul Tetzloff. "We are thrilled to see his hard work acknowledged and the level of passion and care that he delivers to clients fully recognized."
Read the full story...Reprinted courtesy of
Newmeyer Dillion
Insured General Contractor Prevails on Motion for Summary Judgment to Establish Builder’s Risk Coverage
July 06, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe general contractor’s motion for partial summary judgment successfully established that damage to footings in place before the policy period was covered after the collapse of a building. Big D Builders, Inc. v. Am Zurich Ins. Co., 2026 U.S. Dist. LEXIS 72012 (D. Idaho March 31, 2026).
Big D was the general contractor for building a new airplane hangar by erecting a 38,000 square foot structure. Before Big D began construction, the site of the hangar did not contain any pre-existing structures or buildings. Before completion of the hangar, it collapsed and caused extensive property damage.
The builder’s risk policy issued by Zurich covered certain aspects of the construction project for the policy period December 28, 2023, to December 28, 2024. Zurich accepted coverage for most of the damage but not for damage to footings and columns installed prior to the start date of the policy.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
DOI Finalizes Long-Awaited Modernization of Type A Natural Resource Damage Assessment Regulations
August 03, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogFor nearly three decades, the U.S. Department of the Interior’s (DOI) simplified “Type A” Natural Resource Damage Assessment (NRDA) regulations were available more in theory than in practice, constrained by dated models, narrow geographic applicability and a $100,000 cap that rarely matched the economics of modern environmental claims. DOI has now finalized revisions to the Type A natural resource damages assessment procedures under 43 C.F.R. Part 11 for hazardous substance releases under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Clean Water Act (CWA), with the final rule published in the
Federal Register on July 13, 2026 and scheduled to become effective August 12, 2026.
As discussed
previously, DOI has sought to modernize what it views as an “inefficient and inflexible” process and restore the Type A procedure to its intended role as a more streamlined pathway for smaller, less contentious NRD claims. The final rule adopts a $5 million default damages threshold, allows use above that amount if all parties agree, clarifies that Type A may be used in all environments and for all natural resource types, and removes legacy model appendices that had tethered the process to outdated formulas.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...