Inaccurate Representations Can Lead to Differing Site Conditions Claim
May 26, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn the
prior posting, I discussed a case dealing with a differing site condition. In that case, the owner did not have an affirmative duty to make a representation and there was no inaccurate representation made by the owner that misled the contractor.
Well, what about when there is an inaccurate misrepresentation regarding the site? This was the circumstance in an older Florida case where a dredging contractor had a successful differing site conditions claim. See Jacksonville Port Authority v. Parkhill-Goodloe, Co., Inc., 362 So.2d 1009 (Fla. 1st DCA 1978).
The government provided inaccurate information as to the lack of rock that would be encountered during the dredging that was relied on by the dredging contractor. But the government had “
superior knowledge” that there was rock in an adjacent location based on a prior claim from a contractor, yet the government did not disclose the possibility that rock could be encountered.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractor Dispute Resolution Framework and Prevention
July 06, 2026 —
Construction ExecutiveWHAT DEFINES A CONTRACTOR DISPUTE RESOLUTION FRAMEWORK
A contractor dispute resolution framework is a structured system of contractual terms, governance processes and escalation pathways designed to prevent, manage and resolve conflicts between contracting parties with minimal disruption to cost, schedule and performance.
The framework operates as both a preventive control and a corrective mechanism. Preventive elements establish clarity in scope, expectations and accountability before work begins. Corrective elements define how disagreements are identified, documented, escalated and resolved once they arise.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Four Kahana Feld Attorneys Selected to 2027 Southern California Super Lawyers® and Rising Stars Lists
August 16, 2026 —
Kahana FeldIRVINE, CA – Aug. 3, 2026 – Kahana Feld is pleased to announce that partners
Jason Feld,
Amir Kahana, and
Sharon Oh-Kubisch were selected to the 2027 Southern California Super Lawyers list, and attorney
Hannah Ellenhorn Bloom was selected to the 2027 Southern California Super Lawyers Rising Stars list.
Jason Feld was recognized in the area of Construction Litigation. He is a founding partner of Kahana Feld and focuses his practice on the defense of homebuilders, contractors, developers, and real estate professionals primarily in construction defect, general liability, insurance defense, construction accident, and real estate matters. He also represents government entities handling construction, premises liability, general liability, and environmental claims. He serves as panel counsel for many prominent insurance carriers, as well as personal counsel to several national and regional homebuilders, developers, and general contractors.
Read the full story...Reprinted courtesy of
Kahana Feld
Your Construction Contract Won’t Always Save You From a Bad Project Record
November 02, 2026 —
Matthew J. Devries - Best Practices Construction Law BlogConstruction contracts are full of protections. No-damage-for-delay clauses. Consequential damage waivers. Rights to supplement a subcontractor’s work. Broad scheduling provisions. But a recent Tennessee construction case provides an important reminder: the best contract in the world may not save you from bad project facts.
In Commercial Painting Company, Inc. v. The Weitz Company, LLC (TN Ct. App. Oct. 28, 2026), the dispute involved a general contractor and its drywall subcontractor on a multi-building retirement community. The subcontract was originally worth more than $3.2 million, and the parties eventually disagreed about delays, scheduling, supplemental work, backcharges, and unpaid applications for payment. What began as a fairly typical construction dispute became anything but typical. A jury ultimately found that the general contractor had intentionally misrepresented material facts and awarded the subcontractor $3.9 million in punitive damages. (The case has a lengthy procedural history involving multiple appeals, but this post focuses only on the practical lessons from the most recent decision.)
Read the full story...Reprinted courtesy of
Matthew J. Devries, BuchalterMr. Devries may be contacted at
mdevries@buchalter.com
Insufficient Notice of Commencement and Construction Lien Rights
August 03, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice to Owner company will typically rely on the Notice of Commencement to serve Notices to Owners from lower tiers not in contract with the owner. However, when it comes to preparing the lien, a lienor should look beyond just the Notice of Commencement and also look to the property appraiser’s website as a backstop.
In a recent case, a window company had the homeowner sign the Notice of Commencement and then filled in the information. The company naturally did this for the convenience of the homeowner that probably was unfamiliar with the Notice of Commencement process. Regardless, information in the Notice of Commencement was inaccurate. It failed to include all the real property owners. Thus, when a payment dispute arose and a construction lien was prepared, it did not identify all of the real property owners. All of the real property owners were added later during the pendency of a lien foreclosure lawsuit. The trial court denied the lien because of the defective / insufficient Notice of Commencement — the lienor assumed the risk of error by filling out the information in the Notice of Commencement. The trial court further denied the lien holding that because the work did not commence within 90 days of the Notice of Commencement, the Notice of Commencement is void.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Over 50 Lewis Brisbois Attorneys Recognized in 7th Edition of Best Lawyers: Ones to Watch in America
September 01, 2026 —
Lewis Brisbois56 Lewis Brisbois attorneys across 26 offices have been named to the 7th edition of “Best Lawyers: Ones to Watch in America.” Congratulations to the following attorneys on this recognition!
You can see the full list of Lewis Brisbois attorneys named to Best Lawyers' 33rd edition of The Best Lawyers in America
here.
Akron, OH
- Partner Meleah M. Skillern - Commercial Litigation
Atlanta, GA
- Partner Catherine Crawley - Personal Injury Litigation – Defendants; and Transportation Law
- Associate Davis Lackey - Insurance Law; and Personal Injury Litigation – Defendants
Read the full story...Reprinted courtesy of
Lewis Brisbois
Same Insurers, Different Results: Another Chapter in Acuity v. Kinsale and the Limits of Co-Carrier Recovery Under Colorado Law
October 27, 2026 —
David McLain - Colorado Construction Litigation BlogWhen multiple insurers potentially owe coverage for the same construction defect claim, can one insurer force another to participate in the defense or indemnification of their common insured? If the other insurer refuses, what remedies are available?
As is often the case in insurance coverage litigation, the answer depends on precisely what claim is being asserted, whose rights are being enforced, and when the claim is brought.
In our earlier article,
Acuity v. Kinsale Insurance Company: Co-Carrier Obligations and Subrogation under Colorado Law, we examined the United States District Court for the District of Colorado’s decision in Acuity v. Kinsale Insurance Company, 750 F. Supp. 3d 1229 (D. Colo. 2024). That decision addressed the circumstances under which an insurer that funded a construction defect settlement could pursue another insurer for equitable contribution, contractual subrogation, and alleged bad-faith conduct.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Appeals Court Upholds Skanska, Granite Win in ‘I-4 Ultimate’ JV Dispute
June 15, 2026 —
Bryan Gottlieb - Engineering News-RecordA federal appeals court has upheld a lower court’s decision requiring The Lane Construction Corp. to pay roughly $79 million in damages, plus interest, to joint venture partners Skanska USA Civil Southeast and Granite Construction for work on Florida’s I-4 Ultimate highway megaproject in Orlando, which was completed in 2022.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at