Surety Liability Is Coextensive with Its Bond Principal
April 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller act payment bond case, U.S. f/u/b/o Whitetail General Constructors v. Northcon, Inc., 2026 WL 46671 (D.Mont. 2026), contains a short noteworthy discussion as to a surety’s liability being coextensive with that of its bond principal. If you are bonded, or you are pursuing a bond, you need to appreciate this, which is why this is a noteworthy discussion:
A “surety’s liability on a Miller Act bond must be at least coextensive with the obligations imposed by the Act if the bond is to have its intended effect.” “Therefore, ‘the liability of a surety and its principal on a Miller Act payment bond is coextensive with the contractual liability of the principal only to the extent that it is consistent with the rights and obligations created under the Miller Act.’” In other words, “[w]here a subcontract’s terms are consistent with the Miller Act’s provisions, the surety’s liability on the Miller Act bond is coextensive with the contractual liability of its princip[al].”
“The liability of a surety under the Miller Act is controlled by federal law, rather than state contract law[.]” The court may, however, “look to state law when interpreting contractual provisions” in a Miller Act case.
“[T]he measure of recovery under the Miller Act is generally determined by the terms of the subcontract [or underlying contract].”
Northcon, supra, at *4-5 (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
A Customized Approach to Data Center Construction
June 29, 2026 —
James P. Bobotek, Arielle L. Murphy & Robert A. James - Gravel2Gavel Construction & Real Estate Law BlogData center construction projects are, to put it mildly, distinct. They differ from traditional construction in a host of manners, and are particularly distinctive because the value of the facility depends on unique measures of performance. A center that cannot meet uptime, cooling, redundancy or connectivity standards will not achieve its mission, whether or not the structure itself meets standard industry contract-form “substantial completion” or “mechanical completion” definitions.
Owners, developers, lenders, operators and hyperscalers—especially hyperscalers!—want it all. They seek favorable and stable pricing, accelerated delivery and sophisticated components, all of which are evolving in “real project time.” Standard construction contract forms deserve extensive modifications to align clauses with expectations, with a heightened focus on systems integration, commissioning, and allocation of special risks. This article details customized considerations for drafting, negotiating and administering data center design and construction agreements.
Reprinted courtesy of
James P. Bobotek, Pillsbury,
Arielle L. Murphy, Pillsbury and
Robert A. James, Pillsbury
Mr. Bobotek may be contacted at james.bobotek@pillsburylaw.com
Ms. Murphy may be contacted at arielle.murphy@pillsburylaw.com
Mr. James may be contacted at rob.james@pillsburylaw.com
Read the full story...
Can Foreclosure Sale Be Overturned Because Sale Price Is Grossly Inadequate?
January 26, 2026 —
David Adelstein - Florida Construction Legal UpdatesForeclosure actions are equity actions. See Verzura Construction, Inc. v. Hotel La Petitite Muse, LLC, 50 Fla.L.Weekly D2500a (Fla. 3d DCA 2025). Can a sale price at a foreclosure auction sale be set aside because the foreclosed party believes the sale price is grossly inadequate? A recent case discusses this question and, as you will see, the argument that the sale price is grossly inadequate is not enough to overturn a sale.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Data Center Construction and the AEC Partner of the Future
April 14, 2026 —
Aarni Heiskanen - AEC BusinessDuring my involvement in designing mobile phone production facilities, the speed of design and construction was critical. Any delay could directly translate into lost revenue. That same logic now applies to data centers, though the stakes are much higher. Instead of optimizing physical production lines, we are constructing infrastructure for digital production.
The global data center capacity is expected to nearly double by 2030, and with this level of demand, the traditional project-by-project delivery model begins to show its limitations.
Data centers are no longer isolated projects in the traditional sense. They are evolving into repeatable, scalable production systems, making them ideal environments for AEC process and business model innovation.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Research Illuminates Pollution Problem in Tijuana River Valley
June 29, 2026 —
Jeff Yoders - Engineering News-RecordThe Tijuana River watershed between southern California and northern Mexico has been the epicenter of an environmental and public health crisis for more than two decades. Since October 2023 alone, more than 31 billion gallons of raw sewage and polluted water have flowed into the U.S. and, eventually, the Pacific Ocean.
Read the full story...Reprinted courtesy of
Jeff Yoders, Engineering News-RecordMr. Yoders may be contacted at
yodersj@enr.com
New York Amends Prompt Payment Act: Retainage Above 5% in Private Construction Contracts Now Void
February 10, 2026 —
Mark A. Snyder, Levi W. Barrett, Patrick T. Murray & Skyler L. Santomartino - Peckar & Abramson, P.C.In 2023 New York overhauled its Prompt Payment Act. The
2023 amendments, largely aimed at restricting the amount of retainage that can be withheld on private projects, were unclear about whether parties could contract around the statute, as they can with other provisions of the statute. The State Legislature recently clarified that issue.
On December 19, 2025, New York enacted a new law, tightening the State’s Prompt Payment Act retainage laws by amending the Prompt Payment Act under General Business Law § 757. Under § 757, the new law renders void any contract provision in private construction contracts that requires retainage in excess of 5% of the total contract sum, meaning owners cannot hold more than 5% from their prime contractors and prime contractors cannot hold more than 5% from their subcontractors.
Reprinted courtesy of
Mark A. Snyder, Peckar & Abramson, P.C.,
Levi W. Barrett, Peckar & Abramson, P.C.,
Patrick T. Murray, Peckar & Abramson, P.C. and
Skyler L. Santomartino, Peckar & Abramson, P.C.
Mr. Snyder may be contacted at msnyder@pecklaw.com
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Murray may be contacted at pmurray@pecklaw.com
Mr. Santomartino may be contacted at ssantomartino@pecklaw.com
Read the full story...
Don’t Hire Me! (Principle Is Expensive, and Lawsuits Based on Principle Are Even More Expensive)
February 10, 2026 —
Melissa Dewey Brumback - Construction Law in North CarolinaI spend a lot of time trying to convince my clients to NOT hire me. I’m not crazy—let me explain. Litigation is costly. Very costly. And it is time consuming. Don’t get me wrong—I will go to Court and fight just as hard as you want me to, but I want you to know what you are facing before you go down that road.
Now, obviously, if you are the one that is being sued, you have no choice but to defend yourself and your Firm. But if you are considering suing someone else, think long and hard about it before you pull the trigger. There are ways to reduce cost, time, and risk: for example, pre-suit or early mediation, or agreeing to arbitration in lieu of trial. But I always want my clients to know that real law is not like Law & Order. Things take time. A trial is often a year or more away from when you first file the lawsuit. Make your decisions on not just your heart, but your economic brain as well.
Read the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Executive Order Addresses Wildfire Rebuilding Delays Through Federal Preemption of State and Local Permitting
February 10, 2026 —
Olivia LaCasto & Josh Schneiderman - Snell & WilmerQuick Take
On January 23, 2026, one year after the Los Angeles wildfires, the President issued Executive Order 14377 directing the Secretary of Homeland Security, acting through the Administrator of the Federal Emergency Management Agency (FEMA), and the Administrator of the Small Business Administration (SBA) to consider regulations that would preempt state and local permitting requirements for federally funded reconstruction projects in the Pacific Palisades and Eaton Canyon areas. The Order mandates expedited federal environmental and historic preservation reviews, directs the development of legislative proposals, and orders an audit of California’s use of Hazard Mitigation Grant Program (HGMP) funding.
Key Provisions
Federal Preemption of State and Local Permitting
The Order directs FEMA and the SBA to consider promulgating regulations that would preempt state or local permitting processes found to have “unduly impeded” the timely use of federal emergency-relief funds by homeowners, businesses, or houses of worship seeking to rebuild. Under the proposed framework, preempted permitting regimes would be replaced with a self-certification requirement, whereby builders would certify to a federal designee that they have complied with all applicable substantive state and local health and safety standards. FEMA would retain authority to review all repairs and construction for compliance with applicable health and safety standards. Proposed regulations must be published within 30 days, with final regulations due within 90 days.
Reprinted courtesy of
Olivia LaCasto, Snell & Wilmer and
Josh Schneiderman, Snell & Wilmer
Ms. LaCasto may be contacted at olacasto@swlaw.com
Mr. Schneiderman may be contacted at jschneiderman@swlaw.com
Read the full story...