Surety Liability Is Coextensive with Its Bond Principal
April 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller act payment bond case, U.S. f/u/b/o Whitetail General Constructors v. Northcon, Inc., 2026 WL 46671 (D.Mont. 2026), contains a short noteworthy discussion as to a surety’s liability being coextensive with that of its bond principal. If you are bonded, or you are pursuing a bond, you need to appreciate this, which is why this is a noteworthy discussion:
A “surety’s liability on a Miller Act bond must be at least coextensive with the obligations imposed by the Act if the bond is to have its intended effect.” “Therefore, ‘the liability of a surety and its principal on a Miller Act payment bond is coextensive with the contractual liability of the principal only to the extent that it is consistent with the rights and obligations created under the Miller Act.’” In other words, “[w]here a subcontract’s terms are consistent with the Miller Act’s provisions, the surety’s liability on the Miller Act bond is coextensive with the contractual liability of its princip[al].”
“The liability of a surety under the Miller Act is controlled by federal law, rather than state contract law[.]” The court may, however, “look to state law when interpreting contractual provisions” in a Miller Act case.
“[T]he measure of recovery under the Miller Act is generally determined by the terms of the subcontract [or underlying contract].”
Northcon, supra, at *4-5 (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
$356 Million Judgement Against Developer for Defective Construction of DC Condominium
August 16, 2026 —
Nicholas D. Cowie - Cowie Law GroupOn July 31, 2026, the Superior Court of the District of Columbia entered a $356,085,513.00 judgment against developers JBG Smith for defective construction and renovation of the Wardman Tower Residential Condominium in Washington, D.C. The case is Wardman Tower Residential Condominium Unit Owners Association v. JBG Smith Properties, et al., No. 2020 CA 004807 B (D.C. Super. Ct.). In a 148-page
Trial Order, the D.C. Superior Court awarded $118,695,171.00 in damages in favor of the condominium association and against the condominium developers, including JBG Smith. The Court trebled those damages pursuant to the District of Columbia Consumer Protection Procedures Act (“CPPA”) to reach an ultimate judgment of $356,085,513.00. See Cowie Law Group:
DC Condominium Construction Defects: Recovering Attorney’s Fees, Litigation Expenses & Treble Damages Under the Consumer Protection Procedures Act.
Cowie Law Group, P.C. filed the lawsuit on behalf of the Association in 2020. The firm represented the Association throughout years of pretrial discovery and ultimately served as trial counsel with Williams & Connolly LLP during a lengthy bench trial before the Honorable Yvonne Williams. The Cowie Law Group team included attorneys, George A. Bealefeld, III, Albert G. McCarraher, Stanford L. Kimmel, III and Nicholas D. Cowie.
Read the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie Law GroupMr. Cowie may be contacted at
ndc@cowielawgroup.com
Travelers Injury Impact Report Highlights Longer Recovery Times Amid Declining Injury Rates
May 05, 2026 —
The Travelers Companies, Inc.HARTFORD, Conn.--(BUSINESS WIRE)--The Travelers Companies, Inc. (NYSE: TRV) today released its 2026 Injury Impact Report, an analysis of more than 1.2 million workers compensation claims received by the company from 2021 through 2025. The report finds that even as workplace injury rates decline, the injuries that do occur are growing more complex and taking longer to heal – a trend driven by an aging workforce and the disproportionate vulnerability of first-year employees.
“The decrease in workplace injuries is a positive story, yet injured workers are still missing an average of 80 workdays,” said Claude Howard, Vice President of Workers Compensation Claim at Travelers. “This report is a reminder that progress doesn’t mean the risk environment requires any less attention, and an employer’s commitment to safety must keep pace with an ever-evolving workforce and injury landscape.”
Read the full story...Reprinted courtesy of
The Travelers Companies, Inc.
Real Estate & Construction News Roundup (8/5/26) – Data Centers Reshape Hotel Demand, AI Changes Construction Workflows and Global Tariffs Raise CRE Construction Costs
August 16, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, AI creates new real estate play for VCs, Wall Street sells more rental homes, builders capitalize on flood of water projects and more!
- Data center construction has the potential to be a significant opportunity for extended stay hotels in the near and long term, provided sustainable demand patterns exist within a given market. (Jenna Graber, Hotel Dive)
- Artificial intelligence doesn’t represent an “extinction event” for AEC firms, but it will fundamentally change the way construction pros streamline certain tasks. (Matthew Thibault, Construction Dive)
- With the 21st Century ROAD to Housing now law, there are a number of outstanding questions about implementation and compliance for multifamily pros. (Julie Strupp, Multifamily Dive)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Construction Liens: Liening for Amounts Not Yet Technically Due Does Not Mean Lien Is Fraudulent
August 11, 2026 —
David Adelstein - Florida Construction Legal UpdatesA 2024 bankruptcy ruling, In re Edgewater Construction Group, Inc., 657 B.R. 668 (S.D.Fla. 2024), touched upon an interesting issue when it comes to construction liens. Is a construction lien fraudulent simply because the lien includes amounts not yet due? Not necessarily.
In this bankruptcy dispute, the subcontractor debtor (that filed for bankruptcy) recorded two construction liens on projects. The general contractor argued in the bankruptcy court that the subcontractor debtor’s liens were fraudulent.
As to the first lien, the general contractor argued that the lien was fraudulent because it included amounts that the debtor knew the general contractor had already paid to the debtor’s subcontractors/suppliers. The bankruptcy court disagreed: “The Court finds that, although the Debtor had been told that [the general contractor] had paid these subcontractors, in light of the ongoing dispute between Debtor and [the general contractor], it was reasonable for the Debtor to demand proof. Debtor’s subsequent filing of a partial satisfaction of lien once the Debtor received the requested proof of payment from [the general contractor] counters any claim of willful exaggeration.” In re Edgewater Construction Group, supra, at 672-673.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Insufficient Notice of Commencement and Construction Lien Rights
August 03, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice to Owner company will typically rely on the Notice of Commencement to serve Notices to Owners from lower tiers not in contract with the owner. However, when it comes to preparing the lien, a lienor should look beyond just the Notice of Commencement and also look to the property appraiser’s website as a backstop.
In a recent case, a window company had the homeowner sign the Notice of Commencement and then filled in the information. The company naturally did this for the convenience of the homeowner that probably was unfamiliar with the Notice of Commencement process. Regardless, information in the Notice of Commencement was inaccurate. It failed to include all the real property owners. Thus, when a payment dispute arose and a construction lien was prepared, it did not identify all of the real property owners. All of the real property owners were added later during the pendency of a lien foreclosure lawsuit. The trial court denied the lien because of the defective / insufficient Notice of Commencement — the lienor assumed the risk of error by filling out the information in the Notice of Commencement. The trial court further denied the lien holding that because the work did not commence within 90 days of the Notice of Commencement, the Notice of Commencement is void.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Limitations of Liability Provisions in Construction Contracts: A Means to Manage Risk and Limit Financial Exposure
June 23, 2026 —
Ellen Chapelle, Richard Reizen, Hannah Batsche - Construction ExecutiveTaking a cue from architects and engineers, construction contractors have started inserting limitation of
liability clauses in their construction contracts to manage risk and limit financial exposure. This article will address the specific risks that can be limited through an LOL, tips for negotiating the LOL terms with reluctant owners to cover those specific risks, how to limit unintended consequences of an LOL (such as relieving an insurer of its obligations to cover certain losses), and approaches to setting the amount of the liability cap in the LOL.
Addressing Particular Risks
An LOL can address a wide range of risks, including:
- Damages for delay
- Liability for non-conforming or defective work
- Liability for third-party bodily injury or property damage
- Liability excluded by a general liability policy (e.g., pollution and cyber liability)
- Liability related to intellectual property
Reprinted courtesy of
Ellen Chapelle, Richard Reizen, Hannah Batsche, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Navigating Timelines and Technology: Patent Strategies for Space and Earth
June 01, 2026 —
Kate Nuehring Su & Vanessa Wang - Engineering News-RecordMore than half a century after the Apollo 11 landing
fulfilled President John F. Kennedy’s bold vision, the global race back to the Moon is no longer theoretical. With renewed attention on NASA’s Artemis program and a surge of commercial investment in space infrastructure, lunar exploration is again shaping technology priorities here on Earth.
Reprinted courtesy of
Kate Nuehring Su, Engineering News-Record and
Vanessa Wang, Engineering News-Record Read the full story...ENR may be contacted at
enr@enr.com