Inaccurate Representations Can Lead to Differing Site Conditions Claim
May 26, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn the
prior posting, I discussed a case dealing with a differing site condition. In that case, the owner did not have an affirmative duty to make a representation and there was no inaccurate representation made by the owner that misled the contractor.
Well, what about when there is an inaccurate misrepresentation regarding the site? This was the circumstance in an older Florida case where a dredging contractor had a successful differing site conditions claim. See Jacksonville Port Authority v. Parkhill-Goodloe, Co., Inc., 362 So.2d 1009 (Fla. 1st DCA 1978).
The government provided inaccurate information as to the lack of rock that would be encountered during the dredging that was relied on by the dredging contractor. But the government had “
superior knowledge” that there was rock in an adjacent location based on a prior claim from a contractor, yet the government did not disclose the possibility that rock could be encountered.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Can Anything Supersede Excel in AEC?
April 27, 2026 —
Aarni Heiskanen - AEC BusinessIf there’s one piece of software that dominates the business world across industries, it’s Microsoft Excel. Can AI finally dethrone the mighty spreadsheet?
Memorable Spreadsheet Moments
Everyone has memorable spreadsheet moments. I have a few. For example, my then-architecture firm was involved in more than a dozen housing developments abroad. I developed an Excel workbook that took the required number of households as input and automatically generated a breakdown of buildings and their apartment types for AutoCAD. This was urban planning and architectural design done with a spreadsheet.
I also developed business software using Excel for project portfolio management. The prototype was later scaled into a commercial SaaS that is now used globally.
Another memorable moment was when a property owner told me their Excel file grew so large that it ran out of rows and columns. That must have been before 2007, when the maximum number of columns on a sheet was still just 256 and the maximum number of rows was 65,536. The current limits are 1,048,576 rows and 16,384 columns, which I hope no one will exceed.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Steel Cooling: Steel Costs Steadily Decline After Pandemic Price Shock
May 12, 2026 —
Construction ExecutiveSteel prices have continued trending downward after several years of volatility, according to Gordian’s latest analysis based on RSMeans Data. After dramatic spikes during the pandemic-era supply disruptions, the market has gradually stabilized as supply chains improve and demand softens in some construction segments. However, selective volatility and tariff uncertainty continue to influence pricing across the sector.
Key findings from the report include:
- Steel prices declining: The national average price of structural steel fell to about $2,343.93 per ton in January 2026, down 5.38% from the previous quarter and 7.18% year over year.
- Longer-term price correction: Steel costs have been trending downward since 2024 after earlier volatility driven by inflation, supply shortages and global demand swings.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Supply Chain Is a Legal Exposure—Not Just a Force Majeure Problem
September 08, 2026 —
Owen Newman - Construction ExecutiveThis is not another force majeure article. The supply-chain related legal exposure that contractors are carrying today—in sanctions risk, specification non-compliance, warranty exposure and regulatory volatility—extends well beyond what even a well-drafted force majeure clause protects.
An engineering, procurement and construction contractor on a gas-fired power plant discovers during commissioning that transformer oil in a critical unit contains Russian-origin naphthenic base oil, which is a prohibited source under Office of Foreign Assets Control sanctions. The contractor didn’t source it. A subsupplier two tiers below made the substitution when disruptions in the Strait of Hormuz tightened the primary supply chain for this specialty product and no one in the purchase-order chain flagged it. The procurement decision is long done and the documentation trail that should have caught it doesn’t exist.
Reprinted courtesy of
Owen Newman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Mr. Newman may be contacted at
oknewman@duanemorris.com
AI Can Now Train the Soft Skills Construction Ignored
August 03, 2026 —
Aarni Heiskanen - AEC BusinessMost AEC professionals learn to work in teams and across teams through trial and error. There are, however, opportunities to better prepare for the real world with formal training. Until now, it has required human facilitators. Now, generative AI is emerging as a scalable alternative, which I’m also exploring.
A Gap in Curricula
When I studied architecture, most of the teamwork happened with co-students in the same department. However, one course focused on industrial projects where future architects and engineers collaborated on a simulated project. I’m not sure if a similar course is still in the curriculum, but it was certainly worthwhile and should have been much more extensive.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
The “Pay When Paid” Clause in California Construction—Strategies as the Battle Continues
August 03, 2026 —
William L. Porter - Porter Law GroupIt is well known in California Construction circles that the “Pay If Paid” clause is illegal in this state. There is a great distinction, though, between this clause and a similar clause, known as a “Pay When Paid” clause. A pay if paid clause allows a contractor to tell a subcontractor that if the contractor is unpaid for the subcontractor’s work, then the contractor has no legal obligation to pay the subcontractor, ever. For a great variety of reasons, the California Supreme Court, in the case of Wm. R. Clarke Corp v. Safeco Ins. Co. of America (1997) 15 Cal.4th 882, declared this type of clause illegal in California Construction.
Although the pay if paid clause is illegal in California, the pay when paid clause is still perfectly legal and is found in many subcontracts that contractors issue to their subcontractors. The pay when paid clause allows a contractor to delay paying its subcontractors until the dispute between the contractor and the property owner over payment has been resolved and the contractor is paid by the property owner. Although seemingly reasonable (since it merely delays payment until the contractor is paid by the owner, thereby providing a funding source to pay subcontractors), significant problems still arise.
Read the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Powering Data Centers in a Moving Regulatory Landscape: Positioning Deals Before FERC’s Next Move
April 27, 2026 —
Stephen J. Humes, Alicia M. McKnight & Andrew H. Jacobs - Gravel2Gavel Construction & Real Estate Law BlogThe explosive growth of data‑center load—driven by artificial intelligence, cloud computing and the expansion of digital infrastructure across industries—has forced U.S. energy regulators into unfamiliar territory. Nowhere is this more evident than at the Federal Energy Regulatory Commission (FERC), which is actively considering how large, concentrated loads can be powered without compromising grid reliability or shifting costs to other customers.
FERC has not yet issued a standalone rulemaking on data centers. But make no mistake, the regulatory framework is quietly and deliberately being built. For developers, hyperscalers, utilities and investors, the period before FERC finalizes its next round of decisions represents the critical window to crystallize advocacy and structure transactions in ways that anticipate regulatory change.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury and
Andrew H. Jacobs, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Jacobs may be contacted at andrew.jacobs@pillsburylaw.com
Read the full story...
Anomaly in Adding a Third-Party Claimant to a Liability Insurance Coverage Dispute
May 05, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn an insurance coverage lawsuit seeking declaratory relief, an insurer sued the third-party claimant. The insurer was seeking a declaration that there was no coverage, which naturally would impact the third-party claimant. The insured did not respond to the lawsuit and the insurer moved for a default judgment which was objected to by the third-party claimant. The trial court granted a final judgment in favor of the insurer, which prompted an appeal from the third-party claimant because the final judgment impacts its rights to coverage if it obtains a judgment against the insured.
The appellate court reversed but please take a look at this Court’s discussion on the issue of an insurer adding a third-party claimant to a coverage lawsuit when then the third-party cannot pursue a direct claim against the insurer until it obtains a settlement or judgment against the insured. It presents an interesting argument and counter-point for a third-party claimant that is added to the coverage lawsuit which has implications if it obtains a judgment against the insured:
This case involves an apparent anomaly in Florida law. It is well-established that third-party claimants injured by an insured’s negligence have a right as third-party beneficiaries to payment from the insured’s insurance proceeds. It is equally well-established that the third-party claimants’ rights in this regard do not accrue unless and until they obtain a verdict or settlement against the insured. A quick review of this law is helpful at this point.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com