Modular Construction’s Big Boom: New Risks Outpacing Standard Contracts in Industrial Projects
March 24, 2026 —
Chad Theriot & Jack Mayo - Construction ExecutiveModular construction is revolutionizing the construction industry, tackling labor shortages, sustainability goals and supply-chain challenges, with the global market for modular and prefabricated construction projected to reach over $200 billion by 2030. While residential builders have embraced modular’s speed and affordability, the greatest risks—and opportunities—are emerging in the industrial sector, where project scale and complexity demand new legal strategies.
In 2023, Chad Theriot explored industrial and infrastructure applications of modular construction, addressing risks like offsite fabrication and integration complexities in his article, “
The Rise of Modular Construction—Impacts for Consideration.” Since that time, modular construction has continued to experience significant advancements and has been increasingly adopted by contractors across a broad spectrum of industrial and commercial projects. As modular construction continues to reshape the industrial landscape, contractors and owners alike must be mindful of the legal implications associated with its use, specifically as it relates to liability and risk allocation, regulatory compliance, quality control and upstream factors such as transportation and intellectual property concerns.
Reprinted courtesy of
Chad Theriot and Jack Mayo, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Executive Order Addresses Wildfire Rebuilding Delays Through Federal Preemption of State and Local Permitting
February 10, 2026 —
Olivia LaCasto & Josh Schneiderman - Snell & WilmerQuick Take
On January 23, 2026, one year after the Los Angeles wildfires, the President issued Executive Order 14377 directing the Secretary of Homeland Security, acting through the Administrator of the Federal Emergency Management Agency (FEMA), and the Administrator of the Small Business Administration (SBA) to consider regulations that would preempt state and local permitting requirements for federally funded reconstruction projects in the Pacific Palisades and Eaton Canyon areas. The Order mandates expedited federal environmental and historic preservation reviews, directs the development of legislative proposals, and orders an audit of California’s use of Hazard Mitigation Grant Program (HGMP) funding.
Key Provisions
Federal Preemption of State and Local Permitting
The Order directs FEMA and the SBA to consider promulgating regulations that would preempt state or local permitting processes found to have “unduly impeded” the timely use of federal emergency-relief funds by homeowners, businesses, or houses of worship seeking to rebuild. Under the proposed framework, preempted permitting regimes would be replaced with a self-certification requirement, whereby builders would certify to a federal designee that they have complied with all applicable substantive state and local health and safety standards. FEMA would retain authority to review all repairs and construction for compliance with applicable health and safety standards. Proposed regulations must be published within 30 days, with final regulations due within 90 days.
Reprinted courtesy of
Olivia LaCasto, Snell & Wilmer and
Josh Schneiderman, Snell & Wilmer
Ms. LaCasto may be contacted at olacasto@swlaw.com
Mr. Schneiderman may be contacted at jschneiderman@swlaw.com
Read the full story...
New York Orders Moratorium on Large Data Center Permits
July 27, 2026 —
Levi W. Barrett - Peckar & Abramson, P.C.Levi W. Barrett, Co-Managing Partner of Peckar & Abramson’s New Jersey office, Co-Chair of the firm’s
Construction Contracts & Risk Management team, and Executive Committee Member, was recently quoted in “New York Orders Moratorium on Large Data Center Permits,” an article written by
Engineering News-Record (ENR). The article examines New York Governor Kathy Hochul’s executive order temporarily halting state environmental permit reviews for certain large-scale data center projects while regulators develop a comprehensive framework to address the sector’s energy demands, water consumption, environmental impacts, and effects on local communities. It also explores the broader implications of the moratorium for developers, contractors, investors, and other stakeholders, as well as the ongoing debate between economic development, AI-driven infrastructure growth, and environmental and utility ratepayer concerns.
Read the full story...Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.Mr. Barrett may be contacted at
lbarrett@pecklaw.com
Balancing the Right to Repair With Evidence Preservation in Construction Defect Litigation
April 20, 2026 —
Benton Wheatley & Anna Spicer - Construction ExecutiveEvery major construction project comes with risk, whether it’s a
warehouse build, a
multifamily development or a major renovation. Parties tend to be aligned when things are proceeding as planned. But when something goes wrong—cracked concrete, water intrusion, systems that don’t perform as expected—those interests can quickly diverge.
Property owners are often caught in the middle when construction defects surface. They’re expected to act quickly to limit damage and costs. But they also have legal obligations to preserve evidence and allow potentially responsible parties, such as contractors or designers, to observe testing, demolition and repairs. Additionally, owners often have duties to lenders and investors to fix problems promptly and pursue claims against those responsible. Meanwhile, contractors and other parties have obligations of their own—not to interfere with repairs and not to delay mitigation efforts while investigations are underway.
What follows will examine how those competing responsibilities play out in construction defect disputes.
Reprinted courtesy of
Benton Wheatley & Anna Spicer, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Pulling the Plug, Preserving the Product: Protecting Rights to a Modular Subcontractor’s Work Post-Termination
June 08, 2026 —
Paul Williamson - ConsensusDocsVolumetric Modular Construction (VMC) is a building method where a structure is divided into large components or modules, fabricated in an offsite factory and then transported to a construction site for assembly.[
1] Proponents of VMC hail it as a cost-efficient alternative to traditional building methods that leads to more consistent quality and shorter construction duration.[
2] Due to a growing labor shortage, high demand for compressed project schedules, and stagnant construction productivity rates, the construction industry is embracing VMC.[
3] A recent report on the market size of prefabricated construction estimates that from 2026 to 2031, VMC will grow at a compound annual growth rate of 7.16% and become a 413.11-billion-dollar industry.[
4]
As VMC becomes more prevalent, owners, general contractors, and subcontractors must consider how to effectively contract for modular construction. One important consideration, which this article focuses on, is navigating termination of a modular subcontractor.
Read the full story...Reprinted courtesy of
Paul Williamson, Peckar & Abramson, P.C.Mr. Williamson may be contacted at
pwilliamson@pecklaw.com
Labor Shortages in Construction: Managing Legal and Operational Risks
April 14, 2026 —
Meghan Douris - Construction ExecutiveLabor shortages in the construction industry have become more than a scheduling headache—they are a legal and financial risk multiplier. As contractors scramble to meet deadlines with limited manpower, shortcuts in compliance, safety and subcontractor oversight become more likely. These gaps can expose companies to regulatory penalties, contractual disputes and reputational damage. Understanding how workforce constraints intersect with labor laws and contractual obligations is critical to mitigating the risks and navigating these challenges without compromising compliance or project integrity.
The construction industry has faced persistent workforce challenges for years, but recent trends have intensified the problem. Factors such as an aging workforce, reduced immigration and post-pandemic recovery pressures have left contractors struggling to find skilled labor. According to
Associated Builders and Contractors, the construction workforce shortage surpassed half a million workers in 2024; in the same year,
Associated General Contractors reported 88% of construction companies had difficulty finding qualified workers.
Reprinted courtesy of
Meghan Douris, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Congratulations to Reno Partner Karen Baytosh for Securing a Complete Dismissal via a Motion for Summary Judgment
July 13, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBWB&O is proud to announce that Reno Partner Karen Baytosh received a significant victory on behalf of the firm’s Developer Client in a high-exposure personal injury matter.
Plaintiff, a teenager, was struck by an intoxicated driver while walking her dog at night, sustaining catastrophic injuries requiring 24-hour critical care for the remainder of her life. Plaintiff’s Guardian brought suit against the drunk driver and her husband, the City, and BWB&O’s Developer Clients, alleging that the City and Developers failed to improve street lighting and install a sidewalk that would have prevented the accident.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Quick Note: Include Key Time Related Facts in Contract to Avoid an Ambiguity
February 17, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen drafting or negotiating a contract, it is important to consider key time-related facts. In other words, if there are important provisions dealing with time, you don’t want to leave them undefined as that can create an ambiguity in the contract.
In a recent case dealing with an investment contract, discussed
here, that’s exactly what happened. The contract allowed investors to exercise an option to return their equity in exchange for a refund of their investment but the contract didn’t contain an expiration date on when the option must be exercised. The investors tried to exercise the option two years later leading to a dispute as to whether that was a “reasonable time.” This is because the lack of clarity regarding this temporal fact led to a latent ambiguity meaning it was a question of fact as to whether the investors exercising the option two years later was reasonable under the circumstances.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com