Additional Insureds Owed a Defense in Underlying Personal Injury Suit
March 03, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted partial summary judgment on the duty to defend to two additional insureds who were named as defendants in the underlying personal injury suit. In re Third St. Equity, LLC, 2025 U.S. Dist. LEXIS 234909 (E.D. N. Y. Dec. 2, 2025).
Third Street Equity LLD hired Developing NY State, LLC as the contractor for a construction project. Developing NY entered a subcontract agreement with Capital Source Concrete NY LLC for concrete work as well as labor and services for a construction project. The subcontract required that Capital Concrete keep the construction site free of debris, waste material or rubbish. Further, Capital Concrete was responsible for compliance with OSHA safety regulations. It was also agreed that Capital Concrete would obtain liability and workers compensation insurance naming Third Street and Developing NY as additional insureds.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurer’s Federal Suit Dismissed in Favor of Insured’s State Suit
April 14, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insured’s motion to dismiss the insurer’s federal suit for declaratory judgment because the insured filed a more complete action in state court. Church Mut. Ins. Co. v. Elmwood Baptist Church, 2025 U.S. Dist. LEXIS 259762 (S.D. W.V. Dec. 16, 2025).
Elmwood purchased a property policy from Church Mutual Insurance Company. After the roof of Elmwood’s property collapsed, the parties disputed the amount Church Mutual owed to Elmwood.
Church Mutual filed suit in federal district court asking for a declaration that the policy was “void ab initio,’ or, alternatively, that Church had fully compensated Elmwood for its loss.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Can Anything Supersede Excel in AEC?
April 27, 2026 —
Aarni Heiskanen - AEC BusinessIf there’s one piece of software that dominates the business world across industries, it’s Microsoft Excel. Can AI finally dethrone the mighty spreadsheet?
Memorable Spreadsheet Moments
Everyone has memorable spreadsheet moments. I have a few. For example, my then-architecture firm was involved in more than a dozen housing developments abroad. I developed an Excel workbook that took the required number of households as input and automatically generated a breakdown of buildings and their apartment types for AutoCAD. This was urban planning and architectural design done with a spreadsheet.
I also developed business software using Excel for project portfolio management. The prototype was later scaled into a commercial SaaS that is now used globally.
Another memorable moment was when a property owner told me their Excel file grew so large that it ran out of rows and columns. That must have been before 2007, when the maximum number of columns on a sheet was still just 256 and the maximum number of rows was 65,536. The current limits are 1,048,576 rows and 16,384 columns, which I hope no one will exceed.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Risks of Using an AI Chatbot for Legal Advice: Lessons from United States v. Heppner
April 08, 2026 —
Payne & Fears LLPImagine that you are an executive (who is not a lawyer) and are concerned about what your company plans to do is legal. You could call your lawyer who might bill you for the call. Or, you can ask your AI chatbot, such as Claude or ChatGPT, about the legal risk. The chatbot will likely compliment you on the incisive question, provide you with highly confident answer (that may or may not be right) and will not bill you on an hourly basis.
That is essentially what financial services executive Bradley Heppner did. It did not end well. A federal court recently ruled that Heppner’s chats with the AI tool Claude were not protected by attorney-client privilege or the work-product doctrine. That means that the other side (in this case, the federal government) could get access to his chatbot prompts, uploads and responses, and learn a great deal about, for example, whether Heppner knew what he was doing was illegal.
Read the full story...Reprinted courtesy of
Payne & Fears LLP
Consider The Limited Warranty from Your Homebuilder
July 06, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen purchasing a home from a homebuilder, there is an important consideration when it comes to the limited warranty you receive around the time you close on the home. That limited warranty likely includes an arbitration provision requiring you to arbitrate your disputes, such as construction defect claims, against the homebuilder. That arbitration provision will most likely include all claims, including statutory claims (such as a statutory violation of a building code claim), requiring you to arbitrate, as opposed to litigate, your disputes against the homebuilder. This is an important consideration. If the arbitration provision does not allow you to arbitrate all of your claims, and eliminates your rights to legitimate statutory claims, the arbitration provision could be unenforceable.
By way of example, in a residential construction defect dispute, Anderson v. Taylor Morrison of Florida, Inc., 223 So.3d 1088 (Fla. 2d DCA 2017), the appeal turned on whether the arbitration provision in the homebuilder’s limited warranty was valid. The homeowners took possession of their home in 2009. In 2015, the homeowners served a Florida Statutes Chapter 558 notice of construction defects that included a statutory violation of a building code claim under Florida Statute §553.84. The limited warranty included an arbitration provision that specified it was the “exclusive remedy” for all disputes arising out of or related to the warranty or issues with the home and property. When read together with the warranty’s disclaimer that precluded claims not covered by the warranty “whether in contract, tort, or otherwise,” the statutory building code violation claim could not be remedied through arbitration because it fell outside the warranty’s coverage.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Delay Matters: Florida’s Fourth DCA Reverses Hurricane Irma Dismissal
June 08, 2026 —
Andrea DeField, Machaella Reisman & Cary D. Steklof - Hunton Insurance Recovery BlogThe mantra “delay, deny, defend” is frequently referenced in discussions of insurance claims handling, though insurers will invariably disavow these tactics. While it would be facially improper for an insurer to delay a coverage decision to gain a tactical advantage, empirical examples nonetheless exist. This very dynamic was addressed by Florida’s Fourth District Court of Appeals when it handed policyholders a win in
Hypoluxo Mariner’s Cay Condo. Assoc’n, Inc. v. Underwriters at Lloyd’s London, No. 4D2024‑2250 (Fla. 4th DCA Apr. 1, 2026), reversing a trial court order dismissing a condominium association’s Hurricane Irma coverage lawsuit against its property insurer.
Delay to Run the Statute of Limitations
Following Hurricane Irma, a condominium association suffered roof and exterior envelope damage, reported an insurance claim, and submitted a sworn proof of loss to its property insurer in compliance with Florida Statute § 627.70132 (2020). The statute establishes a timeframe within which a policyholder must submit a claim for hurricane damage.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth LLP,
Machaella Reisman, Hunton Andrews Kurth LLP and
Cary D. Steklof, Hunton Andrews Kurth LLP
Ms. DeField may be contacted at adefield@hunton.com
Ms. Reisman may be contacted at reismanm@hunton.com
Mr. Steklof may be contacted at csteklof@hunton.com
Read the full story...
Colorado Supreme Court Reverses Course on Public Project Liens: Key Takeaways From Wadsworth v. Regional Rail Partners
July 27, 2026 —
Amanda E. McKinlay - Snell & WilmerOn April 6, 2026, the Colorado Supreme Court issued a unanimous opinion in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, 2026 CO 19, reversing the Colorado Court of Appeals and providing much-needed clarity regarding verified statements of claim (VSOCs) under the Colorado Public Works Act, C.R.S. §§ 38-26-101 et seq. The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
Under C.R.S. § 38-26-107(1), a subcontractor on a public works project may file a VSOC with the contracting public entity for amounts due and unpaid for “…furnished labor, materials, sustenance, or other supplies used or consumed by a contractor or his or her subcontractor in or about the performance of the work contracted to be done or that supplies laborers, rental machinery, tools, or equipment to the extent used in the prosecution of the work….” If a claimant files a VSOC for “an amount greater than the amount due” without a reasonable possibility that the amount is due and with knowledge that the claim is excessive, the claimant “shall forfeit all rights to the amount claimed” and becomes liable for the opposing party’s costs and attorneys’ fees. C.R.S. § 38-26-110.
Read the full story...Reprinted courtesy of
Amanda E. McKinlay, Snell & WilmerMs. McKinlay may be contacted at
amckinlay@swlaw.com
The AI Knows Too Much: When Employees Feed Trade Secrets into Generative AI Tools
April 14, 2026 —
Kazim A. Naqvi & John V. Mysliwiec - SheppardEvery time an employee pastes proprietary source code, a customer list, or a confidential business strategy into
ChatGPT,
Claude, or
Google Gemini, they may be quietly dismantling the legal protections that make those secrets worth protecting. Courts and regulators are only beginning to grapple with this problem, and right now, the burden of preventing it falls squarely on employers.
The Legal Stakes
Under the federal
Defend Trade Secrets Act (“DTSA”) and the
Uniform Trade Secrets Act (“UTSA”) as adopted across most states, a trade secret plaintiff must show that the information at issue was subject to reasonable measures to maintain its secrecy. Courts have historically credited measures like confidentiality agreements, physical access controls, and employee training—but those safeguards were designed for a world of thumb drives and disgruntled employees. They were not built for a world where a well-meaning engineer can, in seconds, transmit an entire corpus of proprietary data to a third-party AI platform operating under terms of service that may permit the provider to use inputs for model training.
Reprinted courtesy of
Kazim A. Naqvi, Sheppard and
John V. Mysliwiec, Sheppard
Mr. Naqvi may be contacted at knaqvi@sheppard.com
Mr. Mysliwiec may be contacted at jmysliwiec@sheppard.com
Read the full story...