OC Streetcar Project Mediation Sets $50M Payment to Walsh
July 20, 2026 —
Richard Korman - Engineering News-RecordWalsh Construction told a California state court judge last month that lawsuit mediation of its claims on an Orange County light-rail project—known as OC Streetcar—had produced a settlement of some claims under which the county agreed to pay the contractor almost an additional $50 million.
Read the full story...Reprinted courtesy of
Richard Korman, Engineering News-RecordMr. Korman may be contacted at
kormanr@enr.com
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.
Kahana Feld Obtains Favorable Result in High-Exposure NY Premises Liability Case
June 15, 2026 —
Leigh Katz - Kahana FeldKahana Feld partner Leigh Katz obtained a significant victory in a recent matter involving a videotaped alleged trip and fall on the sidewalk in front of the client’s commercial residence. The plaintiff claimed he suffered a knee injury that necessitated surgery, along with other assorted injuries that prevented him from continuing high-level athletic activities. Leigh was able to demonstrate that the fall was staged and received a voluntary discontinuance with prejudice.
At mediation, Leigh emphasized that KF’s expert witness challenged the plaintiff’s claim that the fall was caused by a sidewalk height differential after reviewing the videotape footage and determining the plaintiff’s fall began before his feet made contact with the alleged defect. Based on this analysis, the expert concluded the reported height differential did not initiate the fall, which supported KF’s position that the incident depicted in the video was unrealistic and appeared staged.
Read the full story...Reprinted courtesy of
Leigh Katz, Kahana FeldMs. Katz may be contacted at
lkatz@kahanafeld.com
No Ink, No Problem: When Employees and Agents Can Enforce Arbitration Agreements
August 11, 2026 —
Jordan Heath & Jacob Morrison - ConsensusDocsArbitration is a fundamental component of modern construction contracting. Many in the industry recognize the potential benefits and protections arbitration can provide to the business in the event of a dispute. But an important question many contracts do not address is: who does the arbitration agreement cover? Does it include the business entity only, or the individuals acting on behalf of the entity?
As courts have long recognized, entities can generally only act through their employees, representatives, or agents.[1] This article discusses the circumstances in which an agent may rely on an arbitration provision entered by its employer. This is known as the agency doctrine.
Reprinted courtesy of
Jordan Heath, Associate, Jones Walker LLP and Jacob Morrison, Law Student University of Georgia, Jones Walker LLP
Read the full story...Mr. Heath may be contacted at
jheath@joneswalker.com
Insured’s Bad Faith Claim Survives Summary Judgment
July 13, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer’s motion for partial summary judgment to dispose of the insured’s bad faith claim was unsuccessful. Page v. State Farm Lloyds, 2026 U.S. Dist. LEXIS 102293 (E.D. Texas March 18, 2026).
Plaintiff insured alleged that hail and a windstorm caused damage to his property. The damage was reported to the defendant insurer. A claims adjuster inspected the property. Defendant then paid plaintiff $24,493.06, which was the total of the estimated damage minus depreciation and the deductible.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sixth Circuit Revives Builder’s Risk Coverage, Refusing to Let Insurer Escape on a Technicality
July 27, 2026 —
Kevin V. Small & Adriana A. Perez - Hunton Insurance Recovery BlogIn 3371 Reading, LLC v. Liberty Mutual Group, the Sixth Circuit did something courts do not always do in coverage disputes: it refused to let an insurer avoid liability based on a technical policy condition that could never actually be satisfied.
The decision is a straightforward reminder of two core principles. First, policies must be interpreted from the standpoint of a reasonably prudent insured. Second, hyper-technical conditions cannot be used to deny coverage where compliance is never possible.
Reprinted courtesy of
Kevin V. Small, Hunton Andrews Kurth LLP and
Adriana A. Perez, Hunton Andrews Kurth LLP
Mr. Small may be contacted at ksmall@hunton.com
Ms. Perez may be contacted at pereza@hunton.com
Read the full story...
Real Estate & Construction News Roundup (8/19/26) – Single-Family Housing Investors Worry, Confidence in Multifamily REITs and Construction Backlog Falls
September 08, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, U.S. Chamber of Commerce creates Housing Advisory Council, a legal battle develops over new federal rules related to mortgage escrow accounts, hospitality dealmakers pursue ‘bigger, higher-conviction’ M&A, and more!
- In the wake of the 21st Century ROAD to Housing Act becoming law, the U.S. Chamber of Commerce has created a Housing Advisory Council with the goal of advancing market-driven policies that help increase housing supply and promote affordability. (Julie Strupp, Multifamily Dive)
- Investors in the single-family housing market are increasingly concerned about interest rates, rising insurance and home costs, and the ongoing war with Iran. (Diana Olick, CNBC)
- A legal battle is brewing over new federal rules related to accounts that hold money to pay homeowners’ property taxes and insurance payments. (Sarah Agostino, CNBC)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Document Everything! Always! No Exceptions! (AKA, Help Your Lawyer Help You!)
April 14, 2026 —
Melissa Dewey Brumback - Construction Law in North CarolinaI had a case last year in which once again I found myself thinking: if only my client had better documented the verbal agreements, we would have had a much easier time defending his work.
I know this is often easier said than done— you are in the middle of building a project, and you get a call, and you need to keep the project moving. No time for written change directives or a special bulletin. And yet—it is simply amazing to me the number of people who develop “litigation amnesia” about things when a lawsuit is involved.
Your documentation system does not need to be perfect. You can use a simple Field notebook and handwritten notations. A text memo to yourself or, better yet, an email confirmation to the owner/contractor/whoever.
Read the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com