Introducing the Updated 2026 Pillsbury Guide to Data Centers
June 08, 2026 —
Gravel2Gavel Team - Gravel2Gavel Construction & Real Estate Law BlogSince the initial publication of the Pillsbury Guide to Data Centers in 2025, the market has continued to evolveâmost notably with respect to power availability, energy strategy, tax and incentives planning, and investment activity across the sector. While many of the legal, commercial and regulatory frameworks addressed in the original Guide remain durable and relevant, recent developments warranted targeted updates and additions.
The
2026 edition expands and updates our energy-focused content to reflect the increasingly central role of power procurement, interconnection and long-term energy strategy in data center development. We have incorporated new materials addressing power purchase and interconnection agreements, solar and other renewable energy solutions, advanced reactor designs, and nuclear-powered data centers projects, including an updated project tracker. We have also added new analysis covering state and local tax considerations and incentive structures relevant to data center development and operations, as well as current M&A and private equity trends shaping investment in the sector.
Read the full story...Reprinted courtesy of
Gravel2Gavel Team
Tampa Team Obtains Highly Favorable Verdict for Property Owner Client in Lawsuit over Traffic Accident
March 24, 2026 —
Lewis Brisbois NewsroomTampa Managing Partner John Rine and Partner Nick Dareneau obtained a very favorable verdict for their property owner client in a Sarasota County trial in a lawsuit arising from a traffic accident. At the end of closing arguments, plaintiffâs counsel requested appropriately $18 million from the jury. The jury returned a net verdict of just over a thousand dollars.
The plaintiff was on a scooter and was involved in an accident with an SUV in a parking lot intersection. Our firm represented the property owner. The plaintiffs argued that the landscape vegetation was too tall and violated the sight lines of the two drivers, and that the height of the shrubbery violated the ownerâs landscaping contract and a local sight line ordinance. They also argued that the intersection lacked a stop sign in contrast to the other six parking lot entrances, which had stop signs.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Anti-Concurrent Causation Clause Prevents Coverage for Collapse
April 27, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court affirmed the decision of the trial court granting summary judgment to the insurer after agreeing that the policyâs anti-concurrent causation clause barred coverage. Lido Hospitality, Inc. v. AIX Specialty Ins. Co., 2026 Iii. App. Unpub. LEXIS 133 (Ill. Ct. App. Jan. 27, 2026).
One of the brick veneer walls of the Lido Motel collapsed during a windstorm. Lido reported the loss it its insurer, AIX. AIX investigated and determined that the brick veneer collapsed due to pervasive wear and tear and corrosion of the underlying infrastructure that secured the veneer- specifically the components that anchored or tied the masonry veneer to the underlying wooden substrate.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Two Snell & Wilmer Attorneys Selected as 2026 San Diego Super Lawyers Rising Stars
May 14, 2026 —
Snell & WilmerSAN DIEGO â Snell & Wilmer is pleased to announce that two attorneys in the San Diego office have been selected for inclusion in the
2026 San Diego Super Lawyers Rising Stars publication.
Rising Stars is a listing of lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. To be eligible for inclusion, a candidate must be either 40 years old or younger or in practice for 10 years or less. The selection process is multi-phased and includes independent research and peer nominations, with no more than 2.5 percent of the lawyers in the state named to the Rising Stars list.
Read the full story...Reprinted courtesy of
Snell & Wilmer
Turnover Traps for Community Associations: Investigate First, Release Claims Later
April 14, 2026 —
Nicholas B. Vargo - Ball Janik LLPTurnover of a community association from developer control to owner control is a uniquely vulnerable moment. Developers are increasingly presenting Florida condominium and homeownersâ associations with âstandardâ settlement or release agreements at turnover, often being framed as routine steps to finalize the transition of control. In reality, these agreements can have sweeping consequences, including the release of construction-defect claims before the association has conducted any meaningful independent evaluation.
The developer has years of project knowledge and access to plans, subcontractors, and internal records. The newly elected board is just beginning to organize, obtain documents, and understand the propertyâs condition. Many defects, especially those involving roofing, waterproofing, windows, or structural components, are latent and not yet visible. Signing a release at this stage means the association is making a binding decision under conditions of uncertainty, without full information, to release all future potential claims.
Over the last few years, there has been a rise in reports of developers offering a packaged deal: they agree to complete certain repairs, often minor punch-list or cosmetic items, and to âforgiveâ an alleged financial deficit (often around $50,000) supposedly owed by the association from the developer-control period. In exchange, the association is asked to sign a broad release covering all claims, including known and unknown construction defects. To a new HOA board that received their community with limited operating and reserve funds, they are left with a difficult decision to either accept the developerâs offer or assess their owners to pay this alleged debt.
These agreements are occasionally presented through community management companies, which may describe them as âstandardâ or "routine.â Whether due to misunderstanding or influence from the developer, management companies can unintentionally reinforce the idea that signing is expected. Any recommendation provided to HOAs about whether to sign these releases could open community management to liability down the road. The best practice for both associations and community managers is to refer any agreements to be reviewed by general counsel for the association.
The following two case studies illustrate the real-world consequences:
Case Study One: A newly transitioned board relies on its management company to negotiate with the developer-builder to resolve irrigation issues, pond concerns, and signage deficiencies, along with forgiving an asserted financial shortfall. In exchange, the board signs a broad release covering all claims, including latent defects.
Within a year, several punch-list items remain incomplete, and more serious issues arise. When the association demands completion, the developer delays, prompting the association to seek advice on how to enforce the settlement agreement. The association hires counsel to hold the developer responsible for both the previously agreed-upon items and newly identified construction defects. However, when the association brings claims against the developer, the developer points to the release of all potential construction defects in the community. Thus, the only remaining remedy is limited to enforcement of the specific punch-list terms. The community, still relatively new, has no viable claims against the developer-builder for the construction defects. With warranties expired and the release, the association must fund repairs through special assessments, despite defects that would otherwise have been actionable.
Case Study Two: A community is presented with a similar agreement as above. The management company encourages execution, suggesting it is standard and even telling the board to âname your price.â The developer also pressures the newly elected board to sign.
Instead of signing, the board consults with their attorney. Counsel advises the board not to sign the release and recommends further investigation. Engineers are retained and identify early indicators of broader issues, including stucco cracking, water intrusion, and irrigation deficiencies. Based on this information, the association declines to sign the release. Subsequent evaluation reveals potentially significant construction-defect claims, allowing the community to pursue recovery that would have been lost under the proposed agreement.
These scenarios underscore a fundamental point: signing a release at turnover is not an administrative formalityâit is a major legal decision. Board members act in a fiduciary capacity on behalf of their community, and their decisions can bind all current and future owners. At turnover, an associationâs right is to investigate and pursue claims. Preserving that right until a full and independent evaluation is completed is not adversarialâit is responsible governance.
Accordingly, associations should retain independent evaluations of the property and consult qualified legal counsel before signing any âstandardâ agreements, especially ones involving a release of future claims.
Nicholas B. Vargo is a partner in Ball Janik LLPâs Construction Practice Group. He may be reached at nvargo@balljanik.com.
Lawmakers Vote to Reauthorize Programs to Support Water Quality, Coastal Protection
April 20, 2026 —
Pam McFarland - Engineering News-RecordThe U.S. House of Representatives has passed a package of 14 bills that includes measures to reauthorize several U.S. Environmental Protection Agency programs to protect and restore critical water ecosystems, expand access to broadband, reduce regulatory requirements on airport projects and programs and lower costs of federal buildings.
Read the full story...Reprinted courtesy of
Pam McFarland, Engineering News-RecordMs. McFarland may be contacted at
mcfarlandp@enr.com
What Construction Attorneys Do and When Contractors Need Them
August 11, 2026 —
Construction ExecutiveDirect Answer
A construction attorney advises contractors on contracts, payment rights, mechanic's liens, payment bond claims, change orders, delay claims, OSHA matters, defect claims, terminations and dispute resolution. The work covers far more than lawsuitsâmuch of its value comes before a dispute ever becomes formal.
Construction attorneys help contractors protect payment rights, manage project risk, resolve disputes and avoid contract terms that can turn a profitable job into a financial loss. Their work covers more than lawsuits. A construction attorney may review a contract before bid day, help preserve lien rights, respond to a defective work claim, prepare for mediation or defend a contractor after a safety citation.
For contractors, legal counsel is often most valuable before a dispute becomes formal. A missed notice deadline, vague scope clause, unsigned change order or broad indemnity provision can create problems long before a claim is filed. Construction attorneys help identify those risks while there is still time to negotiate, document the issue or preserve leverage.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Insufficient Notice of Commencement and Construction Lien Rights
August 03, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice to Owner company will typically rely on the Notice of Commencement to serve Notices to Owners from lower tiers not in contract with the owner. However, when it comes to preparing the lien, a lienor should look beyond just the Notice of Commencement and also look to the property appraiserâs website as a backstop.
In a recent case, a window company had the homeowner sign the Notice of Commencement and then filled in the information. The company naturally did this for the convenience of the homeowner that probably was unfamiliar with the Notice of Commencement process. Regardless, information in the Notice of Commencement was inaccurate. It failed to include all the real property owners. Thus, when a payment dispute arose and a construction lien was prepared, it did not identify all of the real property owners. All of the real property owners were added later during the pendency of a lien foreclosure lawsuit. The trial court denied the lien because of the defective / insufficient Notice of Commencement â the lienor assumed the risk of error by filling out the information in the Notice of Commencement. The trial court further denied the lien holding that because the work did not commence within 90 days of the Notice of Commencement, the Notice of Commencement is void.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com