Arizona Court of Appeals Clarifies Homeowners Association Open Meeting Requirements
June 29, 2026 —
Jill Casson Owen, Benjamin J. Hawkins & Stephen Wright - Snell & WilmerA Z N H Revocable Trust v. Sunland Springs Village Homeowners Association, No. 1 CA-CV 25-0424 (Ariz. Ct. App. Apr. 28, 2026)
OVERVIEW
The Arizona Court of Appeals issued an opinion clarifying how homeowners associations must conduct meetings under A.R.S. § 33-1804. The decision reinforces the legislative policy favoring transparency in association governance, bringing association meeting requirements more in line with the open meeting standards applicable to public bodies under A.R.S. § 38-431 et seq. (Arizona’s Open Meeting Law).
KEY HOLDINGS
1. All Voting and Formal Actions Must Occur in Open Meetings
The Court affirmed that association boards cannot vote or take formal action during closed (executive) sessions. Under A.R.S. § 33-1804(A), associations may close portions of meetings only for “consideration” of certain enumerated topics, such as legal advice, pending litigation, or personal/financial information about individual members. The Court interpreted “consideration” to mean discussion and deliberation, not voting. The Court noted that dictionaries define “consider” as “spending time thinking about a possibility” and “formulating an opinion,” which are processes that precede formal action. This interpretation mirrors how Arizona’s Open Meeting Law (A.R.S. § 38-431.03(D)) prohibits public bodies from voting in executive session.
Reprinted courtesy of
Jill Casson Owen, Snell & Wilmer,
Benjamin J. Hawkins, Snell & Wilmer and
Stephen Wright, Snell & Wilmer
Ms. Owen may be contacted at jowen@swlaw.com
Mr. Hawkins may be contacted at bhawkins@swlaw.com
Mr. Wright may be contacted at swright@swlaw.com
Read the full story...
DOI Finalizes Long-Awaited Modernization of Type A Natural Resource Damage Assessment Regulations
August 03, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogFor nearly three decades, the U.S. Department of the Interior’s (DOI) simplified “Type A” Natural Resource Damage Assessment (NRDA) regulations were available more in theory than in practice, constrained by dated models, narrow geographic applicability and a $100,000 cap that rarely matched the economics of modern environmental claims. DOI has now finalized revisions to the Type A natural resource damages assessment procedures under 43 C.F.R. Part 11 for hazardous substance releases under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Clean Water Act (CWA), with the final rule published in the
Federal Register on July 13, 2026 and scheduled to become effective August 12, 2026.
As discussed
previously, DOI has sought to modernize what it views as an “inefficient and inflexible” process and restore the Type A procedure to its intended role as a more streamlined pathway for smaller, less contentious NRD claims. The final rule adopts a $5 million default damages threshold, allows use above that amount if all parties agree, clarifies that Type A may be used in all environments and for all natural resource types, and removes legacy model appendices that had tethered the process to outdated formulas.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
AI in AEC 2026: Doing AI Right and Rethinking Your Business Model
April 08, 2026 —
Aarni Heiskanen - AEC BusinessThe sixth AI at the AEC 2026 conference showcased the evolution of AI discussions. There were, naturally, many talks about software and technologies. But more than before, there were conversations about realizing AI’s business value.
Two themes appeared in nearly every session I attended. First, many companies struggle with AI adoption, not because they lack tools, but because their thinking isn’t right. Second, when AI works, it disrupts the business model that brought them there.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Additional Insureds Owed a Defense in Underlying Personal Injury Suit
March 03, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted partial summary judgment on the duty to defend to two additional insureds who were named as defendants in the underlying personal injury suit. In re Third St. Equity, LLC, 2025 U.S. Dist. LEXIS 234909 (E.D. N. Y. Dec. 2, 2025).
Third Street Equity LLD hired Developing NY State, LLC as the contractor for a construction project. Developing NY entered a subcontract agreement with Capital Source Concrete NY LLC for concrete work as well as labor and services for a construction project. The subcontract required that Capital Concrete keep the construction site free of debris, waste material or rubbish. Further, Capital Concrete was responsible for compliance with OSHA safety regulations. It was also agreed that Capital Concrete would obtain liability and workers compensation insurance naming Third Street and Developing NY as additional insureds.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Building in Arizona’s Data Center Boom: How Federal Executive Orders, State Regulation, and National-Security Policy Are Reshaping the Rules for Developers
June 02, 2026 —
Ryan J. Regula - Snell & WilmerDevelopers and practitioners evaluating data center projects in Arizona face a regulatory environment shifting on three fronts simultaneously. Federal executive orders are opening new land, streamlining permitting, and channeling financial incentives toward qualifying projects — but they are not preempting the state and local rules that most directly affect project economics. A carve-out in the December 2025 Artificial Intelligence (AI) Framework Executive Order preserves Arizona’s authority over data center infrastructure, meaning the Arizona Corporation Commission’s (ACC) rate-classification docket, municipal zoning restrictions, water-use ordinances, and pending grid cost-allocation legislation remain the binding constraints on project feasibility. Understanding where federal tailwinds end and state and local headwinds begin is essential for any developer sizing risk or selecting sites in the state.
The Federal Landscape: An Interlocking Framework of Executive Orders
Five interlocking executive orders are accelerating data center development nationally, but none overrides Arizona’s authority over siting energy, or infrastructure.
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
Thomson Reuters Construction Law (Virginia Practice Series)
March 31, 2026 —
Jennifer L. Harris & Michael A. Branca - Peckar & Abramson, P.C.P&A Partners Michael A. Branca and Jennifer L. Harris have authored the most recent edition (2025) of Construction Law (Virginia Practice Series), part of Thomson Reuters’ ProView legal reference library. Associate
Julia Loudenburg also provided substantial assistance for this edition.
Construction Law includes summaries and analysis of statutes, regulations, and cases. It covers all major legal issues, including:
- Licensing
- Building code compliance
- Public-private partnerships
- Public contract bidding and performance
- Dispute resolution
- Damages
- Third-party liability
- Liens and bonds
Reprinted courtesy of
Jennifer L. Harris, Peckar & Abramson, P.C. and
Michael A. Branca, Peckar & Abramson, P.C.
Ms. Harris may be contacted at jharris@pecklaw.com
Mr. Branca may be contacted at mbranca@pecklaw.com
Read the full story...
A Couple of Mechanic’s Lien Bills in VA [UPDATED]
February 23, 2026 —
Christopher G. Hill - Construction Law MusingsWell, its that time of year again, the Virginia General Assembly is in session and looking to make changes to all kinds of things here in the Commonwealth. While most of those changes are well outside of the subject of Construction Law Musings, changes to the
mechanic’s lien statutes certainly are not. This year, the Virginia General Assembly is poised to make some big changes if certain legislation gets out of committee and passes the legislature, a description and some comments on these follow:
HB752 – Mechanics’ liens; liens attaching to property; memorandum of lien. [Original Description] Removes the exclusion of the attachment of a mechanic’s lien to property improved or repaired when the lien is based on a claim for repairs or existing structures. The bill further removes (i) the ability of a lien claimant to file any number of memoranda of lien including the details relating to the lien and (ii) the provisions of the Code specifying that no memorandum filed shall include sums due for (a) labor or materials furnished more than 150 days prior to the last day labor was performed or (b) material furnished to the job preceding the filing of such memorandum.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Single Source of Truth in Construction Projects: Reality or Myth?
March 24, 2026 —
Aarni Heiskanen - AEC BusinessThe idea of a single source of truth has been a fundamental part of the digital vision in the AEC industry for many years. From centralized CAD storage to BIM collaboration platforms and, more recently, Common Data Environments, the goal stays the same. Project teams want a reliable place where everyone can access the latest information.
The phrase “single source of truth” comes from database and information management practices in the IT world, where the goal was to maintain one authoritative record of data and eliminate data redundancy. As the AEC industry began adopting digital tools, the same idea was applied to project information and workflows.
Despite decades of technological progress, the question remains whether “one ring that rules them all” can actually be implemented in real construction projects.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi