Insured Does Not Prevail on Summary Judgment Motion Invoking Ensuing Loss Provision
May 05, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insured’s motion for summary judgment finding genuine issues of fact regarding implication of the policy’s ensuing loss provision. Stella Prop. Dev.. & Event Productions, LLC v. Auto-Owners Ins. Co., 2026 U.S. Dist. LEXIS 15854 (W.D. Pa. Jan. 28, 2026).
Stella owned a cultural center that was insured under a commercial property all-risk policy issued by Auto-Owners. A windstorm with gusts of 65 miles per hour struck the Center causing damage. The Center’s inspector found extensive wind damage on nearly all facets of the roof. Further, the inspector found the existing organic shingles were in “very poor condition” and were “defective, discontinued, and no longer available.” The estimated cost of repairs to the roof was $108,010.52.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
How AI Turns Construction Documents Into Procurement Intelligence
May 05, 2026 —
Aarni Heiskanen - AEC BusinessMEP equipment accounts for up to 40% of costs on data center or hospital projects, has lead times ranging from 20 weeks to over a year, and has historically been the most underserved area in construction software. In
this episode, I speak with Victor Muchiri from BuildVision about what it actually takes to make AI useful in construction procurement, not as a pilot, but in production.
We dig into why you cannot simply upload a set of construction drawings to ChatGPT and trust the output. Construction documents are complex, cross-referenced, and consequential. Without deep domain context, such as manufacturer ontologies, equipment taxonomies, and engineering expertise, AI produces plausible results, not reliable ones. BuildVision’s approach is to act as a harness around AI models, wrapping them in construction-specific knowledge so the output can be trusted for real procurement decisions.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
New York Team Secures Dismissal of Premises Liability Action Against Client
May 26, 2026 —
Lewis BrisboisNew York Associate Nicole Koch and Partner Jennine Gerrard recently secured a complete dismissal of a plaintiff’s claims for injuries following a fall in front of a client’s business at an outdoor mall.
The plaintiff alleged that she was walking on the sidewalk outside of the client's hair care supply store in the Bronx in May 2024 when she tripped and fell on a broken/defective portion of the sidewalk. As a result of the accident, the plaintiff suffered injuries to her spine, hip, wrist, and both knees. She proceeded to file suit in New York County Supreme Court against Lewis Brisbois’ client and the landlord for the property.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Insurer Granted Summary Judgment on Claim for Roof Damage Caused by Windstorm
May 26, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer successfully moved for summary judgment, eliminating the insured’s claim for roof damage due to windstorm. Mulas v. Westchester Surplus Lines Ins. Co., 2026 U.S. Dist. LEXIS 20537 (Jan. 30, 2026).
The insureds’ commercial property sustained windstorm damage during Hurricane Ian. Westchester denied the claim. The insureds believed Westchester wrongfully denied coverage for roof damage and various interior damage to property. The insureds also argued that Westchester’s actual cash value (ACV) payment did not reflect the fully insured loss.
The insureds sued and Westchester moved for summary judgment. Westchester argued the roof damage was not covered because Hurricane Ian did not cause the damage. Westchester hired an engineer who determined the roof damage was not caused by wind from Hurricane Ian. Westchester pointed out that the insureds’ expert also found no wind damage on the roof. The insureds offered no other evidence suggesting the hurricane caused roof damage. Therefore, the insureds could not show that Westchester breached the policy by denying coverage.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
ACEC Supports BUILD America 250 Act as Important First Step on Surface Reauthorization
May 26, 2026 —
The American Council of Engineering CompaniesWASHINGTON -- The American Council of Engineering Companies (ACEC), the business voice of America’s engineering and design services industry released the following statement on the BUILD America 250 Act:
"Chairman Graves and Ranking Member Larsen have taken an important bipartisan step toward reauthorizing the federal surface transportation programs that are critical to economic growth in every state. The BUILD America 250 Act provides five years of stability in funding road and transit projects, raises new revenues to address the solvency of the Highway Trust Fund, and includes meaningful provisions to strengthen project delivery, advance digital infrastructure, and improve the contracting framework that engineering firms rely on every day. ACEC will continue to advocate for investment levels that keep pace with the country's growing infrastructure needs, and we urge the Committee to keep this process moving forward."
The American Council of Engineering Companies (ACEC) is the business association of America’s engineering industry, representing more than 5,500 independent engineering firms and more than 650,000 professionals throughout the United States engaged in the development of America’s transportation, water, and energy infrastructure, along with environmental, industrial, and other public and private facilities. Founded in 1906 and headquartered in Washington, D.C., ACEC is a national federation of 51 state and regional organizations.
The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Self-Healing Infrastructure Could Pave the Road to the Future
May 05, 2026 —
Allan C. Van Vliet - Gravel2Gavel Construction & Real Estate Law BlogA single hairline crack in a bridge deck can seem insignificant. But left undetected, minor cracks and fissures expand, water seeps in, steel corrodes and repair costs start to increase. This risk multiplies across thousands of miles of aging highways and bridges nationwide.
As infrastructure endures increasing strain from heavier traffic, extreme weather and deferred maintenance, engineers are exploring “self-healing” systems, where streets and bridges are built with materials that can repair themselves. Concrete, asphalt and composites capable of detecting and mending microcracks autonomously are moving from laboratory research to pilot projects. But while emerging technology promises longer-lasting infrastructure, it also raises questions about long-term maintenance, performance guarantees, procurement frameworks and risk allocation.
Read the full story...Reprinted courtesy of
Allan C. Van Vliet, PillsburyMr. Van Vliet may be contacted at
allan.vanvliet@pillsburylaw.com
The Great Escape: Non-Invalidation Clauses and Property Damage Claims
October 20, 2026 —
Abigail Smith & Kaarthiga Manimaran - SDV FenchurchAt their core, non-invalidation clauses (“NICs”) recognise an important commercial reality: an insured cannot control everything that happens at its premises.
In the event that an insured finds itself in breach of a condition or warranty owing to events that have increased the risk of damage to its property, but which were outside its authority, knowledge or beyond its control, a NIC may prevent the insurer from avoiding the claim. For that reason, they’re an important tool in an insured’s coverage arsenal.
Although there is relatively little caselaw on NICs, their purpose was recognised in The Seashell of Lisson Grove Ltd v Aviva Insurance Ltd [2011] EWHC 1761 (Comm) (on which we wrote a previous article –
The Good, the Bad & the Ugly: #26 The Good: The Seashell of Lisson Grove Ltd v Aviva)
Reprinted courtesy of
Abigail Smith, SDV Fenchurch and
Kaarthiga Manimaran, SDV Fenchurch
Ms. Smith may be contacted at abigail.smith@sdvfenchurch.uk
Ms. Manimaran may be contacted at kaarthiga.manimaran@sdvfenchurch.uk
Read the full story...