The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Tampa Team Obtains Highly Favorable Verdict for Property Owner Client in Lawsuit over Traffic Accident
March 24, 2026 —
Lewis Brisbois NewsroomTampa Managing Partner John Rine and Partner Nick Dareneau obtained a very favorable verdict for their property owner client in a Sarasota County trial in a lawsuit arising from a traffic accident. At the end of closing arguments, plaintiff’s counsel requested appropriately $18 million from the jury. The jury returned a net verdict of just over a thousand dollars.
The plaintiff was on a scooter and was involved in an accident with an SUV in a parking lot intersection. Our firm represented the property owner. The plaintiffs argued that the landscape vegetation was too tall and violated the sight lines of the two drivers, and that the height of the shrubbery violated the owner’s landscaping contract and a local sight line ordinance. They also argued that the intersection lacked a stop sign in contrast to the other six parking lot entrances, which had stop signs.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Are “Financial Hardship” Damages Recoverable?
June 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn a case out of the Civilian Board of Contract Appeals, F.O.G., LLC v. Department of the Interior, CBCA 8203, 2026 WL 1191881 (CBCA 2026) a contractor claimed damages that included “financial hardship” damages due to slow payments. The financial hardship damages included personal damages to the contractor’s president and his wife. Are these damages recoverable? Drumroll…The Board ruled that the contractor cannot recover such financial hardship damages.
As it relates the personal financial hardship damages, the Board ruled, “Neither [the contractor’s] president nor his wife are a party to this contract, are in privity of contract with [the government], or are the beneficiaries under this contract. [The contractor], therefore, cannot recover for any losses that either one has suffered individually and that [the contractor] claimed in this appeal.” F.O.G., LLC, supra.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Identifying Unfair Clauses in Construction Contracts
February 17, 2026 —
Curtis W. Martin - Peckar & Abramson, P.C.In 1979, virtually all projects were completed under form contracts. As I started practicing construction law, it seemed that most form contracts were generally fair. They were negotiated by industry groups and over the next 10-20 years they appeared to become fairer. We could and did compare provisions in the AIA documents, the Federal contract forms, and the EJCDC agreements. When we did, we found subtle differences, but broad similarities in their approach to contract risk allocation.
Today many (most?) private projects are done with “manuscript” contracts – instruments tailored to the owner’s interests. And many public entities have developed their own contracts. And not all those clauses seem so fair.
This month I focus on contract clauses that I consider unfair. And while unfairness, like beauty, may be in the eye of the beholder, I think that the clauses described below aptly fit that descriptor.
Read the full story...Reprinted courtesy of
Curtis W. Martin, Peckar & Abramson, P.C.Mr. Martin may be contacted at
cmartin@pecklaw.com
U.S. Supreme Court Decision Alters Course of $745M Louisiana Coastal Damage Judgment
June 15, 2026 —
Jennifer Kretschmann & Jennifer E. Michel - Lewis BrisboisThe U.S. Supreme Court has issued a unanimous decision allowing oil and gas companies to move Louisiana coastal erosion lawsuits from state court to federal court under the federal officer removal statute. While the ruling is procedural, it carries significant implications for environmental- and energy-related risks. The case,
Chevron U.S.A. Inc. v. Plaquemines Parish, Louisiana, Slip Op. 24-813 (April 17, 2026), addressed a threshold jurisdictional question but has broader significance for environmental and climate related litigation. State courts are often viewed as more favorable forums for plaintiffs asserting environmental damage claims, particularly those brought by governmental entities.
The opinion issued on April 17, 2026 is the latest development in long-running Louisiana coastal litigation that began more than a decade ago. Starting in 2013, Louisiana parishes filed 42 lawsuits against oil and gas companies alleging environmental damage related to historic oil field operations. The parishes alleged that oil and gas companies violated state coastal management laws by failing to properly restore impacted areas. Chevron sought to remove the cases from state court under 28 U.S.C. § 1442(a)(1), known as federal officer removal, which provides federal jurisdiction over “any person acting under [an] officer” of the United States "for or relating to any act under color of such office." The Fifth Circuit rejected the argument and remanded the case, and others like it, to state court. Trial began in March 2025 in Point à la Hache, Louisiana. On April 4, 2025, the jury awarded a total of $745 million to compensate for land loss, contamination and abandoned equipment. On June 16, 2025, the U.S. Supreme Court agreed to review the question of whether a federal contractor can remove to federal court when sued for oil-production activities undertaken to fulfill a federal oil-refinement contract.
Reprinted courtesy of
Jennifer Kretschmann, Lewis Brisbois and
Jennifer E. Michel, Lewis Brisbois
Ms. Kretschmann may be contacted at Jennifer.Kretschmann@lewisbrisbois.com
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Read the full story...
Brenda Radmacher Authors Chapter in ABA Publication on Construction Delays
May 26, 2026 —
Brenda Radmacher - The Construction SeytBrenda Radmacher, a partner in Seyfarth’s Construction Law practice and a mediator and arbitrator serving on the American Arbitration Association’s panels, is among the contributing authors to the American Bar Association’s forthcoming guide on construction disputes: Time – The Legal Implications of Project Delay in Construction.
Drawing on three decades of experience, Radmacher authors Chapter 8, Contractor Delay Damages, offering practical insight into one of the most contested issues in construction litigation and arbitration.
Read the full story...Reprinted courtesy of
Brenda Radmacher, Seyfarth Shaw LLP
Ball Janik LLP Welcomes Construction Defect Attorney and U.S. Air Force Veteran Jake Scott to its Fort Lauderdale Office
June 02, 2026 —
Ball Janik LLPBall Janik LLP, a leading construction defect and insurance recovery law firm, has welcomed Jake Scott as an associate in its Fort Lauderdale office. Scott joins the Construction Defect Practice Group, bringing experience across construction litigation that includes construction defect, contract dispute, and negligence matters, along with a track record of representing construction professionals through depositions, court appearances, and trial preparation to support the firm's steady growth and client service statewide.
"We're excited to welcome Jake Scott to our Fort Lauderdale office and Construction Defect Practice Group," said James C. Prichard, Managing Partner at Ball Janik LLP. "We look forward to the fresh perspectives and legal solutions he will provide for community associations across South Florida."
Scott is a results-driven attorney dedicated to providing strategic counsel for complex legal challenges. He has experience managing all phases of a case, from early investigation and discovery through trial preparation and settlement negotiations.
Prior to joining Ball Janik, Scott served as an associate attorney in Fort Lauderdale, where he represented clients in construction litigation matters, handled depositions and court appearances, conducted legal research, and drafted pleadings, motions, and briefs. He also worked as an attorney in Tampa, where he represented contractors, subcontractors, and construction firms in defending claims involving construction defects, contractual disputes, and negligence, and worked closely with expert witnesses, engineers, and consultants to develop and present technical evidence.
Scott's experience representing the development and building sides of construction disputes provides a valuable, contrast-driven perspective that supports the strategic evaluation of claims and practical approaches to resolution for Ball Janik's clients.
A proud veteran, Scott served in the United States Air Force for eight years, including roles as an Airspace Control Officer and in Space Systems Operations, supporting safe space flight operations and satellite communications.
Carrying the discipline of airborne operations, Scott worked in the aerospace sector as a Satellite Engineer and Orbital Analyst. He also held a role in the housing sector, supporting marketing and business development initiatives.
Scott received his law degree from Stetson University College of Law. He attended American Military University, where he earned degrees in marketing, business management, and related support services.
About Ball Janik LLP
Ball Janik LLP is a Florida-based law firm offering construction defect, construction law, insurance recovery, and commercial litigation counsel to its local and national clients. The firm was founded in 1982 and has expanded its capabilities, professionals, and geographic footprint. What started as a small firm focused on real property, land use, and litigation (known then as Ball Janik & Novack) has grown to a team of 50-plus attorneys and paralegals in 5 offices in Florida, with centuries of combined experience and capabilities. The firm has been recognized by Chambers USA, U.S. News & World Report and Best Lawyers®, The Best Lawyers in America©, and Corporate International. Read more here: https://www.balljanik.com.
Yet Another Reason That Your Contract Matters
February 10, 2026 —
Christopher G. Hill - Construction Law MusingsI have discussed on several occasions the fact that
construction contracts matter. The words in contracts matter and, in Virginia (as well as other states), most provisions, if not all
will be enforced to the letter. Recently, the Western District of Virginia federal court ruled in a way that reminded me of another reason for a well-drafted contract.
In
Rockingham Precast, Inc. v. American Infrastructure – Maryland, Inc. the Western District of Virginia Court considered a motion to transfer the venue to Maryland filed by American Infrastructure. The plaintiff, Rockingham Precast, a Virginia-based company sued in Virginia. American Infrastructure conceded that VA could be a proper forum for the lawsuit but argued that the form was much too inconvenient and costly for the party and non-party witnesses and that the cost made the forum an unfair place to try the case.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com