Newmeyer Dillion Ranked in Chambers Spotlight California 2026 Guide
May 26, 2026 —
Newmeyer DillionNEWPORT BEACH, Calif. – May 14, 2026 - Prominent business and real estate law firm Newmeyer Dillion has been ranked in Chambers Spotlight California 2026 guide and recognized as a leading firm in Litigation: General Commercial for Orange County.
Newmeyer Dillion was selected based on an independent and in-depth market analysis, coupled with an assessment of the firm’s experience, expertise and caliber of talent where the firm stood out for its exceptional work and is recognized in Litigation: General Commercial.
Managing Partner Paul Tetzloff expressed the firm's gratitude: “It is an honor for our firm to be recognized by Chambers and Partners in their Spotlight California 2026 guide. This acknowledgment reflects our commitment to providing high quality legal services tailored to the unique needs of our clients.”
Read the full story...Reprinted courtesy of
Newmeyer Dillion
Lost in Translation: AEC Tech’s Missing Role
May 12, 2026 —
Aarni Heiskanen - AEC BusinessI once visited a construction site where the contractor’s headquarters had commissioned a tech company to build an on-site quality-inspection application. The developer had admitted to the site engineer that they had never set foot on a construction site before. The engineer showed me what he was actually using: his own phone camera and an Excel sheet. The new app did not map to how work actually happened on site.
This is not an isolated story. The vendor builds something technically coherent but operationally disconnected. The client, somewhere up the chain, had fallen in love with the idea of the solution before anyone had built an honest business case for it.
The result is a tool that gets demonstrated at a board meeting but isn’t used in the field.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
New York Team Secures Dismissal of Premises Liability Action Against Client
May 26, 2026 —
Lewis BrisboisNew York Associate Nicole Koch and Partner Jennine Gerrard recently secured a complete dismissal of a plaintiff’s claims for injuries following a fall in front of a client’s business at an outdoor mall.
The plaintiff alleged that she was walking on the sidewalk outside of the client's hair care supply store in the Bronx in May 2024 when she tripped and fell on a broken/defective portion of the sidewalk. As a result of the accident, the plaintiff suffered injuries to her spine, hip, wrist, and both knees. She proceeded to file suit in New York County Supreme Court against Lewis Brisbois’ client and the landlord for the property.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Settlement Agreements and Contracts Require a Meeting of the Minds
July 20, 2026 —
David Adelstein - Florida Construction Legal UpdatesA settlement agreement does not need to be executed for it to be enforceable as long as there was a MEETING OF THE MINDS. The same rings true for any contract regardless of whether the contract is signed – THERE NEEDS TO BE A MEETING OF THE MINDS.
In a recent case dealing with the settlement agreement on a construction lien, the essential settlement terms (money and mutual release) were memorialized in an e-mail exchange between the parties (owner and subcontractor). The settlement required the owner to pay the principal amount plus some attorney’s fees and then a mutual general release would be prepared. In response to the confirmatory email, the owner sent a check, which the subcontractor deposited, but the owner refused to sign the release signed and sent by the subcontractor. The owner further claimed it doesn’t need to pay the attorney’s fees because the lien amount was paid in full. The subcontractor sued arguing the owner breached the terms of the settlement. The appellate court agreed.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Safeguarding Your Privileged Construction Information With a Clawback Agreement
June 08, 2026 —
Laura Fraher - Construction ExecutiveFor contractors and construction executives, a
dispute that escalates to litigation brings risks that go well beyond the jobsite. When a dispute escalates to litigation, the attorney-client privilege is a critical protection to safeguard your interests. Disclosing privileged material can undermine your litigation position and, in some cases, negatively impact your business. In the construction context, this often includes sensitive communications about project delays, defect investigations, safety incidents or payment disputes—materials that can significantly impact both liability and reputation.
During litigation, the discovery process requires the exchange of documents and data with your adversary. If privileged materials are disclosed to your adversary during discovery you risk the waiver of your privilege, which in plain terms means you lose the protection of the privilege and make the privileged information, and in some cases all other information related to the same subject matter, available to your adversary. It is critical that your attorney take steps to protect against the unintentional disclosure of privileged materials during discovery to avoid a waiver.
Reprinted courtesy of
Laura Fraher, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Ms. Fraher may be contacted at
lfraher@barclaydamon.com
AI in AEC 2026: Doing AI Right and Rethinking Your Business Model
April 08, 2026 —
Aarni Heiskanen - AEC BusinessThe sixth AI at the AEC 2026 conference showcased the evolution of AI discussions. There were, naturally, many talks about software and technologies. But more than before, there were conversations about realizing AI’s business value.
Two themes appeared in nearly every session I attended. First, many companies struggle with AI adoption, not because they lack tools, but because their thinking isn’t right. Second, when AI works, it disrupts the business model that brought them there.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Ninth Circuit Holds That Policies Covering Environmental Claims Do Not Have Aggregate Limits
May 12, 2026 —
Lorelie S. Masters & Joseph T. Niczky - Hunton Insurance Recovery BlogIn the case of
County of San Bernardino v. Insurance Company of the State of Pennsylvania, the Ninth Circuit recently addressed the issue of whether general liability policies issued in the 1960s and 1970s included aggregate limits for claims arising under the premises-operations coverage in CGL policies. The difference between the policyholder’s interpretation of the policies’ limits clauses and the insurer’s interpretation was worth hundreds of millions of dollars in exposure for the insurer. The Court closely examined the policy language and extrinsic evidence from both the insurance industry’s drafting history and the parties before concluding that the policies were ambiguous. The Court construed that ambiguity in favor of the policyholder and ruled that aggregate limits did not apply to the claims at issue. The Court’s decision underscores the importance of carefully examining a policy’s limits, especially for older policies written before 1986 when the insurance industry revised the standard-form CGL policy to state the aggregate limits apply not only to products liability claims but to premises-operations claims as well. Decades of insurance industry drafting history confirms, as the policyholder’s submissions in this case indicate, that the industry well understood that operations claims like the environmental waste-disposal claims at issue here typically were not subject to aggregate limits.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth LLP and
Joseph T. Niczky, Hunton Andrews Kurth LLP
Ms. Masters may be contacted at lmasters@hunton.com
Mr. Niczky may be contacted at jniczky@hunton.com