2026 Top Business Risks for Construction and Engineering Companies
May 26, 2026 —
Darren Tasker - Construction ExecutiveThe 2026 Allianz Risk Barometer revealed some surprising findings for construction and engineering businesses. Now in its fifteenth year, this
annual business risk ranking by corporate insurer
Allianz Commercial incorporates the views of 3,338 global risk management professionals on the main perils on their radar for the year.
Survey respondents included construction and engineering risk experts who identified the threats keeping them up at night. Here is how they ranked the top industry risks for 2026:
Natural Catastrophes
Natural catastrophe risk retains the top spot, with 38% of construction and engineering respondents citing this risk as their leading concern for 2026. From the insurance perspective, economic and insured losses remained high, albeit lower than the 10-year average. The evolving nature of natural catastrophes continues to pose significant challenges to businesses and the (re)insurance industry. Insured losses from natural catastrophes are set to reach $107 billion for 2025, according to Swiss Re—the sixth year in a row they have exceeded $100 billion, while economic losses are well in excess of $200 billion.
Reprinted courtesy of
Darren Tasker, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Cal Unity Bar Names Angela Zanin as Statewide President
August 11, 2026 —
Lewis BrisboisThe California Unity Bar has named Los Angeles Partner Angela Zanin as its statewide president for the 2026-2027 term. This appointment follows Ms. Zanin's extensive involvement in the organization, including as the founding co-chair of the Los Angeles County Unity Bar in 2024 and as its chair for the 2024-2025 term. Ms. Zanin also has served as a member of the Executive Steering Committee of the California Unity Bar since 2025.
In her inaugural message as president, which the Cal Unity Bar published in its newsletter of July 2026, Ms. Zanin stated that she vowed to continue the organization’s “commitment to promoting equal opportunities and embracing diversity, equity, and inclusion in the State of California.” She also noted that as she assumed the role of president, she thought of “the famous words of Dr. Martin Luther King, Jr.: ‘The arc of the moral universe is long, but it bends toward justice.”’ Ms. Zanin closed her message by observing, “At a time when the rule of law faces challenges, our alliance stands strong, built on trust and confidence in each other.”
Read the full story...Reprinted courtesy of
Lewis Brisbois
Four Kahana Feld Attorneys Selected to 2027 Southern California Super Lawyers® and Rising Stars Lists
August 16, 2026 —
Kahana FeldIRVINE, CA – Aug. 3, 2026 – Kahana Feld is pleased to announce that partners
Jason Feld,
Amir Kahana, and
Sharon Oh-Kubisch were selected to the 2027 Southern California Super Lawyers list, and attorney
Hannah Ellenhorn Bloom was selected to the 2027 Southern California Super Lawyers Rising Stars list.
Jason Feld was recognized in the area of Construction Litigation. He is a founding partner of Kahana Feld and focuses his practice on the defense of homebuilders, contractors, developers, and real estate professionals primarily in construction defect, general liability, insurance defense, construction accident, and real estate matters. He also represents government entities handling construction, premises liability, general liability, and environmental claims. He serves as panel counsel for many prominent insurance carriers, as well as personal counsel to several national and regional homebuilders, developers, and general contractors.
Read the full story...Reprinted courtesy of
Kahana Feld
Insured’s Failure to Determine Depreciation When Presenting Claim for Replacement Cost Value
August 16, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Third Circuit affirmed the district court’s granting of summary judgment to the insurer when the insured submitted replacement cost value of the loss but did not include a determination of depreciation. Kimmel v. Massachusetts Bay Ins. Co., 2026 U.S. App. LEXIS 16569 (3d Cir. June 9, 2026).
A lightning strike downed a tree on the insured’s property, causing extensive damage to the home. The insured had a homeowner’s policy with Massachusetts Bay Insurance Company (MBIC). MBIC denied the claim, determining that much of the claimed damage already existed and that several policy exclusions otherwise barred coverage. The insured filed suit for breach of contract and bad faith.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Enacts First-in-the-Nation Statewide Data Center Moratorium
August 03, 2026 —
Joshua L. Sturtevant - SheppardAs of May 2026, nearly 12 gigawatts of data center load requests were in the New York Independent System Operator interconnection queue, with more than two-thirds of capacity requests entering the queue in 2025 alone. On July 14, 2026, in response to concerns over this rapid growth, Governor Kathy Hochul issued Executive Order No. 62 (the “Order”) imposing a temporary moratorium on data centers in New York State. Among the concerns cited in the Order are the cost burden on ratepayers associated with transmission upgrades required to accommodate large loads, potential environmental impacts, and large-scale water use.
The moratorium is intended to halt activities while the state government develops a comprehensive legal framework for data center development. While dozens of municipal and county-level moratoriums are in place throughout the U.S., and while the legislatures of several states, including Maine, have proposed moratoriums, the Order is the first statewide moratorium to be enacted nationally.
Read the full story...Reprinted courtesy of
Joshua L. Sturtevant, SheppardMr. Sturtevant may be contacted at
jsturtevant@sheppard.com
Research Illuminates Pollution Problem in Tijuana River Valley
June 29, 2026 —
Jeff Yoders - Engineering News-RecordThe Tijuana River watershed between southern California and northern Mexico has been the epicenter of an environmental and public health crisis for more than two decades. Since October 2023 alone, more than 31 billion gallons of raw sewage and polluted water have flowed into the U.S. and, eventually, the Pacific Ocean.
Read the full story...Reprinted courtesy of
Jeff Yoders, Engineering News-RecordMr. Yoders may be contacted at
yodersj@enr.com
Voluntary Dismissal of an Indemnity Claim Does Not Make the Subcontractor a “Prevailing Party,” Washington Court of Appeals Holds
September 21, 2026 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIn
King County v. Walsh Construction Company II, LLC, No. 86503-0-I (Wash. Ct. App. Aug. 4, 2025), an unpublished decision from Division I of the Washington Court of Appeals, the Court affirmed the denial of a subcontractor’s request for prevailing-party attorney fees under an indemnity clause after the general contractor voluntarily dismissed its indemnity claims. Because the indemnity claim was no longer live and no determination of fault had occurred, the Court held that the trial court did not err in denying the request. ACS represented Walsh, the general contractor, in securing the denial of the fee request at the trial court that the Court of Appeals affirmed.
A Pass-Through Indemnity Claim That Ended Before Fault Was Decided
The dispute arose out of a public works contract under which King County hired Walsh Construction Company II, LLC (“Walsh”) to construct and install a conveyance pipeline. After the pipeline broke, King County sued Walsh for breach of contract and warranty, expressly identifying both Walsh and its subcontractor, Mears Group Inc., (“Mears”) as responsible. Walsh tendered defense and indemnity to Mears under the subcontract.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at