Arizona Court Enters $323 Million Judgment Against ZOM Living Following Unanimous Jury Verdict
May 26, 2026 —
Gray Development GroupPHOENIX, May 19, 2026 /PRNewswire/ -- A Maricopa County court has entered a $323 million compensatory damages judgment in favor of Gray Development Group against ZOM Holding Inc., doing business as ZOM Living, following a 12-day trial, a unanimous jury verdict and post-trial proceedings related to a proposed business transaction.
The jury found ZOM liable on claims of breach of contract and breach of the implied covenant of good faith and fair dealing stemming from a proposed joint venture tied to a planned pipeline of luxury multifamily and commercial projects in Phoenix and Scottsdale.
The lawsuit centered on a 13-project, $1.4 billion development pipeline originated and planned by Gray Development Group over more than a decade. In 2019, Gray invited Florida-based ZOM to participate in a joint venture involving the completion of five projects, which would have marked ZOM's entry into the Arizona market.
According to court findings presented at trial, the companies entered into a mutual confidentiality and non-circumvention agreement before Gray shared extensive sensitive and proprietary information related to the projects, including planning, market analysis, costs, financial data, local business relationships and operational strategies developed by Gray over decades in Arizona.
Evidence presented during trial showed that over a 10-month period while under contract, ZOM made hundreds of requests for confidential project and market information before circumventing Gray and pursuing the projects independently, ultimately displacing Gray from projects it spent years planning and developing.
ZOM Living, headquartered in Orlando, develops multifamily and senior housing communities across the United States and operates regional offices in Boston, Dallas, Fort Lauderdale, Nashville, Phoenix, and Raleigh. ZOM is owned by Timeless Investments, the Amsterdam-based family office of Dutch businessman Hans van Veggel, which acquired the company in 1997.
About Gray Development Group
Gray Development Group was founded by architect Bruce Gray in 1991. The Phoenix-based company was the top-ranked multifamily developer in Arizona for more than a decade. The company designed and developed more than 15,000 apartment and condominium units throughout metropolitan Phoenix. Two Gray-designed developments — a Tempe midrise and a San Diego high-rise — received National Apartment Community of the Year awards.
Applying Jury Verdict Method in Quantifying Damages Due to Defective Specifications
March 31, 2026 —
David Adelstein - Florida Construction Legal UpdatesAn older case deals with three important considerations: (1) defective specifications; (2) whether the defective specifications were misleading or misrepresentative; and (3) applying the jury verdict method in quantifying damages.
In Metric Construction Co., Inc. v. U.S., 80 Fed. Cl. 178 (Fed. Cl. 2008), a contractor was contracted by the federal government to construct a warehouse. There were defects in the structural steel design specifications underlying the standing seam metal roof installed by the contractor and, as a result, the roof system leaked causing damage. The contractor incurred significant costs in repairing the damage, and pursued recovery of these costs against the government. The contractor claimed the structural steel design serving as the framework for the metal roof was defective and misleading and caused the leaks.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Motion for Summary Judgment Granted in Significant California Public Utilities Suit
May 12, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Partner Mike D’Andrea and Associates Ruth Rasiah and Kaylah Abdullah in the Los Angeles office for obtaining a complete dismissal of their clients in a significant claim involving California’s Public Utilities regulations.
After lengthy litigation, BWB&O’s Motion for Summary Judgment was granted against Claimant, Spectrum (Charter Communications), which resulted in a complete dismissal of the action against BWB&O’s clients. At issue was whether California’s Public Utilities Code shifted the common law duty to maintain certain utility equipment in residential areas within Southern California. After significant briefing, the Superior Court found that BWB&O correctly argued that the Public Utilities Code required utility companies, like Spectrum, to fully maintain utility equipment, and that private residents are not responsible for utility maintenance (even if the physical equipment is located on private property).
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Navigating the New Frontier of Federal-State Energy Regulation: What Energy Companies Need to Know
June 08, 2026 —
Ryan J. Regula - Snell & WilmerIntroduction
The jurisdictional boundary between the Federal Energy Regulatory Commission (FERC) and the states is being actively contested, from challenges to landmark transmission planning rules to disputes over emergency cost-allocation orders, in ways that carry significant legal, financial, and operational implications for energy companies. For utilities, independent power producers, and transmission developers, understanding these dynamics is now a strategic imperative.
The Jurisdictional Divide: A Bright Line That Isn’t
The Federal Power Act divides authority between FERC and the states: FERC exercises jurisdiction over interstate transmission and wholesale electricity sales, while states retain authority over generation facilities, retail rates, and decisions about resource mix. The D.C. Circuit has regularly been called upon to “referee the Federal Power Act’s jurisdictional line separating [FERC’s] jurisdiction over the federal wholesale market and States’ jurisdiction over facilities used in local distribution.”1
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
PSA: Be Sure to Document (Even When Time is Short)
April 14, 2026 —
Christopher G. Hill - Construction Law MusingsWritten
change orders are a big deal. Almost all construction contracts (at least
the well drafted ones) require written contracts. Written change orders are even important enough that Virginia law
requires these provisions in residential construction contracts.
Why are they so important? Because they are a “mini-contract” of sorts. They
set the expectations, price, time, and work to be performed; work that was not included in the original price or scope for the project. Without this in writing, there will be no record of what the parties agreed to do. Does this sound familiar? Sound like its own contract? It should.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Samuel Alhadeff Represents LGI Homes in Acquisition and Re-Entitlement of Maravilla Estates
July 06, 2026 —
Lewis BrisboisTemecula Partner Samuel Alhadeff recently represented LGI Homes in its acquisition and re-entitlement of Maravilla Estates, a 169-lot active adult community located in San Jacinto, California.
The acquisition and re-entitlement of the project provide LGI Homes with the opportunity to deliver much-needed age-qualified housing in one of Riverside County's growing residential markets. The community includes a recorded final map and finished lots, as well as future development inventory and planned amenities, positioning the project for continued development and completion.
Read the full story...Reprinted courtesy of
Lewis Brisbois
CEO: Power Isn’t the Only Electrical Challenge for AI Data Centers
April 14, 2026 —
Francesco "Frio" Iorio - Engineering News-RecordEveryone knows that data centers are voracious consumers of electricity. In fact, the U.S. is currently scrambling to meet unprecedented levels of power demand not seen since
the early days of electrification and the widespread adoption of air conditioning.
Read the full story...Reprinted courtesy of
Francesco "Frio" Iorio, Engineering News-RecordENR may be contacted at
enr@enr.com
Supreme Court Strikes Down IEEPA Tariffs: The Refund Process Will Be Messy
March 10, 2026 —
Brett W. Johnson, Derek Flint, T. Troy Galan & Thomas Williams - Snell & WilmerOn February 20, 2026, the U.S. Supreme Court held in Learning Resources, Inc. v. Trump, and the consolidated case Trump v. V.O.S. Selections, Inc., that the International Emergency Economic Powers Act (IEEPA) does not authorize the President to impose tariffs unilaterally.1 The decision invalidates both the “reciprocal” tariffs and the drug-trafficking tariffs imposed under IEEPA.
For importers, the immediate question is whether, how, and when refunds can actually be obtained. On that issue, the U.S. Supreme Court provided no roadmap. To the contrary, the dissent warned that the United States “may be required to refund billions of dollars,” that the process is likely to be a “mess,” and that the majority opinion “says nothing today about whether, and if so how, the Government should go about returning the billions of dollars that it has collected from importers.”
Reprinted courtesy of
Brett W. Johnson, Snell & Wilmer,
Derek Flint, Snell & Wilmer,
T. Troy Galan, Snell & Wilmer and
Thomas Williams, Snell & Wilmer
Mr. Johnson may be contacted at bwjohnson@swlaw.com
Mr. Flint may be contacted at dflint@swlaw.com
Mr. Galan may be contacted at tgalan@swlaw.com
Mr. Williams may be contacted at twilliams@swlaw.com>
Read the full story...