Prefatory Contract Language Cannot Be Used to Create an Ambiguity with Operative Provisions
May 12, 2026 —
David Adelstein - Florida Construction Legal UpdatesContract drafting and interpretation matters.
A case dealt with the potential conflict with prefatory language in an agreement compared with operative provisions in the agreement. The trial court held that the operative provisions control. I discussed this case
here where the appellate court reversed based on the prefatory language.
But, through a motion for rehearing, the appellate court reconsidered its position and affirmed the trial court based on the operative provisions, mainly that the prefatory language cannot be used to create an ambiguity with operative provisions. Consider this explanation in affirming the trial court:
Because the trial court correctly found that the initial language in the contract was prefatory and could not be used to create an ambiguity in the remainder of the contract, we affirm the final judgment.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
GRSM Team Obtains Defense Verdict for Homeowners’ Association in Orange County Superior Court
August 11, 2026 —
Gordon Rees Scully MansukhaniA Gordon Rees Scully Mansukhani multi-state team, including Partners Christine Barker, Sean Ferron, and Keith Cramer, obtained a defense verdict on behalf of a homeowners’ association (HOA) in an Orange County Superior Court bench trial spanning two months.
The case began in 2022 when a homeowner sued after the Architectural Review Committee and HOA Board of Directors declined his teardown-and-rebuild plans due to view and aesthetic concerns. After a motion for summary judgment ruling in which the court found that the existing covenants, conditions, and restrictions (CC&Rs) did not protect views, the HOA held a special election to add explicit view protections to the CC&Rs. At the February 2025 trial call, the plaintiff sought leave to file a third amended complaint challenging the validity of that vote, drastically reframing the case from CC&R enforcement to one of election validity. A second plaintiff then filed a parallel action toward the end of the limitations period, and the two cases were consolidated.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Colorado Supreme Court Reverses Course on Public Project Liens: Key Takeaways From Wadsworth v. Regional Rail Partners
July 27, 2026 —
Amanda E. McKinlay - Snell & WilmerOn April 6, 2026, the Colorado Supreme Court issued a unanimous opinion in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, 2026 CO 19, reversing the Colorado Court of Appeals and providing much-needed clarity regarding verified statements of claim (VSOCs) under the Colorado Public Works Act, C.R.S. §§ 38-26-101 et seq. The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
Under C.R.S. § 38-26-107(1), a subcontractor on a public works project may file a VSOC with the contracting public entity for amounts due and unpaid for “…furnished labor, materials, sustenance, or other supplies used or consumed by a contractor or his or her subcontractor in or about the performance of the work contracted to be done or that supplies laborers, rental machinery, tools, or equipment to the extent used in the prosecution of the work….” If a claimant files a VSOC for “an amount greater than the amount due” without a reasonable possibility that the amount is due and with knowledge that the claim is excessive, the claimant “shall forfeit all rights to the amount claimed” and becomes liable for the opposing party’s costs and attorneys’ fees. C.R.S. § 38-26-110.
Read the full story...Reprinted courtesy of
Amanda E. McKinlay, Snell & WilmerMs. McKinlay may be contacted at
amckinlay@swlaw.com
Presumption of Prejudice Applies to All Affirmative Defenses Regarding Insured’s Failure to Comply with Post-Loss Policy Conditions
June 23, 2026 —
David Adelstein - Florida Construction Legal Updatesn a recent property insurance coverage dispute, an issue on appeal pertained to the “prejudice” jury instruction associated with the insured’s failure to comply with post-loss policy conditions. The trial court found that the prejudice only pertained to prompt notice and not other post-loss policy conditions. This was reversed on appeal as prejudice applied to ALL the post loss policy conditions that the insured failed to comply with, not just the prompt notice requirement. The prejudice presumption applies to all affirmative defenses regarding an insured’s failure to comply with post-loss policy conditions.
Consider this discussion when dealing with an insurer raising prejudice as an affirmative defense to do an insured’s failure to comply with post-loss policy conditions, and the associated burdens of proof:
On appeal, [the insurer] contends the trial court erred by instructing the jury that the presumption of prejudice was inapplicable to all of its post-loss obligation defenses except prompt notice. We agree.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Pulling the Plug, Preserving the Product: Protecting Rights to a Modular Subcontractor’s Work Post-Termination
June 08, 2026 —
Paul Williamson - ConsensusDocsVolumetric Modular Construction (VMC) is a building method where a structure is divided into large components or modules, fabricated in an offsite factory and then transported to a construction site for assembly.[
1] Proponents of VMC hail it as a cost-efficient alternative to traditional building methods that leads to more consistent quality and shorter construction duration.[
2] Due to a growing labor shortage, high demand for compressed project schedules, and stagnant construction productivity rates, the construction industry is embracing VMC.[
3] A recent report on the market size of prefabricated construction estimates that from 2026 to 2031, VMC will grow at a compound annual growth rate of 7.16% and become a 413.11-billion-dollar industry.[
4]
As VMC becomes more prevalent, owners, general contractors, and subcontractors must consider how to effectively contract for modular construction. One important consideration, which this article focuses on, is navigating termination of a modular subcontractor.
Read the full story...Reprinted courtesy of
Paul Williamson, Peckar & Abramson, P.C.Mr. Williamson may be contacted at
pwilliamson@pecklaw.com
Data Center Construction: Contractors Must Step Up
May 26, 2026 —
Aarni Heiskanen - AEC BusinessI attended the
Datacenter Forum 2026 in Helsinki last week. Over 400 people packed the room. Walking out, I had one overriding thought: Is construction operating in a different century from the technology it is being asked to house?
Is Our Industry on Par?
Ciarán Forde, Senior Vice President at CTS Nordics, opened the forum with a statement that set the tone for everything that followed: data centers are no longer just a technical challenge; they are a national strategy. Before AI, Ciarán had worked in telecoms, where data centers were already complex. But now, he said flatly, everything has changed, and the industry must rethink everything.
The numbers behind the claim are staggering. Current AI data center racks run at 40 to 100 kW. In three years, 800 kW per rack is on the roadmap. And the development cycle for a new chip is roughly one year, which means deployments begin aging out almost as soon as they are commissioned.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Daily Journal Publishes Article by Brenda Radmacher on Proposed Overhaul of California Construction Defect Law
June 29, 2026 —
Brenda Radmacher - The Construction SeytDaily Journal (California) featured an article by Construction Law partner
Brenda Radmacher, “A new path for construction defects in California.” The piece, published on June 15, 2026, examines Assembly Bill 1903 and its potential to significantly reshape California’s construction defect framework, particularly for common interest properties.
The article highlights how AB 1903 would overhaul the state’s current right-to-repair system by mandating completion of prelitigation procedures, raising requirements for defect claims, strengthening developers’/builders’ rights to repair, and introducing a voluntary “certified building” program. The legislation aims to rebalance competing interests by reducing litigation-driven costs while preserving protections for homeowners.
Read the full story...Reprinted courtesy of
Brenda Radmacher, Seyfarth Shaw LLPMs. Radmacher may be contacted at
bradmacher@seyfarth.com
Chambers USA Recognizes Hunton’s Insurance Coverage Practice in 2026 Guide
June 29, 2026 —
Hunton Insurance Recovery BlogHunton is pleased to announce that its insurance coverage practice was recognized nationally for Insurance: Dispute Resolution – Policyholder in the recently released 2026 Chambers USA guide. The team also received state rankings in Florida (Insurance: Dispute Resolution), Georgia (Insurance), the District of Columbia (Insurance: Policyholder), and Massachusetts (Insurance).
In addition to the insurance team’s group recognition across multiple states, the 2026 guide included individual rankings for
Lorelie “Lorie” S. Masters (USA Nationwide and District of Columbia),
Latosha M. Ellis (District of Columbia),
Michael S. Levine (District of Columbia),
Koorosh “KT” Talieh (District of Columbia),
Walter J. Andrews (Florida),
Andrea DeField (Florida),
Cary D. Steklof (Florida),
Lawrence J. Bracken II (Georgia), and
Geoffrey B. Fehling (Massachusetts).
Read the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP