Integration Can Inoculate in Utah
July 20, 2026 —
Mark O. Morris - Snell & WilmerThe Utah Court of Appeals recently reaffirmed, in the construction context, Utah’s strict approach to enforcing integration clauses to preclude parol evidence and other legal theories that would vary the written terms of a contract. In Reid v. All Surface LC, 2025 UT App 134, decided last September, the court affirmed in all respects the trial court’s grant of summary judgment based on the strength of an integration clause against a homeowner who sued a contractor for breach of contract, breach of the covenant of good faith and fair dealing, fraud, negligent misrepresentation, civil conspiracy, negligence, and breach of the implied warranty of habitability. More recently, however, the same court rejected those same arguments in Tidwell v. Jensen, 2026 UT App 13 as to tort claims arising from a used car sale.
The facts in Reid were sympathetic to the plaintiff. After being told she had a mold issue near a defective basement shower, the plaintiff solicited bids. A remediation contractor advised that while it could address the mold, the shower replacement should be handled by someone else. The plaintiff contacted All Surface LC, a shower replacement contractor. During an interview, the sales representative stated that All Surface could “do full mold remediation, tear everything out, and reframe the shower.” The plaintiff ultimately retained All Surface, expecting it would both resolve the mold issues and replace the shower.
Read the full story...Reprinted courtesy of
Mark O. Morris, Snell & WilmerMr. Morris may be contacted at
mmorris@swlaw.com
Achieving Sustainability Through Design Build Delivery: Part II – A Framework for Managing Sustainability Objectives on Private Commercial Construction
October 06, 2026 —
Jennifer Harris, Tiffany Harrod & Joshua Pruett - ConsensusDocsPart I of this series traced the history and development of sustainability in construction and explained why design-build (“DB”) contracting is particularly well suited to achieve sustainability objectives. But selecting DB contracting does not by itself ensure a sustainable outcome. The parties must define their sustainability objectives with precision, establish measurable performance criteria and identify who will measure compliance with the criteria, and also draft contract terms that clearly and fairly allocate the associated responsibilities and risks. Otherwise, the completed project may fall short of its sustainability objectives and expose the parties to claims, disputes, and litigation. Part II offers a non-exhaustive list of practical guidance for addressing these issues and reducing those risks.
This article references the ConsensusDocs 310 Green Building Addendum, in conjunction with an agreement between the Owner and the Design-Builder (e.g., ConsensusDocs 415)
[1],
[2] and AIA Document E204–2017 Sustainable Projects Exhibit,
[3] together with AIA A141,
[4] as its contractual baseline. The five-part framework that follows is a roadmap for allocating sustainability risk between private owners and design-builders: define the requirements, identify hidden performance guarantees, map out the sustainable objective, address third-party certification risk, and track performance against agreed benchmarks.
Reprinted courtesy of
Jennifer Harris, Peckar & Abramson, P.C.,
Tiffany Harrod, Peckar & Abramson, P.C. and
Joshua Pruett, Peckar & Abramson, P.C.
Ms. Harris may be contacted at jharris@pecklaw.com
Ms. Harrod may be contacted at tharrod@pecklaw.com
Mr. Pruett may be contacted at jpruett@pecklaw.com
Read the full story...
WSHB Managing Partner Chad Dunigan Named Finalist for Jerrold S. Oliver "Ollie" Award of Excellence
May 12, 2026 —
Wood Smith Henning BermanChad Dunigan, Managing Partner of Wood Smith Henning & Berman's Orlando, Florida, office, has been selected as one of just four finalists for the prestigious Jerrold S. Oliver Award of Excellence, affectionately known in the construction defect community as the "Ollie" Award. This distinguished honor recognizes individuals who have made exceptional contributions and demonstrated unwavering dedication to advancing the field of construction defect law.
Named in honor of the late Judge Jerrold S. Oliver, a revered founder of alternative dispute resolution in construction defect claims and litigation, the Ollie award symbolizes loyalty, commitment, and trust within the industry. Judge Oliver's legacy as a staunch believer in the resolution process continues to inspire professionals who strive for excellence in the construction defect community.
Read the full story...Reprinted courtesy of
Wood Smith Henning Berman
Two Snell & Wilmer Attorneys Selected as 2026 San Diego Super Lawyers Rising Stars
May 14, 2026 —
Snell & WilmerSAN DIEGO – Snell & Wilmer is pleased to announce that two attorneys in the San Diego office have been selected for inclusion in the
2026 San Diego Super Lawyers Rising Stars publication.
Rising Stars is a listing of lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. To be eligible for inclusion, a candidate must be either 40 years old or younger or in practice for 10 years or less. The selection process is multi-phased and includes independent research and peer nominations, with no more than 2.5 percent of the lawyers in the state named to the Rising Stars list.
Read the full story...Reprinted courtesy of
Snell & Wilmer
A Green Light for Housing? What Executive Order 14394 Means for Your Next Project
May 26, 2026 —
Bennett Houck, Miranda Martinez & Byron Sarhangian - Snell & WilmerOn March 13, 2026, President Trump signed Executive Order 14394, “Removing Regulatory Barriers to Affordable Home Construction” (the “Order”). The Order directs federal agencies to reduce regulatory burdens on residential development, streamline environmental permitting, and encourage state and local governments to adopt housing-friendly policies.
The Order includes several key provisions that developers and homebuilders should be aware of moving forward.
Key Provisions
The Order targets four main areas:
1. Federal Environmental Regulations
First, it directs the Secretary of the Army and Environmental Protection Agency (EPA) to revise permitting standards, including stormwater permits, wetlands permits under Section 404 of the Clean Water Act, and related construction-site requirements. The Order also targets energy-efficiency mandates for U.S. Department of Housing and Urban Development (HUD) and U.S. Department of Agriculture (USDA) financed housing. For developers and homebuilders, these revisions could reduce project delays and compliance costs associated with stormwater management, wetlands mitigation, and energy-efficiency upgrades, expenses that often add significant time and cost to residential development projects.
Reprinted courtesy of
Bennett Houck, Snell & Wilmer,
Miranda Martinez, Snell & Wilmer and
Byron Sarhangian, Snell & Wilmer
Mr. Houck may be contacted at bhouck@swlaw.com
Ms. Martinez may be contacted at mimartinez@swlaw.com
Mr. Sarhangian may be contacted at bsarhangian@swlaw.com
Read the full story...
Conditional Payment Bond Consideration-Make Sure There Is Pay-If-Paid Provision
June 29, 2026 —
David Adelstein - Florida Construction Legal UpdatesIf a general contractor is going to have a conditional payment bond, it needs to ensure it subcontracts contain pay-if-paid or pay-when-paid provisions. This conditional payment language in subcontracts is the general contractor’s defense that it doesn’t have to pay a subcontractor UNTIL owner has paid the general contractor for the subcontractor’s work.
The general contractor (and the surety) can look at the conditional payment bond with the s. 713.245 legend stamped on its face designating the conditional nature of the bond, and assume the conditional structure is locked in against the bond: no payment from the owner, no obligation to the subcontractors under the bond. But what happens when the subcontracts contain no express conditional payment language despite having a valid conditional payment bond?
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Beyond the Forecast: Managing Extreme Weather Risks on Construction Sites
November 02, 2026 —
Jordan Graustark - Construction ExecutiveConstruction leaders would never downplay or dismiss a fall, struck-by incident or equipment failure as “just part of the job.” Yet, some temperature-related conditions, such as heat exhaustion, frostbite and hypothermia, are often accepted as unavoidable consequences of working conditions. Temperature-related incidents likely won’t command the same attention as a crane collapse, but understating their seriousness can be a costly mistake. As extreme weather becomes more frequent and unpredictable, that mindset is becoming increasingly difficult to defend.
Extreme weather is not simply a seasonal inconvenience; it’s a serious occupational hazard. Heat waves, cold snaps and rapid temperature swings can contribute to serious injuries and fatalities—or SIFs—productivity losses and costly project disruptions. A single temperature-related incident can quickly become an OSHA recordable and project management challenge. Reduced physical and impaired cognitive performance from heat or cold stress can increase the risk of workplace incidents long before a medical emergency occurs.
Reprinted courtesy of
Jordan Graustark, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Nevada’s Mandatory Nonbinding Arbitration Law for Civil Cases is Going Through Changes
May 14, 2026 —
Brandon Wright & Manuel Gurule - Lewis BrisboisNevada currently operates an expedited litigation program designed to resolve civil disputes with a value up to $50,000 without incurring the “usual” expense of litigating these disputes. Over time, however, the number of civil cases that have been “exempted” from this program based on the claimed damages exceeding $50,000 has grown dramatically. In response, the Nevada Legislature recently enacted a number of rule changes designed to streamline Nevada’s arbitration process and include more cases. Among these changes are increasing the arbitration “cap” from $50,000 to $100,000.
By way of background, the Nevada’s Court Annexed Arbitration program is a mandatory, non-binding program for civil cases in judicial districts that have county populations of 100,000 or more [1]. Nevada’s Court Annexed Arbitration was born out of NRS 38.250, which was enacted in 1991 and went into effect in the summer of 1992. The newly enacted NRS 38.250 was regarded as a way to address the problem of increased court caseloads while promoting judicial economy and efficiency in civil cases having a probable jury award of less than $25,000 [2]. Initially, cases that were automatically exempt from the program included class actions, medical malpractice disputes, divorce proceedings, and other domestic relations matters [3].
Reprinted courtesy of
Brandon Wright, Lewis Brisbois and
Manuel Gurule, Lewis Brisbois
Mr. Wright may be contacted at Brandon.Wright@lewisbrisbois.com
Mr. Gurule may be contacted at Manuel.Gurule@lewisbrisbois.com
Read the full story...