Two Important Points Regarding the Miller Act
September 15, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller Act case, U.S. f/u/b/o Boundless Management Outsourcing Group, LLC v. Endurance Assurance Corp, 2026 WL 2241491 (D. Puerto Rico 2026), confirms two important points when it comes to the Miller Act. In this case, a subcontractor pursued a Miller Act payment bond lawsuit more than one year after its work was finished. The subcontractor also asserted a claim against the federal government. The lawsuit was dismissed. Below are two takeaway points to consider if you are dealing with a Miller Act payment bond lawsuit.
First, as it relates the claim against the federal government, the federal district court followed authority that held that the Miller Act does NOT include a waiver of sovereign immunity against the federal government. “[T]he Court does not identify any clear language in the Miller Act expressly waiving the United States or its agencies’ sovereign immunity.” Endurance Assurance Corp., supra at *3.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Not Every Job Is Worth Winning: Contract Risk Questions Contractors Should Ask Before They Bid
September 29, 2026 —
Jack Mayo - ConsensusDocsIntroduction
Winning the work is not the same as winning the project, at least financially. Consider a contractor that commits to procure custom or long-lead materials before receiving complete construction documents. Depending on the language of the contract, if the final design is altered after those materials have been ordered, the contractor may be left responsible for replacement costs, procurement delays, or both. Alternatively, a subcontractor that accepts a pay-if-paid provision without investigating the owner’s financing, or prematurely waives lien rights, potentially risks nonpayment for properly performed work.
Such concessions can quickly transform an apparently profitable project into a significant financial burden. A successful bid can therefore become an unsuccessful project if the contractor accepts contractual “red flags” without evaluating their consequences and the long-term financial impacts that they may have. The significance of each risk will depend on the project, the parties, the proposed contract, applicable law, and the contractor’s business objectives. Although not comprehensive, this article identifies several key considerations for that process to help mitigate certain risks.
Read the full story...Reprinted courtesy of
Jack Mayo, Jones Walker LLPMr. Mayo may be contacted at
jmayo@joneswalker.com
The ROI of Estimating Accuracy in Preconstruction
September 15, 2026 —
Aaron Kivett - Construction ExecutivePrecision is the foundation of profitability in construction. Even minor quantity or pricing mistakes can swing bids anywhere from 5-15%, leading to project delays, unprofitable jobs or margin erosion through change orders. And worse, these losses can damage client trust and jeopardize long-term relationships that drive repeat business and future bids. Consistently
estimating accurately builds confidence, speeds up bidding and positions your company to win more profitable projects.
Estimating accuracy is where profit is either protected or lost. In construction, you make your biggest financial decisions before a project ever starts. Once a bid is won, most of the project’s cost structure is locked in. If the estimate is wrong, no amount of execution can fully fix those mistakes. That makes estimating accuracy a business issue, not just an operations issue.
Reprinted courtesy of
Aaron Kivett, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Cal Unity Bar Names Angela Zanin as Statewide President
August 11, 2026 —
Lewis BrisboisThe California Unity Bar has named Los Angeles Partner Angela Zanin as its statewide president for the 2026-2027 term. This appointment follows Ms. Zanin's extensive involvement in the organization, including as the founding co-chair of the Los Angeles County Unity Bar in 2024 and as its chair for the 2024-2025 term. Ms. Zanin also has served as a member of the Executive Steering Committee of the California Unity Bar since 2025.
In her inaugural message as president, which the Cal Unity Bar published in its newsletter of July 2026, Ms. Zanin stated that she vowed to continue the organization’s “commitment to promoting equal opportunities and embracing diversity, equity, and inclusion in the State of California.” She also noted that as she assumed the role of president, she thought of “the famous words of Dr. Martin Luther King, Jr.: ‘The arc of the moral universe is long, but it bends toward justice.”’ Ms. Zanin closed her message by observing, “At a time when the rule of law faces challenges, our alliance stands strong, built on trust and confidence in each other.”
Read the full story...Reprinted courtesy of
Lewis Brisbois
U.S. Supreme Court Decision May Negate State Law Requirement to File a Certificate of Merit with the Complaint in a Federal Action Against a Design Professional
April 27, 2026 —
Christopher Olsen & Phillip Boldt - ConsensusDocsTo deter frivolous and unfounded claims against design professionals, states throughout the country have enacted statutes which generally require litigants to furnish a formal certification of merit (“COM”) from a qualified expert or face potential dismissal of their lawsuit. These COM statutes can impose a significant front-end burden on claimants who must pay an expert to review project records, interview the project team, and prepare a formal report before the lawsuit can be filed—often regardless of the amount in controversy. However, in light of a recent U.S. Supreme Court decision in a medical malpractice case, most, if not all of these statutes, may no longer be enforceable in federal court. This article examines the recent decision in Berk v. Choy, 146 S. Ct. 546 (2026), the decisions thus far which have applied Berk to invalidate COM statutes, and other categories of statutes applicable to the construction industry which may face a similar fate.
The U.S. Supreme Court Decision (Berk v. Choy)
In Berk, the plaintiff, Harold Berk, sued a doctor for medical malpractice under Delaware law in Delaware federal court. 146 S. Ct. at 551. Under Del. Code, Tit. 18, § 6853(a)(1), an affidavit of merit (like a COM) must accompany a complaint alleging medical malpractice. Id. Berk failed to include an affidavit of merit with his complaint. Id. at 552. Applying Delaware state law, the federal court dismissed Berk’s medical malpractice claim. Berk appealed to the Third Circuit, arguing that the affidavit of merit required by § 6853(a)(1) is unenforceable in federal court because it is more onerous than the Federal Rules of Civil Procedure. The Third Circuit affirmed the District Court’s ruling, finding § 6853(a)(1) enforceable in federal court.
Reprinted courtesy of
Christopher Olsen, Peckar & Abramson, P.C. and
Phillip Boldt, Peckar & Abramson, P.C.
Mr. Olsen may be contacted at colsen@pecklaw.com
Mr. Boldt may be contacted at pboldt@pecklaw.com
Read the full story...
Voluntary Dismissal of an Indemnity Claim Does Not Make the Subcontractor a “Prevailing Party,” Washington Court of Appeals Holds
September 21, 2026 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIn
King County v. Walsh Construction Company II, LLC, No. 86503-0-I (Wash. Ct. App. Aug. 4, 2025), an unpublished decision from Division I of the Washington Court of Appeals, the Court affirmed the denial of a subcontractor’s request for prevailing-party attorney fees under an indemnity clause after the general contractor voluntarily dismissed its indemnity claims. Because the indemnity claim was no longer live and no determination of fault had occurred, the Court held that the trial court did not err in denying the request. ACS represented Walsh, the general contractor, in securing the denial of the fee request at the trial court that the Court of Appeals affirmed.
A Pass-Through Indemnity Claim That Ended Before Fault Was Decided
The dispute arose out of a public works contract under which King County hired Walsh Construction Company II, LLC (“Walsh”) to construct and install a conveyance pipeline. After the pipeline broke, King County sued Walsh for breach of contract and warranty, expressly identifying both Walsh and its subcontractor, Mears Group Inc., (“Mears”) as responsible. Walsh tendered defense and indemnity to Mears under the subcontract.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Steel Cooling: Steel Costs Steadily Decline After Pandemic Price Shock
May 12, 2026 —
Construction ExecutiveSteel prices have continued trending downward after several years of volatility, according to Gordian’s latest analysis based on RSMeans Data. After dramatic spikes during the pandemic-era supply disruptions, the market has gradually stabilized as supply chains improve and demand softens in some construction segments. However, selective volatility and tariff uncertainty continue to influence pricing across the sector.
Key findings from the report include:
- Steel prices declining: The national average price of structural steel fell to about $2,343.93 per ton in January 2026, down 5.38% from the previous quarter and 7.18% year over year.
- Longer-term price correction: Steel costs have been trending downward since 2024 after earlier volatility driven by inflation, supply shortages and global demand swings.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
4th Department Narrowly Interprets Professional Services
August 11, 2026 —
Craig Rokuson - Traub LiebermanIn the recent case of Cty. of Erie v. Selective Ins. Co. of Am., 2026 NY Slip Op 04092 (App. Div. 4th Dept.), New York’s Appellate Division, Fourth Department held that a general liability carrier for a construction manager owed additional insured coverage to the County of Erie, notwithstanding an exclusion in the construction manager’s policy for injuries arising out of professional services.
The underlying case involved injuries sustained when the underlying plaintiff fell off of her bicycle at a park owned by the County when she transitioned from the pavement edge to grass.
Read the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com