Cal Unity Bar Names Angela Zanin as Statewide President
August 11, 2026 —
Lewis BrisboisThe California Unity Bar has named Los Angeles Partner Angela Zanin as its statewide president for the 2026-2027 term. This appointment follows Ms. Zanin's extensive involvement in the organization, including as the founding co-chair of the Los Angeles County Unity Bar in 2024 and as its chair for the 2024-2025 term. Ms. Zanin also has served as a member of the Executive Steering Committee of the California Unity Bar since 2025.
In her inaugural message as president, which the Cal Unity Bar published in its newsletter of July 2026, Ms. Zanin stated that she vowed to continue the organization’s “commitment to promoting equal opportunities and embracing diversity, equity, and inclusion in the State of California.” She also noted that as she assumed the role of president, she thought of “the famous words of Dr. Martin Luther King, Jr.: ‘The arc of the moral universe is long, but it bends toward justice.”’ Ms. Zanin closed her message by observing, “At a time when the rule of law faces challenges, our alliance stands strong, built on trust and confidence in each other.”
Read the full story...Reprinted courtesy of
Lewis Brisbois
Jurisdiction Over Foreign Manufacturers in Construction Litigation
May 14, 2026 —
Timothy J. Repass & Miki J. Saito - Wood Smith Henning BermanA recent decision from the Washington Court of Appeals provides important guidance on personal jurisdiction over foreign product manufacturers in construction and infrastructure litigation. In King County v. Aquatherm GmbH, No. 85572-7-I (Wash.Ct. App.Div.I)(unpublished), the court addressed whether a German manufacturer could be sued in Washington for alleged defects in piping used in major public infrastructure projects. The ruling offers a detailed, fact-driven roadmap for how Washington courts evaluate jurisdiction over foreign manufacturers operating through layered distribution networks. It also reflects a broader trend toward focusing on real-world commercial conduct rather than formal corporate structure.
Background of the Case
King County sued after widespread failures in polypropylene piping installed at the King County Correctional Facility. The pipe, manufactured by Aquatherm GmbH in Germany, was marketed, distributed, and installed through a network of U.S.-based entities. Following a six-week trial, the jury returned a verdict exceeding $18 million on claims under the Washington Product Liability Act and Consumer Protection Act. Aquatherm challenged, among other things, the trial court's exercise of personal jurisdiction.
Reprinted courtesy of
Timothy J. Repass, Wood Smith Henning Berman and
Miki J. Saito, Wood Smith Henning Berman
Mr. Repass may be contacted at trepass@wshblaw.com
Ms. Saito may be contacted at msaito@wshblaw.com
Read the full story...
New York Enacts First-in-the-Nation Statewide Data Center Moratorium
August 03, 2026 —
Joshua L. Sturtevant - SheppardAs of May 2026, nearly 12 gigawatts of data center load requests were in the New York Independent System Operator interconnection queue, with more than two-thirds of capacity requests entering the queue in 2025 alone. On July 14, 2026, in response to concerns over this rapid growth, Governor Kathy Hochul issued Executive Order No. 62 (the “Order”) imposing a temporary moratorium on data centers in New York State. Among the concerns cited in the Order are the cost burden on ratepayers associated with transmission upgrades required to accommodate large loads, potential environmental impacts, and large-scale water use.
The moratorium is intended to halt activities while the state government develops a comprehensive legal framework for data center development. While dozens of municipal and county-level moratoriums are in place throughout the U.S., and while the legislatures of several states, including Maine, have proposed moratoriums, the Order is the first statewide moratorium to be enacted nationally.
Read the full story...Reprinted courtesy of
Joshua L. Sturtevant, SheppardMr. Sturtevant may be contacted at
jsturtevant@sheppard.com
Federal Court Strikes Down New York’s Climate Superfund Act: What It Means for the “Polluter Pays” Movement
September 28, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogA federal judge in the Northern District of New York has struck down New York’s
Climate Change Superfund Act, ruling that the “polluter pays” climate law is preempted by federal law and “simply beyond the limits of state law.” The court concluded that the Clean Air Act (CAA) does not authorize New York’s compensation scheme, which calculates liability based on greenhouse gas (GHG) emissions attributable to worldwide fossil fuel extraction and refining. It separately held that any cost-recovery demand against a foreign producer would be preempted under the constitutional foreign affairs doctrine, which limits state intrusion into matters committed predominantly to the federal government. The court directed the parties to file a status report by September 14, leaving the form of further relief unresolved. In practical terms, the court has decided that the Act is preempted and cannot be enforced but has not yet determined the precise terms of its final order, including whether to formally enjoin its enforcement.
The
decision in West Virginia v. James, Case No. 1:25-cv-00168 (N.D.N.Y. Aug. 31, 2026), issued by Chief U.S. District Judge Brenda K. Sannes, who was appointed by President Obama, marks the first judicial invalidation of a state climate superfund statute and carries significant implications for the
climate superfund landscape and the three remaining
lawsuits challenging these laws.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
Suit Limitation Provision Eliminates Wind Loss Claim
July 27, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer’s motion for judgment on the pleadings was granted after the insured failed to file suit against the insurer within the policy’s two-year suit limitation provision. Interstate Investments, LLC v. Mt. Hawley Ins Co., 2026 U.S. Dist. LEXIS 98108 (S.D. N. Y. May 4, 2026).
On or before June 27, 2023, a wind, hail and rainstorm damaged Interstate’s property in Oklahoma. Interstate filed a claim under its policy with Mt. Hawley. The policy provided that New York law applied and contained a two- year suit limitation provision.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ayushi Neogi Published in ADC Defense Comment on Arbitration in Evolving Plaintiff-Friendly Landscape
May 12, 2026 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani Senior Counsel Ayushi Neogi has authored an article in the Association of Defense Counsel of Northern California and Nevada’s Defense Comment magazine examining the shifting landscape of arbitration following the Ending Forced Arbitration Act.
Titled “Compelling Arbitration in a Post-Ending Forced Arbitration Act, Plaintiff-Friendly Landscape,” the article analyzes how recent legislative changes are reshaping arbitration strategy, particularly as employees gain greater ability to bypass arbitration in certain claims. Neogi provides practical insight into how courts are responding and what this means for defense counsel navigating increasingly complex and plaintiff-friendly environments.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Surety Requiring Collateral Security Under General Agreement of Indemnity
September 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn order to procure bonds (payment and performance bonds), you need to sign a General Agreement of Indemnity (referred to as the “GAI”) with the surety (bonding company). It does not matter the surety issuing the bonds, the terms and conditions in the General Agreement of Indemnity are largely consistent. These terms and conditions are one-sided written in favor of the surety. This is because bonds are not insurance. When a surety issues such bonds, it is doing so under the premise that it will get reimbursed every penny that it incurs relative to its exposure- whether incurred in attorney’s fees, consulting costs, or remediating a default or claim under the applicable bond. The General Agreement of Indemnity is one of the most powerful contracts in construction and is a contract that is not to be taken lightly. It provides the surety numerous rights in the event of a claim.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Are “Financial Hardship” Damages Recoverable?
June 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn a case out of the Civilian Board of Contract Appeals, F.O.G., LLC v. Department of the Interior, CBCA 8203, 2026 WL 1191881 (CBCA 2026) a contractor claimed damages that included “financial hardship” damages due to slow payments. The financial hardship damages included personal damages to the contractor’s president and his wife. Are these damages recoverable? Drumroll…The Board ruled that the contractor cannot recover such financial hardship damages.
As it relates the personal financial hardship damages, the Board ruled, “Neither [the contractor’s] president nor his wife are a party to this contract, are in privity of contract with [the government], or are the beneficiaries under this contract. [The contractor], therefore, cannot recover for any losses that either one has suffered individually and that [the contractor] claimed in this appeal.” F.O.G., LLC, supra.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com