Miller Act Payment Bond Claim “No Nos!”
October 06, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent federal district court opinion, Sauer Construction, LLC v. United Structures of Georgia, LLC, 2026 WL 2522849 (M.D.Fla. 2026), addressed two worthy considerations when it comes to a Miller Act payment bond claim. And, when I am talking about considerations, I am really talking about “no-nos.” These are things you don’t do.
First, don’t file an untimely Miller Act payment bond lawsuit. Make sure, as a claimant, you file that lawsuit within one year from your final furnishing. In this case, the subcontractor claimant did not and tried to argue around the statute of limitations with an equitable tolling argument, i.e., that the statute of limitations should be equitably tolled to accommodate the late filing of the lawsuit. Guess what? The subcontractor was not successful. You are fighting an uphill (losing) battle when arguing equitable tolling because “traditional equitable tolling principles require that the claimant demonstrate extraordinary circumstances, such as fraud, misinformation, or deliberate concealment.” Sauer Construction, supra. This means you need ultra-persuasive evidence to support such equitable tolling principles. Actually, having this evidence is doubtful. Thus, timely file the Miller Act payment bond lawsuit. There is no legitimate reason not to.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Greg Katz Quoted in Insurance Journal Article About How Big Data & AI Are Driving Up Verdicts, Settlements
October 06, 2026 —
Lewis BrisboisNational Managing Partner Greg Katz was recently quoted in an Insurance Journal article about how plaintiff's lawyers are harnessing big data and artificial intelligence to attempt to drive up jury awards and settlement demands.
The article, titled "The Big Data/AI ‘Revolution’ Is Driving Up Verdicts, Settlements as Plaintiffs Buy In," points out that a growing number of personal injury and claims law firms, some of which are working with an influx of cash from investors and litigation funders, are using a multitude of high-tech tools to try to gain an advantage in litigation. They are using large online mock juries to test legal theories, big data to find sympathetic jurors and venues in which to try cases, and AI programs to analyze their own arguments and those of opponents.
“They’re taking instincts and intuition out of the equation,” Mr. Katz told Insurance Journal. “They think they’ve come up with a different way to ring the bell and, in their words, add zeroes to awards.”
Read the full story...Reprinted courtesy of
Lewis Brisbois
In the Eye of the Beholder: Court of Appeal Finds Duty of Care Owed by Owner and Contractors for Death of Minors Caused by Independent Truck Driver
May 05, 2026 —
Garret D. Murai - California Construction Law BlogI was a T.A. for my high school history teacher, a really smart and nice guy, Mr. Reynolds. In the room at the back of the classroom which served as his office he had
the picture above. It’s called “My Wife and My Mother-in-Law” and is taken from a German postcard from 1888. Depending on how you look it, you might see fashionable young lady, or an old lady.
Cases can sometimes be like that: You see what you want to see. The next case is also like that.
In
Lorenzo v. Calex Engineering, Inc., 110 Cal.App.5th 49 (2025), the 2nd District Court of Appeals reversed a motion for summary judgment granted in favor of an owner and its contractors in a case involving the death of two minors struck by a dump truck enroute to a non-permitted off-site staging area.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Not Every Job Is Worth Winning: Contract Risk Questions Contractors Should Ask Before They Bid
September 29, 2026 —
Jack Mayo - ConsensusDocsIntroduction
Winning the work is not the same as winning the project, at least financially. Consider a contractor that commits to procure custom or long-lead materials before receiving complete construction documents. Depending on the language of the contract, if the final design is altered after those materials have been ordered, the contractor may be left responsible for replacement costs, procurement delays, or both. Alternatively, a subcontractor that accepts a pay-if-paid provision without investigating the owner’s financing, or prematurely waives lien rights, potentially risks nonpayment for properly performed work.
Such concessions can quickly transform an apparently profitable project into a significant financial burden. A successful bid can therefore become an unsuccessful project if the contractor accepts contractual “red flags” without evaluating their consequences and the long-term financial impacts that they may have. The significance of each risk will depend on the project, the parties, the proposed contract, applicable law, and the contractor’s business objectives. Although not comprehensive, this article identifies several key considerations for that process to help mitigate certain risks.
Read the full story...Reprinted courtesy of
Jack Mayo, Jones Walker LLPMr. Mayo may be contacted at
jmayo@joneswalker.com
Location, Location, Location — But Which One? The Few Words in Your Construction Contract that Pick Where You Fight
June 29, 2026 —
Brad Sands - ConsensusDocsMost professionals know the old real estate line: location, location, location. It turns out to be just as true for construction contracts as it is for property.
Consider a recent case involving a project owner that hired two design firms for a project. When issues arose during construction, the owner sued the design firms in state court in Brazoria County, Texas, pursuant to the forum selection clause in the parties’ contracts. The defendants then removed the case to the federal district court in Galveston, a courthouse in a different county. But the owner wanted the case back in Brazoria County state court. Whether it got its wish came down to two words in the contract: “situated in.” This article is about words like those.
A construction contract’s forum selection clause names the place for the fight nobody plans to have, and where that fight happens can shape how it goes. This article explains why the wording in your forum selection clause deserves careful reading before you sign a construction contract. It is not a deep dive into the mechanics of federal removal jurisdiction, and it is not an academic comparison of the terms “forum” and “venue.” Instead, it is a practical look at how courts actually read these clauses, so the location of a future fight is the one you intended.
Read the full story...Reprinted courtesy of
Brad Sands, Jones Walker, LLPMr. Sands may be contacted at
bsands@joneswalker.com
White and Williams LLP Secures $42.4 Million Award for Ventana DBS LLC in Philadelphia Marriott Construction Litigation
July 27, 2026 —
Craig O'Neill, Lindsay Liebman, Kristen Nichols Wright, Zachary Roth & William Taylor - White and WilliamsWhite and Williams LLP's Construction and Surety Practice attorneys secured a significant victory for client Ventana DBS LLC in a complex commercial construction dispute before the Philadelphia Court of Common Pleas, Commerce Division. The trial team, led by Bill Taylor, retired Partner, and Craig O'Neill, Co-Chair of the Construction and Surety Practice Group, with support from Lindsay Liebman, Counsel, Zachary Roth, Partner, Kristen Nichols Wright, Associate, and Sue Ferrante, Legal Secretary, obtained a $42.4 million award on Ventana's claims for unpaid work, delay costs, CASPA penalties and interest, attorneys’ fees and other project-related costs arising from the construction of the Marriott W/Element Hotel Project in Philadelphia.
To achieve this result, the White and Williams team managed an extensive discovery period over the course of four-years of litigation, conducted over sixty depositions, participated in court-ordered mediation and arbitration proceedings, and successfully represented Ventana during a bifurcated trial that spanned over the course of a year.
Reprinted courtesy of
Craig O'Neill, White and Williams,
Lindsay Liebman, White and Williams,
Kristen Nichols Wright, White and Williams,
Zachary Roth, White and Williams and
William Taylor, White and Williams
Mr. O'Neill may be contacted at oneillc@whiteandwilliams.com
Ms. Liebman may be contacted at liebmanl@whiteandwilliams.com
Ms. Wright may be contacted at wrightk@whiteandwilliams.com
Mr. Roth may be contacted at rothz@whiteandwilliams.com
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com
Read the full story...
Data Center Construction: Contractors Must Step Up
May 26, 2026 —
Aarni Heiskanen - AEC BusinessI attended the
Datacenter Forum 2026 in Helsinki last week. Over 400 people packed the room. Walking out, I had one overriding thought: Is construction operating in a different century from the technology it is being asked to house?
Is Our Industry on Par?
Ciarán Forde, Senior Vice President at CTS Nordics, opened the forum with a statement that set the tone for everything that followed: data centers are no longer just a technical challenge; they are a national strategy. Before AI, Ciarán had worked in telecoms, where data centers were already complex. But now, he said flatly, everything has changed, and the industry must rethink everything.
The numbers behind the claim are staggering. Current AI data center racks run at 40 to 100 kW. In three years, 800 kW per rack is on the roadmap. And the development cycle for a new chip is roughly one year, which means deployments begin aging out almost as soon as they are commissioned.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Newmeyer Dillion Ranked in Chambers Spotlight California 2026 Guide
May 26, 2026 —
Newmeyer DillionNEWPORT BEACH, Calif. – May 14, 2026 - Prominent business and real estate law firm Newmeyer Dillion has been ranked in Chambers Spotlight California 2026 guide and recognized as a leading firm in Litigation: General Commercial for Orange County.
Newmeyer Dillion was selected based on an independent and in-depth market analysis, coupled with an assessment of the firm’s experience, expertise and caliber of talent where the firm stood out for its exceptional work and is recognized in Litigation: General Commercial.
Managing Partner Paul Tetzloff expressed the firm's gratitude: “It is an honor for our firm to be recognized by Chambers and Partners in their Spotlight California 2026 guide. This acknowledgment reflects our commitment to providing high quality legal services tailored to the unique needs of our clients.”
Read the full story...Reprinted courtesy of
Newmeyer Dillion