California Poised for the Most Significant Residential Construction Defect Reforms in Decades
September 01, 2026 —
Thomas D. Fama & Andrew J. Mallon - Wood Smith Henning BermanThe California Legislature is considering legislation that would dramatically alter the landscape of residential construction defect litigation. Assembly Bill 1903, currently pending before the Senate Judiciary Committee, proposes extensive amendments to California's Right to Repair Act (Civil Code sections 895-945.5) that would substantially strengthen procedural protections for builders while narrowing the scope of recoverable construction defect claims.
If enacted, the legislation would affect virtually every stage of a construction defect dispute- from the initial notice of claim through litigation and settlement- and would introduce an entirely new certification process for newly constructed condominium projects. This article details some of the most significant proposed changes.
Higher Burden for Construction Defect Plaintiffs
Perhaps the most consequential change is the bill's modification of the proof required to establish liability. current law generally requires a claimant to demonstrate the residence fails to satisfy one of the statutory performance standards established under the Right to Repair Act. AB1903 would instead require claimants to establish three separate elements:
- A violation of an applicable statutory performance standard;
- The violation caused appreciable, present, non-speculative physical damage to another building component; and
- The violation resulted from the original construction.
Reprinted courtesy of
Thomas D. Fama, Wood Smith Henning Berman and
Andrew J. Mallon, Wood Smith Henning Berman
Mr. Fama may be contacted at tfama@wshblaw.com
Mr. Mallon may be contacted at amallon@wshblaw.com
Read the full story...
Samuel Alhadeff Represents LGI Homes in Acquisition and Re-Entitlement of Maravilla Estates
July 06, 2026 —
Lewis BrisboisTemecula Partner Samuel Alhadeff recently represented LGI Homes in its acquisition and re-entitlement of Maravilla Estates, a 169-lot active adult community located in San Jacinto, California.
The acquisition and re-entitlement of the project provide LGI Homes with the opportunity to deliver much-needed age-qualified housing in one of Riverside County's growing residential markets. The community includes a recorded final map and finished lots, as well as future development inventory and planned amenities, positioning the project for continued development and completion.
Read the full story...Reprinted courtesy of
Lewis Brisbois
GRSM Team Obtains Defense Verdict for Homeowners’ Association in Orange County Superior Court
July 20, 2026 —
Gordon Rees Scully MansukhaniA Gordon Rees Scully Mansukhani multi-state team, including Partners Christine Barker, Sean Ferron, and Keith Cramer, obtained a defense verdict on behalf of a homeowners’ association (HOA) in an Orange County Superior Court bench trial spanning two months.
The case began in 2022 when a homeowner sued after the Architectural Review Committee and HOA Board of Directors declined his teardown-and-rebuild plans due to view and aesthetic concerns. After a motion for summary judgment ruling in which the court found that the existing covenants, conditions, and restrictions (CC&Rs) did not protect views, the HOA held a special election to add explicit view protections to the CC&Rs. At the February 2025 trial call, the plaintiff sought leave to file a third amended complaint challenging the validity of that vote, drastically reframing the case from CC&R enforcement to one of election validity. A second plaintiff then filed a parallel action toward the end of the limitations period, and the two cases were consolidated.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Ahlers Cressman & Sleight leads in recognized Construction Litigation Attorneys
September 01, 2026 —
Ahlers Cressman & Sleight PLLCAhlers Cressman & Sleight is pleased to announce its leading recognition in the 2026 Washington Super Lawyers magazine. With ten members named, ACS has more recognized Construction Litigation attorneys than any other firm on the 2026 Washington Super Lawyers list, compared to three at the next closest firm. Two ACS members were also recognized on the 2026 Washington Rising Stars list.
Super Lawyers selects these recognized lawyers by using a patented multiphase selection process. First, lawyers enter the candidate pool by being nominated by their peers or by being identified by managing partner surveys, third-party feedback, or the Super Lawyersresearch team. Next, Super Lawyersconducts an independently researched evaluation using twelve indicators of professional achievement and peer recognition: verdicts/settlements, transactions, representative clients, experience, honors/awards, special licenses/certifications, position within a law firm, bar and/or professional activity, pro bono and community service, scholarly lectures/writings, education/employment background, and other outstanding achievements. Then, candidates with the highest point totals serve on a Blue Ribbon panel, evaluating other candidates within their primary practice area. Finally, only 5% of attorneys are selected for the Super Lawyers list, and 2.5% of attorneys are selected for the Rising Stars list. More information about the Super Lawyers Selection Process can be found
here.
Read the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Italian Court Convicts 32 in Morandi Bridge Collapse Case
August 25, 2026 —
Bryan Gottlieb - Engineering News-RecordFormer Autostrade per l'Italia CEO Giovanni Castellucci was sentenced to 12 years in prison July 16 after an Italian court handed down the first criminal verdicts stemming from the 2018 Morandi Bridge collapse in Genoa that killed 43 people.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
Defend Now, Allocate Later? An Unresolved Tension in Colorado Construction Law
August 16, 2026 —
David McLain - Colorado Construction Litigation BlogFor decades, Colorado law has recognized an important distinction between the duty to defend and the duty to indemnify. The former ordinarily arises at the beginning of litigation; the latter generally cannot be determined until the underlying liability is known. That distinction makes intuitive sense. A defense that becomes due only after litigation concludes is not much of a defense.
But Colorado’s construction anti-indemnity statute, C.R.S. § 13-21-111.5(6), raises an interesting question about how that familiar rule operates in construction disputes. The statute expressly regulates contractual obligations not only to indemnify, but also to insure and defend, and it reflects a legislative policy that construction businesses should bear financial responsibility for their own negligence.
Those principles have developed along separate tracks. At some point, a Colorado appellate court may have to decide precisely how they fit together.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Voluntary Dismissal of an Indemnity Claim Does Not Make the Subcontractor a “Prevailing Party,” Washington Court of Appeals Holds
September 21, 2026 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIn
King County v. Walsh Construction Company II, LLC, No. 86503-0-I (Wash. Ct. App. Aug. 4, 2025), an unpublished decision from Division I of the Washington Court of Appeals, the Court affirmed the denial of a subcontractor’s request for prevailing-party attorney fees under an indemnity clause after the general contractor voluntarily dismissed its indemnity claims. Because the indemnity claim was no longer live and no determination of fault had occurred, the Court held that the trial court did not err in denying the request. ACS represented Walsh, the general contractor, in securing the denial of the fee request at the trial court that the Court of Appeals affirmed.
A Pass-Through Indemnity Claim That Ended Before Fault Was Decided
The dispute arose out of a public works contract under which King County hired Walsh Construction Company II, LLC (“Walsh”) to construct and install a conveyance pipeline. After the pipeline broke, King County sued Walsh for breach of contract and warranty, expressly identifying both Walsh and its subcontractor, Mears Group Inc., (“Mears”) as responsible. Walsh tendered defense and indemnity to Mears under the subcontract.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Builders Risk/Construction All Risks and Delay in Start-Up Coverage for Large Energy Projects: Protecting Revenue Before Operations Begin
September 21, 2026 —
Will Bennett - SDV FenchurchThe Most Significant Loss May Be the Delay, Not the Damage
Power and energy projects are uniquely vulnerable to losses during construction. Whether the project involves a utility-scale solar facility, battery storage installation, a wind farm, transmission project, LNG terminal, or conventional generation facility, loss events in this sector often have consequences far more impactful than the actual cost of repairing damaged property.
Any number of construction losses can delay commercial operation of the facility by months, triggering lost revenues, financing impacts, contractual penalties, and investor concerns. In many cases, those delay-related losses significantly exceed the underlying repair costs.
Construction All Risk (“CAR”) insurance and Delay in Start-Up (“DSU”) coverage are designed to respond to these exposures. However, recovering delay-related losses is far more complicated than many insureds anticipate, particularly when projects involve international stakeholders, global supply chains, and London market insurance placements.
Read the full story...Reprinted courtesy of
Will Bennett, SDV FenchurchMr. Bennett may be contacted at
will.bennett@sdvfenchurch.us