Consider The Limited Warranty from Your Homebuilder
July 06, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen purchasing a home from a homebuilder, there is an important consideration when it comes to the limited warranty you receive around the time you close on the home. That limited warranty likely includes an arbitration provision requiring you to arbitrate your disputes, such as construction defect claims, against the homebuilder. That arbitration provision will most likely include all claims, including statutory claims (such as a statutory violation of a building code claim), requiring you to arbitrate, as opposed to litigate, your disputes against the homebuilder. This is an important consideration. If the arbitration provision does not allow you to arbitrate all of your claims, and eliminates your rights to legitimate statutory claims, the arbitration provision could be unenforceable.
By way of example, in a residential construction defect dispute, Anderson v. Taylor Morrison of Florida, Inc., 223 So.3d 1088 (Fla. 2d DCA 2017), the appeal turned on whether the arbitration provision in the homebuilder’s limited warranty was valid. The homeowners took possession of their home in 2009. In 2015, the homeowners served a Florida Statutes Chapter 558 notice of construction defects that included a statutory violation of a building code claim under Florida Statute §553.84. The limited warranty included an arbitration provision that specified it was the “exclusive remedy” for all disputes arising out of or related to the warranty or issues with the home and property. When read together with the warranty’s disclaimer that precluded claims not covered by the warranty “whether in contract, tort, or otherwise,” the statutory building code violation claim could not be remedied through arbitration because it fell outside the warranty’s coverage.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Sixth Circuit Revives Builder’s Risk Coverage, Refusing to Let Insurer Escape on a Technicality
July 27, 2026 —
Kevin V. Small & Adriana A. Perez - Hunton Insurance Recovery BlogIn 3371 Reading, LLC v. Liberty Mutual Group, the Sixth Circuit did something courts do not always do in coverage disputes: it refused to let an insurer avoid liability based on a technical policy condition that could never actually be satisfied.
The decision is a straightforward reminder of two core principles. First, policies must be interpreted from the standpoint of a reasonably prudent insured. Second, hyper-technical conditions cannot be used to deny coverage where compliance is never possible.
Reprinted courtesy of
Kevin V. Small, Hunton Andrews Kurth LLP and
Adriana A. Perez, Hunton Andrews Kurth LLP
Mr. Small may be contacted at ksmall@hunton.com
Ms. Perez may be contacted at pereza@hunton.com
Read the full story...
Utah’s Emerging Framework for Responsible Data Center Development
September 08, 2026 —
Denise A. Dragoo & Josh Miller - Snell & WilmerUtah is establishing itself as one of the nation’s most attractive jurisdictions for large-scale data center development, with a structured, defensible regulatory pathway that gives developers and investors the clarity needed to deploy capital at scale. The cornerstone is Executive Order 2026-03, “Establishing a Higher Bar for Data Center Development in Utah,” signed by Governor Spencer J. Cox on May 29, 2026.
The Executive Order creates an actionable compliance framework letting developers demonstrate stewardship across water, air quality, energy, wildlife, and community engagement – reducing regulatory and reputational risk. Recent enactments on energy self-supply and water rights operationalize these principles, while a few counties have adopted short-term local moratoria to update zoning; understanding how these interact with the state framework matters for site selection.
Reprinted courtesy of
Denise A. Dragoo, Snell & Wilmer and
Josh Miller, Snell & Wilmer
Ms. Dragoo may be contacted at ddragoo@swlaw.com
Mr. Miller may be contacted at jmiller@swlaw.com
Read the full story...
White and Williams LLP Attorneys Recognized as PA and DE Super Lawyers
July 06, 2026 —
White and Williams LLPWhite and Williams LLP is proud to announce that eight attorneys in the firm’s Philadelphia office and one attorney in the firm's Delaware Office have been recognized on the 2026 Super Lawyers® and Rising Star lists. This recognition highlights our attorney's exceptional legal acumen and their commitment to client service excellence.
Lawyers are selected for inclusion in Pennsylvania and Delaware Area Super Lawyers® and Rising Stars through a process that considers independent research, peer recognition and the professional achievements of attorneys from more than 70 practice areas. Approximately 2.5% of lawyers in each state are selected by the research team at Super Lawyers® to receive this honor.
Read the full story...Reprinted courtesy of
White and Williams LLP
Voluntary Dismissal of an Indemnity Claim Does Not Make the Subcontractor a “Prevailing Party,” Washington Court of Appeals Holds
September 21, 2026 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIn
King County v. Walsh Construction Company II, LLC, No. 86503-0-I (Wash. Ct. App. Aug. 4, 2025), an unpublished decision from Division I of the Washington Court of Appeals, the Court affirmed the denial of a subcontractor’s request for prevailing-party attorney fees under an indemnity clause after the general contractor voluntarily dismissed its indemnity claims. Because the indemnity claim was no longer live and no determination of fault had occurred, the Court held that the trial court did not err in denying the request. ACS represented Walsh, the general contractor, in securing the denial of the fee request at the trial court that the Court of Appeals affirmed.
A Pass-Through Indemnity Claim That Ended Before Fault Was Decided
The dispute arose out of a public works contract under which King County hired Walsh Construction Company II, LLC (“Walsh”) to construct and install a conveyance pipeline. After the pipeline broke, King County sued Walsh for breach of contract and warranty, expressly identifying both Walsh and its subcontractor, Mears Group Inc., (“Mears”) as responsible. Walsh tendered defense and indemnity to Mears under the subcontract.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Presumption of Prejudice Applies to All Affirmative Defenses Regarding Insured’s Failure to Comply with Post-Loss Policy Conditions
June 23, 2026 —
David Adelstein - Florida Construction Legal Updatesn a recent property insurance coverage dispute, an issue on appeal pertained to the “prejudice” jury instruction associated with the insured’s failure to comply with post-loss policy conditions. The trial court found that the prejudice only pertained to prompt notice and not other post-loss policy conditions. This was reversed on appeal as prejudice applied to ALL the post loss policy conditions that the insured failed to comply with, not just the prompt notice requirement. The prejudice presumption applies to all affirmative defenses regarding an insured’s failure to comply with post-loss policy conditions.
Consider this discussion when dealing with an insurer raising prejudice as an affirmative defense to do an insured’s failure to comply with post-loss policy conditions, and the associated burdens of proof:
On appeal, [the insurer] contends the trial court erred by instructing the jury that the presumption of prejudice was inapplicable to all of its post-loss obligation defenses except prompt notice. We agree.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Real Estate & Construction News Roundup (6/24/26) – HUD to Fund AI Grants, Luxury Hotel Deal Investment Activity to Surge, ESPCs to Fund Energy and Infrastructure Improvements
July 06, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, data centers are exposed to climate change, commercial tenant sues CoStar, cities see opportunities in emerging sports markets, and more!
- With deferred maintenance growing and capital dollars stretched thin, local governments are using ESPCs to fund energy and infrastructure improvements through future operational savings. (Vicky Uhland, Construction Dive)
- The U.S. Department of Housing and Urban Development is offering up to $3 million in grants for local governments to deploy automated permitting and building code systems. (Ryan Kushner, Construction Dive)
- Luxury hotel deals are set to see a surge in investment activity due to strong fundamentals and strengthening capital markets. (Noor Adatia, Hotel Dive)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
U.S. Supreme Court Decision Alters Course of $745M Louisiana Coastal Damage Judgment
June 15, 2026 —
Jennifer Kretschmann & Jennifer E. Michel - Lewis BrisboisThe U.S. Supreme Court has issued a unanimous decision allowing oil and gas companies to move Louisiana coastal erosion lawsuits from state court to federal court under the federal officer removal statute. While the ruling is procedural, it carries significant implications for environmental- and energy-related risks. The case,
Chevron U.S.A. Inc. v. Plaquemines Parish, Louisiana, Slip Op. 24-813 (April 17, 2026), addressed a threshold jurisdictional question but has broader significance for environmental and climate related litigation. State courts are often viewed as more favorable forums for plaintiffs asserting environmental damage claims, particularly those brought by governmental entities.
The opinion issued on April 17, 2026 is the latest development in long-running Louisiana coastal litigation that began more than a decade ago. Starting in 2013, Louisiana parishes filed 42 lawsuits against oil and gas companies alleging environmental damage related to historic oil field operations. The parishes alleged that oil and gas companies violated state coastal management laws by failing to properly restore impacted areas. Chevron sought to remove the cases from state court under 28 U.S.C. § 1442(a)(1), known as federal officer removal, which provides federal jurisdiction over “any person acting under [an] officer” of the United States "for or relating to any act under color of such office." The Fifth Circuit rejected the argument and remanded the case, and others like it, to state court. Trial began in March 2025 in Point à la Hache, Louisiana. On April 4, 2025, the jury awarded a total of $745 million to compensate for land loss, contamination and abandoned equipment. On June 16, 2025, the U.S. Supreme Court agreed to review the question of whether a federal contractor can remove to federal court when sued for oil-production activities undertaken to fulfill a federal oil-refinement contract.
Reprinted courtesy of
Jennifer Kretschmann, Lewis Brisbois and
Jennifer E. Michel, Lewis Brisbois
Ms. Kretschmann may be contacted at Jennifer.Kretschmann@lewisbrisbois.com
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Read the full story...