EPA Steps Back, Arizona Moves Forward
May 12, 2026 —
Patrick J. Paul, John Habib & Sukhmani K. Singh - Snell & WilmerIn a significant development for Arizona’s business community and environmental policymakers, the U.S. Environmental Protection Agency (EPA) has paused its planned reclassification of Maricopa County from “Moderate” to “Serious” ozone nonattainment status pursuant to the Clean Air Act’s National Ambient Air Quality Standards (NAAQS).
This decision marks a shift in federal air policy — one that recognizes the unique challenges faced by regions like metro Phoenix, where environmental conditions beyond local control are often key contributors to air quality readings.
The EPA’s move follows a series of meetings between EPA Administrator Lee Zeldin, Arizona elected officials, and business and civic leaders, including a recent roundtable in Phoenix convened by U.S. Senator Mark Kelly. In announcing the pause, Zeldin acknowledged the need for flexibility and fairness in the application of Clean Air Act standards, especially when emissions from other states, nations, and natural events significantly influence local air quality.
Reprinted courtesy of
Patrick J. Paul, Snell & Wilmer,
John Habib, Snell & Wilmer and
Sukhmani K. Singh, Snell & Wilmer
Mr. Paul may be contacted at ppaul@swlaw.com
Mr. Habib may be contacted at jhabib@swlaw.com
Ms. Singh may be contacted at ssingh@swlaw.com
Read the full story...
Hidden Risks Behind Today’s Stadium Construction Boom
July 20, 2026 —
Thomas Strong, Andrew Canning & Marc Gnesin - Construction ExecutiveAfter a decade-plus lull, professional sports leagues, universities and municipalities are once again spending heavily on new
stadiums and major renovations. In the NFL alone, multiple marquee projects are underway or planned, representing more than $10 billion in facilities and mixed-use entertainment districts, rivaling or exceeding the scale of development during the last stadium-build cycle of the early 2000s.
Beneath the excitement of architectural ambition and civic pride lies a risk landscape that has fundamentally changed since the last wave of stadium construction. Teams, cities and contractors that rely on outdated assumptions may find themselves exposed to cost overruns, schedule delays and liabilities that are far more difficult to unwind once construction is underway.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Actual Controversy Without Actual Exhaustion: California Supreme Court Allows Declaratory Relief and Bad Faith Claims Against Excess Insurers
August 24, 2026 —
Kyle A. Rudolph - Saxe Doernberger & Vita, P.C.California courts were previously split on the issue of whether an insured may bring declaratory relief claims against excess insurers prior to the exhaustion of underlying insurance. Some California courts held that the actual exhaustion of underlying insurance was necessary, whereas other courts allowed for these types of claims to proceed.[
1]
Recently, the California Supreme Court addressed this split of authority and, in doing so, handed down a significant win for policyholders. In Fox Paine & Company, LLC, et al. v. Twin City Fire Insurance Company et al., the Court held that insureds may proceed with bringing forth viable declaratory relief and bad faith claims against excess insurers prior to the exhaustion of underlying insurance.[
2] A summary of the Court’s opinion is provided below.
Read the full story...Reprinted courtesy of
Kyle A. Rudolph, Saxe Doernberger & Vita, P.C.Mr. Rudolph may be contacted at
KRudolph@sdvlaw.com
Course of Construction Exclusions and the CGL Policy
July 20, 2026 —
Anna M. Perry, Rachel S. Kindseth & Nina Catanzaro - Saxe Doernberger & Vita, P.C.I. Course of Construction Exclusions
Course of Construction (“COC”) exclusions are found on General Liability and excess liability policies, typically a wrap-up or project specific policy, and generally exclude “all property damage occurring during the course of construction.” Insurers claim COC exclusions are not problematic because they are intended to prevent an overlap in coverage between the general liability policy and first-party property Builder’s Risk policy. However, because General Liability policies and Builder’s Risk policies provide coverage for different risks, COC exclusions can create a gap in coverage for owners and contractors. Therefore, any exclusion on a wrap-up or project specific policy that limits coverage for property damage liability should be scrutinized, and amendments sought when warranted and commercially achievable, for owners, developers and contractors because General Liability policies do not cover the same risk as that of a Builder’s Risk policy.
General liability policies provide defense and indemnity to the insured(s) for claims made by a third-party against the insured. Broad COC exclusions serve to preclude coverage for all property damage, not just property damage to the insured project. This includes property damage to property other than the insured project, e.g. an adjacent property. On the other hand, Builder’s Risk policies provide first-party property coverage for direct physical loss to the project during the course of construction. The Builder’s Risk policy will not provide coverage for property other than the project itself (e.g., adjacent property) and it will not provide a defense or indemnity in the event the owner of the damaged property brings a claim against a potentially at-fault party.
Reprinted courtesy of
Anna M. Perry, Saxe Doernberger & Vita, P.C.,
Rachel S. Kindseth, Saxe Doernberger & Vita, P.C. and
Nina Catanzaro, Saxe Doernberger & Vita, P.C.
Ms. Perry may be contacted at APerry@sdvlaw.com
Ms. Kindseth may be contacted at rkindseth@sdvlaw.com
Ms. Catanzaro may be contacted at NCatanzaro@sdvlaw.com
Read the full story...
Are “Financial Hardship” Damages Recoverable?
June 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn a case out of the Civilian Board of Contract Appeals, F.O.G., LLC v. Department of the Interior, CBCA 8203, 2026 WL 1191881 (CBCA 2026) a contractor claimed damages that included “financial hardship” damages due to slow payments. The financial hardship damages included personal damages to the contractor’s president and his wife. Are these damages recoverable? Drumroll…The Board ruled that the contractor cannot recover such financial hardship damages.
As it relates the personal financial hardship damages, the Board ruled, “Neither [the contractor’s] president nor his wife are a party to this contract, are in privity of contract with [the government], or are the beneficiaries under this contract. [The contractor], therefore, cannot recover for any losses that either one has suffered individually and that [the contractor] claimed in this appeal.” F.O.G., LLC, supra.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.
Building in Arizona’s Data Center Boom: How Federal Executive Orders, State Regulation, and National-Security Policy Are Reshaping the Rules for Developers
June 02, 2026 —
Ryan J. Regula - Snell & WilmerDevelopers and practitioners evaluating data center projects in Arizona face a regulatory environment shifting on three fronts simultaneously. Federal executive orders are opening new land, streamlining permitting, and channeling financial incentives toward qualifying projects — but they are not preempting the state and local rules that most directly affect project economics. A carve-out in the December 2025 Artificial Intelligence (AI) Framework Executive Order preserves Arizona’s authority over data center infrastructure, meaning the Arizona Corporation Commission’s (ACC) rate-classification docket, municipal zoning restrictions, water-use ordinances, and pending grid cost-allocation legislation remain the binding constraints on project feasibility. Understanding where federal tailwinds end and state and local headwinds begin is essential for any developer sizing risk or selecting sites in the state.
The Federal Landscape: An Interlocking Framework of Executive Orders
Five interlocking executive orders are accelerating data center development nationally, but none overrides Arizona’s authority over siting energy, or infrastructure.
Read the full story...Reprinted courtesy of
Ryan J. Regula, Snell & WilmerMr. Regula may be contacted at
rregula@swlaw.com
Risks of Using an AI Chatbot for Legal Advice: Lessons from United States v. Heppner
April 08, 2026 —
Payne & Fears LLPImagine that you are an executive (who is not a lawyer) and are concerned about what your company plans to do is legal. You could call your lawyer who might bill you for the call. Or, you can ask your AI chatbot, such as Claude or ChatGPT, about the legal risk. The chatbot will likely compliment you on the incisive question, provide you with highly confident answer (that may or may not be right) and will not bill you on an hourly basis.
That is essentially what financial services executive Bradley Heppner did. It did not end well. A federal court recently ruled that Heppner’s chats with the AI tool Claude were not protected by attorney-client privilege or the work-product doctrine. That means that the other side (in this case, the federal government) could get access to his chatbot prompts, uploads and responses, and learn a great deal about, for example, whether Heppner knew what he was doing was illegal.
Read the full story...Reprinted courtesy of
Payne & Fears LLP