Builders Risk/Construction All Risks and Delay in Start-Up Coverage for Large Energy Projects: Protecting Revenue Before Operations Begin
September 21, 2026 —
Will Bennett - SDV FenchurchThe Most Significant Loss May Be the Delay, Not the Damage
Power and energy projects are uniquely vulnerable to losses during construction. Whether the project involves a utility-scale solar facility, battery storage installation, a wind farm, transmission project, LNG terminal, or conventional generation facility, loss events in this sector often have consequences far more impactful than the actual cost of repairing damaged property.
Any number of construction losses can delay commercial operation of the facility by months, triggering lost revenues, financing impacts, contractual penalties, and investor concerns. In many cases, those delay-related losses significantly exceed the underlying repair costs.
Construction All Risk (“CAR”) insurance and Delay in Start-Up (“DSU”) coverage are designed to respond to these exposures. However, recovering delay-related losses is far more complicated than many insureds anticipate, particularly when projects involve international stakeholders, global supply chains, and London market insurance placements.
Read the full story...Reprinted courtesy of
Will Bennett, SDV FenchurchMr. Bennett may be contacted at
will.bennett@sdvfenchurch.us
One Year In: A Look at the Initial Impacts of LEED v5 on the Built Environment
October 20, 2026 —
Eric Haggstrom - Construction ExecutiveAs federal
climate policies shift, the built environment has entered a period of uncertainty where developers, designers and owners need to find pragmatic, forward-looking approaches to sustainability. A year after its launch on April 28, 2025,
LEED v5 is helping lead that charge by pushing the industry toward a stronger long-term focus on carbon reduction, climate resilience and building performance. The framework of this certification provides a snapshot of the current state of the industry and an indication of where it may be headed in the future.
LEED v5’s introduction has helped to begin reframing and informing the approaches of both mission-driven and cost-conscious clients, providing a framework to align their decisions more closely with sustainable priorities by emphasizing carbon reduction, energy efficiency and electrification. These standards can help teams make investments strategically by phasing in upgrades, planning for future technologies and demonstrating how the rating system is influencing long-term decision-making across projects.
Reprinted courtesy of
Eric Haggstrom, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Ohio Supreme Court Blocks Ballot Measure Targeting $4B AWS Data Center
October 26, 2026 —
Bryan Gottlieb - Engineering News-RecordOhio's High Court on Sept. 18 blocked a ballot measure that could have imposed new operating restrictions and citizen lawsuits on a planned $4-billion Amazon Web Services data center campus in Wilmington, about 35 miles southeast of Dayton.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
“The Superintendent Told Us to Do It:” Why Verbal Approval May Not Be Enough
June 02, 2026 —
Andrew Lintner - Colorado Construction Litigation BlogIn construction defect litigation, one scenario appears repeatedly: a subcontractor installs work in a manner that differs from the plans, specifications, manufacturer instructions, or industry standards after being verbally directed to do so by the general contractor, superintendent, architect, or owner’s representative.
At the time, the decision may seem minor. The project is moving quickly, the field team wants to maintain progress, and nobody wants to stop working over what appears to be a small issue. The subcontractor may trust the superintendent or project manager and assume the conversation will be remembered later if questions arise.
Years later, however, when the project experiences problems, the people involved may deny the conversation occurred, remember it differently, or simply no longer remember the project. Without written documentation, the subcontractor can find itself defending claims for defective work, even though it performed the installation exactly as directed.
Read the full story...Reprinted courtesy of
Andrew Lintner, Higgins, Hopkins, McLain & Roswell, LLCMr. Lintner may be contacted at
alintner@hhmrlaw.com
Travelers Injury Impact Report Highlights Longer Recovery Times Amid Declining Injury Rates
May 05, 2026 —
The Travelers Companies, Inc.HARTFORD, Conn.--(BUSINESS WIRE)--The Travelers Companies, Inc. (NYSE: TRV) today released its 2026 Injury Impact Report, an analysis of more than 1.2 million workers compensation claims received by the company from 2021 through 2025. The report finds that even as workplace injury rates decline, the injuries that do occur are growing more complex and taking longer to heal – a trend driven by an aging workforce and the disproportionate vulnerability of first-year employees.
“The decrease in workplace injuries is a positive story, yet injured workers are still missing an average of 80 workdays,” said Claude Howard, Vice President of Workers Compensation Claim at Travelers. “This report is a reminder that progress doesn’t mean the risk environment requires any less attention, and an employer’s commitment to safety must keep pace with an ever-evolving workforce and injury landscape.”
Read the full story...Reprinted courtesy of
The Travelers Companies, Inc.
Celebrating Freedom: The Overlooked Freedom to Contract in Commercial Insurance
July 20, 2026 —
Michael S. Levine & Andrea DeField - Hunton Insurance Recovery BlogHappy 4th and 250 years of freedom . . . to contract!
Many policyholders assume insurance policies are “standard” and must be accepted as-is. That assumption is often wrong—and dangerously limiting. Unlike many consumer insurance markets, the commercial insurance realm preserves a robust “freedom to contract,” allowing sophisticated policyholders to negotiate terms, exclusions, definitions, and limits before a policy is even issued. Particularly in recent years, high-profile disputes over cyber coverage, business interruption, and war/cyber exclusions have shown not just what happens when coverage is denied, but what could have been done up front to avoid those fights.
This post highlights the power policyholders still hold in the negotiation process and illustrates, with concrete examples from recent media-covered disputes, how that freedom can be strategically used.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth LLP and
Andrea DeField, Hunton Andrews Kurth LLP
Mr. Levine may be contacted at mlevine@hunton.com
Ms. DeField may be contacted at adefield@hunton.com
Read the full story...
Conditional Payment Bond Consideration-Make Sure There Is Pay-If-Paid Provision
June 29, 2026 —
David Adelstein - Florida Construction Legal UpdatesIf a general contractor is going to have a conditional payment bond, it needs to ensure it subcontracts contain pay-if-paid or pay-when-paid provisions. This conditional payment language in subcontracts is the general contractor’s defense that it doesn’t have to pay a subcontractor UNTIL owner has paid the general contractor for the subcontractor’s work.
The general contractor (and the surety) can look at the conditional payment bond with the s. 713.245 legend stamped on its face designating the conditional nature of the bond, and assume the conditional structure is locked in against the bond: no payment from the owner, no obligation to the subcontractors under the bond. But what happens when the subcontracts contain no express conditional payment language despite having a valid conditional payment bond?
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
What Construction Attorneys Do and When Contractors Need Them
August 11, 2026 —
Construction ExecutiveDirect Answer
A construction attorney advises contractors on contracts, payment rights, mechanic's liens, payment bond claims, change orders, delay claims, OSHA matters, defect claims, terminations and dispute resolution. The work covers far more than lawsuits—much of its value comes before a dispute ever becomes formal.
Construction attorneys help contractors protect payment rights, manage project risk, resolve disputes and avoid contract terms that can turn a profitable job into a financial loss. Their work covers more than lawsuits. A construction attorney may review a contract before bid day, help preserve lien rights, respond to a defective work claim, prepare for mediation or defend a contractor after a safety citation.
For contractors, legal counsel is often most valuable before a dispute becomes formal. A missed notice deadline, vague scope clause, unsigned change order or broad indemnity provision can create problems long before a claim is filed. Construction attorneys help identify those risks while there is still time to negotiate, document the issue or preserve leverage.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...