Pay-If-Paid: What You Need to Know Before Signing on the Dotted Line
August 03, 2026 —
Christian Fernandez & Matthew Racioppo - Snell & WilmerBuried deep in the fine print of a subcontract, a pay-if-paid clause may be looming. If you are a subcontractor or supplier, misreading these clauses can put your cash flow at risk. If you are an owner or general contractor, drafting them incorrectly can leave you with obligations you never intended — or unenforceable protections you were counting on.
It is more important than ever to understand when pay-if-paid clauses hold up and when they do not, as well as recent litigation and drafting trends. Whether you are negotiating a new agreement, reviewing your standard form contracts, or staring down a payment dispute, understanding how Arizona law treats pay-if-paid clauses is essential. In this article, we break down key considerations, walk through the legal standards Arizona courts apply, and offer practical tips to consider to help you protect your payment rights on the next project.
Reprinted courtesy of
Christian Fernandez, Snell & Wilmer and
Matthew Racioppo, Snell & Wilmer
Mr. Fernandez may be contacted at cfernandez@swlaw.com
Mr. Racioppo may be contacted at mracioppo@swlaw.com
Read the full story...
Every High-Tech Building Has Many Lifespans
August 16, 2026 —
Aarni Heiskanen - AEC BusinessWhen I worked as an architect, our team designed a laboratory for fuel research. The facility included a large research hall where various boilers and other devices were tested and analyzed. The setup required extensive floor channeling under the thick concrete floor. We suggested building a modular system that would allow flexibility in the future, when requirements would certainly change. They did not want that because of budget constraints.
The high-tech construction trend is spreading. Data centers, semiconductor fabs, battery plants, and life science facilities share one property that sets them apart from ordinary buildings. The technology inside turns over faster than the structure around it. Server generations change every three to five years. Rack densities have risen from 10 or 20 kW to 130 kW and beyond in just a few years.
A high-tech facility is really several buildings with different lifespans inside one envelope, and we keep designing them as if they were one. The failure is not that things become obsolete. It is that we never say when each layer is expected to.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Legal 500 US Ranks Hunton’s Insurance Coverage Team Among Top Policyholder Practices in 2026 Guide
July 06, 2026 —
Hunton Insurance Recovery BlogHunton’s insurance coverage practice was once again recognized among the nation’s top policyholder insurance practices, receiving a Band 2 national ranking in the 2026 United States Edition of The Legal 500 for Insurance: Advice to Policyholders. The Legal 500 recognizes firms solely based on merit through numerous factors including client feedback and peer input.
Bolstering the team’s national recognition, several coverage lawyers received individual accolades: special counsel
Lorelie “Lorie” S. Masters was named to The Legal 500’s Hall of Fame; team head
Syed S. Ahmad and partner
Michael S. Levine were named Leading Lawyers; and partners
Andrea DeField and
Latosha M. Ellis were named Next Generation Partners. In addition, partners
Walter J. Andrews,
Lawrence J. Bracken II, and
Koorosh “KT” Talieh were recognized as Key Lawyers on the team.
Read the full story...Reprinted courtesy of
Hunton Andrews Kurth LLP
Did You Get the Message? (And does it count?) The Legal Consequences of Text Messages, Group Chats, and Informal Digital Communication on Construction Projects
March 17, 2026 —
Kellie Ros & Curtis Martin - ConsensusDocsIntroduction: The New Reality of Construction Communication
Construction projects have always depended on a constant stream of communication. Today’s project managers, superintendents, and foremen have broadened the method of communication to include convenient forms of digital communication. Superintendents text photos of field conditions, owners send quick approvals through WhatsApp, architects clarify design intent in a Teams chat, and subcontractors coordinate sequencing through group texts. These channels are fast, convenient, and deeply embedded in modern project culture. Yet the legal framework governing construction contracts has not evolved at the same pace. Many contracts still assume – or require – that notice, directives, and approvals occur through formal written channels—letters, emails to designated recipients, or structured project‑management platforms. This disconnect creates significant legal risk, particularly for contractors who rely on informal messages as authorization for extra work or schedule changes. Courts are increasingly asked to interpret text messages, chat threads, and screenshots as evidence of notice, direction, or waiver. The outcomes vary, but the trend is unmistakable: informal digital communication is now part of the project record, and it can bind parties in ways they did not expect.
Reprinted courtesy of
Kellie Ros, Peckar & Abramson, P.C. and
Curtis Martin, Peckar & Abramson, P.C.
Ms. Ros may be contacted at kros@pecklaw.com
Mr. Martin may be contacted at cmartin@pecklaw.com
Read the full story...
What Massachusetts Contractors and Developers Can Learn from Cannistraro v. Columbia Construction
July 13, 2026 —
Anthony LaPlaca & Luke Marston - The Construction SeytIntroduction
On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.
[1]
Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a “factual and contractual basis for the rejection” and must be “certified as made in good faith.”
[2] In the absence of a timely certified notice, payment is “deemed to be approved” unless the payor properly rejects payment before it comes due.
[3]
Reprinted courtesy of
Anthony LaPlaca, Seyfarth Shaw LLP and
Luke Marston, Seyfarth Shaw LLP
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Mr. Marston may be contacted at lmarston@seyfarth.com
Read the full story...
'Drywall Isn't Light': Peter Lupo on Safety Management at Standard Drywall
May 26, 2026 —
Elaine Silver - Engineering News-RecordPeter Lupo has been safety director since 2019 at San Diego-based Standard Drywall Inc., a major wall and ceiling contractor. He draws on over two decades of safety experience across a wide range of commercial construction work, having previously served as safety director for general contractor T.B. Penick & Sons. He has also previously operated Peter Lupo Consulting, where he reviewed legal cases and provided expert testimony, and blogged on safety for ENR.com. Lupo recently spoke to ENR Correspondent Elaine Silver about the weight of drywall, heat hazard control, bilingual crews and how he supports safety creativity and learning on the Standard Drywall staff. The conversation has been edited.
Read the full story...Reprinted courtesy of
Elaine Silver, Engineering News-RecordENR may be contacted at
enr@enr.com
Late Notice Bars Insured’s Claim for Wind Damage
June 29, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that a six-month delay in reporting damage from wind did not comply with the policy’s notice requirements. Touchmark Hotel Group, LLC v. Mt. Hawley Ins. Co., 2026 U.S. Dist. LEXIS 61910 (S.D. N. Y. March 24, 2026).
A storm caused damage to Touchstone’s hotel on January 4, 2023. Touchstone’s corporate representative, Rohit Patel, testified that he was not at the property on the day of the storm. In a telephone call the next day, the manager of the property reported to Patel that he observed detached shingles from the roof the hotel in the parking lot. Patel testified that he did not file a claim at that time because Touchmark’s employees did not detect any water leakage in the building and because he did not believe that the cost of the damage from the storm would exceed the policy’s deductible.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at