Pulling the Plug, Preserving the Product: Protecting Rights to a Modular Subcontractor’s Work Post-Termination
June 08, 2026 —
Paul Williamson - ConsensusDocsVolumetric Modular Construction (VMC) is a building method where a structure is divided into large components or modules, fabricated in an offsite factory and then transported to a construction site for assembly.[
1] Proponents of VMC hail it as a cost-efficient alternative to traditional building methods that leads to more consistent quality and shorter construction duration.[
2] Due to a growing labor shortage, high demand for compressed project schedules, and stagnant construction productivity rates, the construction industry is embracing VMC.[
3] A recent report on the market size of prefabricated construction estimates that from 2026 to 2031, VMC will grow at a compound annual growth rate of 7.16% and become a 413.11-billion-dollar industry.[
4]
As VMC becomes more prevalent, owners, general contractors, and subcontractors must consider how to effectively contract for modular construction. One important consideration, which this article focuses on, is navigating termination of a modular subcontractor.
Read the full story...Reprinted courtesy of
Paul Williamson, Peckar & Abramson, P.C.Mr. Williamson may be contacted at
pwilliamson@pecklaw.com
Anti-Concurrent Causation Clause Prevents Coverage for Collapse
April 27, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court affirmed the decision of the trial court granting summary judgment to the insurer after agreeing that the policy’s anti-concurrent causation clause barred coverage. Lido Hospitality, Inc. v. AIX Specialty Ins. Co., 2026 Iii. App. Unpub. LEXIS 133 (Ill. Ct. App. Jan. 27, 2026).
One of the brick veneer walls of the Lido Motel collapsed during a windstorm. Lido reported the loss it its insurer, AIX. AIX investigated and determined that the brick veneer collapsed due to pervasive wear and tear and corrosion of the underlying infrastructure that secured the veneer- specifically the components that anchored or tied the masonry veneer to the underlying wooden substrate.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New Law Prompts ABC Minnesota/North Dakota to Design New Telecommunications Safety Training Program
June 29, 2026 —
Grace Calengor - Construction ExecutiveOn the first day of the year, a
Minnesota law requiring installers of underground telecommunication infrastructure broadband, fiber or phone lines (when projects utilize directional drilling, and/or work is being conducted within 10 feet of existing utilities) to undergo a 40-hour certification went into effect.
Originally passed in mid-2024 and proposed to go into effect in July 2025, the law’s requirements were postponed until January 2026, giving
ABC Minnesota/North Dakota—in partnership with
NCCER and the
Minnesota Cable Communications Association—time to roll out their
Safety Qualified Underground Telecommunications Installer training program, which would ensure the workforce of their contractor members were certified.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Wilke Fleury is proud to congratulate attorneys recognized in the 2027 editions of The Best Lawyers in America® and Best Lawyers: Ones to Watch® in America.
September 15, 2026 —
Wilke FleuryThe Best Lawyers in America®:
Dan Egan,
Daniel Foster,
David Frenznick, and
George Guthrie.
Best Lawyers: Ones to Watch® in America:
Islam M. Ahmad,
Kathryne Baldwin,
Melissa Eaton,
Jason Eldred, and
Mustafa Karim.
Congratulations to this outstanding group!
Read the full story...Reprinted courtesy of
Wilke Fleury
Inaccurate Representations Can Lead to Differing Site Conditions Claim
May 26, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn the
prior posting, I discussed a case dealing with a differing site condition. In that case, the owner did not have an affirmative duty to make a representation and there was no inaccurate representation made by the owner that misled the contractor.
Well, what about when there is an inaccurate misrepresentation regarding the site? This was the circumstance in an older Florida case where a dredging contractor had a successful differing site conditions claim. See Jacksonville Port Authority v. Parkhill-Goodloe, Co., Inc., 362 So.2d 1009 (Fla. 1st DCA 1978).
The government provided inaccurate information as to the lack of rock that would be encountered during the dredging that was relied on by the dredging contractor. But the government had “
superior knowledge” that there was rock in an adjacent location based on a prior claim from a contractor, yet the government did not disclose the possibility that rock could be encountered.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
U.S. Supreme Court Decision May Negate State Law Requirement to File a Certificate of Merit with the Complaint in a Federal Action Against a Design Professional
April 27, 2026 —
Christopher Olsen & Phillip Boldt - ConsensusDocsTo deter frivolous and unfounded claims against design professionals, states throughout the country have enacted statutes which generally require litigants to furnish a formal certification of merit (“COM”) from a qualified expert or face potential dismissal of their lawsuit. These COM statutes can impose a significant front-end burden on claimants who must pay an expert to review project records, interview the project team, and prepare a formal report before the lawsuit can be filed—often regardless of the amount in controversy. However, in light of a recent U.S. Supreme Court decision in a medical malpractice case, most, if not all of these statutes, may no longer be enforceable in federal court. This article examines the recent decision in Berk v. Choy, 146 S. Ct. 546 (2026), the decisions thus far which have applied Berk to invalidate COM statutes, and other categories of statutes applicable to the construction industry which may face a similar fate.
The U.S. Supreme Court Decision (Berk v. Choy)
In Berk, the plaintiff, Harold Berk, sued a doctor for medical malpractice under Delaware law in Delaware federal court. 146 S. Ct. at 551. Under Del. Code, Tit. 18, § 6853(a)(1), an affidavit of merit (like a COM) must accompany a complaint alleging medical malpractice. Id. Berk failed to include an affidavit of merit with his complaint. Id. at 552. Applying Delaware state law, the federal court dismissed Berk’s medical malpractice claim. Berk appealed to the Third Circuit, arguing that the affidavit of merit required by § 6853(a)(1) is unenforceable in federal court because it is more onerous than the Federal Rules of Civil Procedure. The Third Circuit affirmed the District Court’s ruling, finding § 6853(a)(1) enforceable in federal court.
Reprinted courtesy of
Christopher Olsen, Peckar & Abramson, P.C. and
Phillip Boldt, Peckar & Abramson, P.C.
Mr. Olsen may be contacted at colsen@pecklaw.com
Mr. Boldt may be contacted at pboldt@pecklaw.com
Read the full story...
Arizona Court of Appeals Clarifies Homeowners Association Open Meeting Requirements
June 29, 2026 —
Jill Casson Owen, Benjamin J. Hawkins & Stephen Wright - Snell & WilmerA Z N H Revocable Trust v. Sunland Springs Village Homeowners Association, No. 1 CA-CV 25-0424 (Ariz. Ct. App. Apr. 28, 2026)
OVERVIEW
The Arizona Court of Appeals issued an opinion clarifying how homeowners associations must conduct meetings under A.R.S. § 33-1804. The decision reinforces the legislative policy favoring transparency in association governance, bringing association meeting requirements more in line with the open meeting standards applicable to public bodies under A.R.S. § 38-431 et seq. (Arizona’s Open Meeting Law).
KEY HOLDINGS
1. All Voting and Formal Actions Must Occur in Open Meetings
The Court affirmed that association boards cannot vote or take formal action during closed (executive) sessions. Under A.R.S. § 33-1804(A), associations may close portions of meetings only for “consideration” of certain enumerated topics, such as legal advice, pending litigation, or personal/financial information about individual members. The Court interpreted “consideration” to mean discussion and deliberation, not voting. The Court noted that dictionaries define “consider” as “spending time thinking about a possibility” and “formulating an opinion,” which are processes that precede formal action. This interpretation mirrors how Arizona’s Open Meeting Law (A.R.S. § 38-431.03(D)) prohibits public bodies from voting in executive session.
Reprinted courtesy of
Jill Casson Owen, Snell & Wilmer,
Benjamin J. Hawkins, Snell & Wilmer and
Stephen Wright, Snell & Wilmer
Ms. Owen may be contacted at jowen@swlaw.com
Mr. Hawkins may be contacted at bhawkins@swlaw.com
Mr. Wright may be contacted at swright@swlaw.com
Read the full story...
Suit Limitation Provision Eliminates Wind Loss Claim
July 27, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer’s motion for judgment on the pleadings was granted after the insured failed to file suit against the insurer within the policy’s two-year suit limitation provision. Interstate Investments, LLC v. Mt. Hawley Ins Co., 2026 U.S. Dist. LEXIS 98108 (S.D. N. Y. May 4, 2026).
On or before June 27, 2023, a wind, hail and rainstorm damaged Interstate’s property in Oklahoma. Interstate filed a claim under its policy with Mt. Hawley. The policy provided that New York law applied and contained a two- year suit limitation provision.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com