Insureds’ Altering Dates for Hailstorm Damage Justifies Denial of Claim
June 02, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Firth Circuit affirmed the district court’s grant of summary judgment to the insurer due to the insureds’ failure to establish the date of loss after a hailstorm. Cutchall v. Chubb Lloyds Ins. Co. of Texas, 2026 WL 625633 (5th Cir. March 5, 2026).
In September 2021, the Cutchalls made a claim on their policy for interior water damage due to a hailstorm that breached their roof. Chubb retained two engineers to inspect the home, but neither found evidence that a hailstorm caused the damage. Instead, the engineers concluded a variety of other causes, such as poor ventilation and as-built defects, caused the damage. Because Chubb concluded that some of these other causes were covered by the policy, it paid only for the covered portions.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Vacant Building Negates Coverage for Broken Pipe
September 01, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe Michigan Court of Appeals found the insured was not covered for water damage because the commercial space was left vacant. Cherry Hill Recreation Center, Inc. v. Conifer Ins Co., 2026 Mich, App. LEXIS 5099 (Mich Ct. App. June 18, 2026).
Alan Abbas purchased a bowling alley. Due to the onset of the COVID-19 pandemic and executive orders issued by the governor, Abbas was unable to operate the bowling center for several months. During the winter, Abbas allowed the thermostat to drop significantly, with the building expected to be around 43 degrees Fahrenheit. He later admitted the sprinkler system’s pipes were not protected against freezing.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ball Janik LLP Welcomes Construction Defect Attorney and U.S. Air Force Veteran Jake Scott to its Fort Lauderdale Office
June 02, 2026 —
Ball Janik LLPBall Janik LLP, a leading construction defect and insurance recovery law firm, has welcomed Jake Scott as an associate in its Fort Lauderdale office. Scott joins the Construction Defect Practice Group, bringing experience across construction litigation that includes construction defect, contract dispute, and negligence matters, along with a track record of representing construction professionals through depositions, court appearances, and trial preparation to support the firm's steady growth and client service statewide.
"We're excited to welcome Jake Scott to our Fort Lauderdale office and Construction Defect Practice Group," said James C. Prichard, Managing Partner at Ball Janik LLP. "We look forward to the fresh perspectives and legal solutions he will provide for community associations across South Florida."
Scott is a results-driven attorney dedicated to providing strategic counsel for complex legal challenges. He has experience managing all phases of a case, from early investigation and discovery through trial preparation and settlement negotiations.
Prior to joining Ball Janik, Scott served as an associate attorney in Fort Lauderdale, where he represented clients in construction litigation matters, handled depositions and court appearances, conducted legal research, and drafted pleadings, motions, and briefs. He also worked as an attorney in Tampa, where he represented contractors, subcontractors, and construction firms in defending claims involving construction defects, contractual disputes, and negligence, and worked closely with expert witnesses, engineers, and consultants to develop and present technical evidence.
Scott's experience representing the development and building sides of construction disputes provides a valuable, contrast-driven perspective that supports the strategic evaluation of claims and practical approaches to resolution for Ball Janik's clients.
A proud veteran, Scott served in the United States Air Force for eight years, including roles as an Airspace Control Officer and in Space Systems Operations, supporting safe space flight operations and satellite communications.
Carrying the discipline of airborne operations, Scott worked in the aerospace sector as a Satellite Engineer and Orbital Analyst. He also held a role in the housing sector, supporting marketing and business development initiatives.
Scott received his law degree from Stetson University College of Law. He attended American Military University, where he earned degrees in marketing, business management, and related support services.
About Ball Janik LLP
Ball Janik LLP is a Florida-based law firm offering construction defect, construction law, insurance recovery, and commercial litigation counsel to its local and national clients. The firm was founded in 1982 and has expanded its capabilities, professionals, and geographic footprint. What started as a small firm focused on real property, land use, and litigation (known then as Ball Janik & Novack) has grown to a team of 50-plus attorneys and paralegals in 5 offices in Florida, with centuries of combined experience and capabilities. The firm has been recognized by Chambers USA, U.S. News & World Report and Best Lawyers®, The Best Lawyers in America©, and Corporate International. Read more here: https://www.balljanik.com.
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about “license to operate” for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of “license to operate” more literally—namely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, “If you can make it there, you can make it anywhere.”) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regime—in our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...
Late Notice Bars Insured’s Claim for Water Leak Damage
August 11, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insurer’s motion for summary judgment dismissing the insured’s claim due to late notice. Global Approach, Inc. v. Scottsdale Ins. Co., 2026 U.S. Dist. LEXIS 120183 (S. D. Fla. June 1, 2026).
Global suffered water damage on September 3, 2021, which originated in the bathroom of one of its rental properties. Global reported the claim to its insurer, Scottsdale, on October 19, 2021. Prior to reporting the claim, Global hired a handyman to inspect the property and then demolished the damaged area and repaired the bathroom.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
HDR Agreed to $12M Settlement With Miami Bridge Design-Build Team
May 12, 2026 —
Richard Korman - Engineering News-RecordHDR last year agreed to pay $12 million to the design-build construction contractor Archer Western-de Moya Group to settle its claims that the engineer had incompletely designed and under-designed Miami's new Signature Bridge when the joint venture committed to a fixed price prior to construction in 2018.
Read the full story...Reprinted courtesy of
Richard Korman, Engineering News-RecordMr. Korman may be contacted at
kormanr@enr.com
The GKN Aerospace Chemical Release and the Laws Designed to Address It
July 06, 2026 —
Sean M. Sherlock - Snell & WilmerOn May 21, 2026, a 34,000-gallon storage tank at the GKN Aerospace facility in Garden Grove, California began leaking methyl methacrylate (MMA), a volatile and highly flammable industrial chemical used to manufacture high-strength acrylic plastics. GKN Aerospace makes advanced military and commercial transparencies, such as aircraft canopies, windshields, cabin windows, bullet-resistant glass, and spacecraft windows.
In polymer chemistry lingo, MMA is known as a monomer. Monomers are like individual links to a chain. Under the right conditions they link up (react) with each other to form long-chained polymers, or plastics. MMA is an unstable monomer that requires controlled storage conditions to avoid setting off a polymerization (chain) reaction.
According to early reports, the MMA tank at GKN Aerospace overheated. The cause of the overheating is not yet clear, but the overheating may have created conditions enabling the MMA to initiate polymerization, which in turn generated heat, which in turn generated pressure, activating the tank’s pressure-relief system and releasing MMA vapor into the atmosphere. Concerns about a runaway reaction, massive release, and explosion led the Orange County Fire Authority to order evacuation of approximately 40,000 residents and closure of thirteen schools.
Read the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
$27B Meta Data Center Pushes Louisiana Toward Massive Power Expansion
April 27, 2026 —
Vince Kong - Engineering News-RecordMeta Platforms has reached an agreement with Entergy Louisiana to fund new energy infrastructure to support its planned $27-billion data center in Richland Parish, a project the company says could ultimately scale to 5 GW, becoming its largest facility to date. CEO Mark Zuckerberg has described the site as large enough to cover a significant portion of Manhattan.
Read the full story...Reprinted courtesy of
Vince Kong, Engineering News-RecordMr. Kong may be contacted at
kongv@enr.com