Real Estate & Construction News Roundup (6/24/26) – HUD to Fund AI Grants, Luxury Hotel Deal Investment Activity to Surge, ESPCs to Fund Energy and Infrastructure Improvements
July 06, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, data centers are exposed to climate change, commercial tenant sues CoStar, cities see opportunities in emerging sports markets, and more!
- With deferred maintenance growing and capital dollars stretched thin, local governments are using ESPCs to fund energy and infrastructure improvements through future operational savings. (Vicky Uhland, Construction Dive)
- The U.S. Department of Housing and Urban Development is offering up to $3 million in grants for local governments to deploy automated permitting and building code systems. (Ryan Kushner, Construction Dive)
- Luxury hotel deals are set to see a surge in investment activity due to strong fundamentals and strengthening capital markets. (Noor Adatia, Hotel Dive)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Chambers Global 2026 Recognizes Sheppard Practices and Attorneys
March 03, 2026 —
SheppardSheppard has been recognized by Chambers Global 2026 in the following practice areas:
- Privacy & Data Security in the United States
- Projects: Power & Renewables: Transactional in the United States
- Projects: Renewables & Alternative Energy in the United States
Additionally, the following Sheppard partners have been recognized by Chambers Global 2026:
- Justin Boose (Projects: Renewables & Alternative Energy – USA)
- Will Chen (Intellectual Property: International Firms – South Korea)
- David Chun (Intellectual Property – South Korea)
Read the full story...Reprinted courtesy of
Sheppard
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about “license to operate” for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of “license to operate” more literally—namely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, “If you can make it there, you can make it anywhere.”) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regime—in our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...
White and Williams LLP Secures Trio of Cyber Coverage Wins
May 12, 2026 —
Gabriel Darwick & Sean Elman - White and Williams LLPThree weeks, three jurisdictions, three cyber wins.
White and Williams picked up the first victory on March 9, 2026, in the United States District Court for the Western District of Texas, where the court granted summary judgment to their client enforcing a Cyber Crime Loss sublimit. See Perry & Perry Builders, Inc. v. Cowbell Cyber and Obsidian Specialty Ins. Co., 2026 U.S. Dist. LEXIS 49409 (E.D. Tex. Mar. 9, 2026). In Perry, the insured was deceived into transferring money intended for a vendor to an unintended third party. The insurer acknowledged that the loss was covered and paid the insured the policy’s Cyber Crime Loss sublimit. Discontent with a single sublimit, the insured argued that because it wired the money to the fraudster in separate transfers, it was entitled to a second Cyber Crime Loss sublimit.
Reprinted courtesy of
Gabriel Darwick, White and Williams LLP and
Sean Elman, White and Williams LLP
Mr. Darwick may be contacted at darwickg@whiteandwilliams.com
Mr. Elman may be contacted at elmans@whiteandwilliams.com
Read the full story...
A Win for Clarity: What a Recent Federal Court Decision Means for Davis-Bacon Compliance
July 13, 2026 —
Stephen E. Irving - Peckar & Abramson, P.C.Following the
Department of Labor’s 2023 Davis-Bacon rule changes, federal construction contractors faced a pressing question: not whether paying prevailing wages is required, but how far those obligations could extend. Could they reach off-site material suppliers? Delivery drivers? Contracts that omitted Davis-Bacon clauses entirely? A recent federal court decision in AGC of America v. US Department of Labor answers these questions in important ways, vacating several disputed provisions and giving contractors greater certainty when pricing, bidding, and administering federal construction projects.
The ruling addresses three aspects of the 2023 regulations that sought to extend Davis-Bacon obligations beyond their traditional scope. By vacating those provisions, the decision creates a more predictable compliance environment and reinforces an important principle: Davis-Bacon enforcement works best when contractors, workers, and regulators operate under clear, objective rules.
Read the full story...Reprinted courtesy of
Stephen E. Irving, Peckar & Abramson, P.C.Mr. Irving may be contacted at
sirving@pecklaw.com
For Urban Walkers, a Patchy Dilemma: Who Owns the Sidewalk?
July 06, 2026 —
Linda Poon – BloombergIn 2007, New York City’s sanitation department
threatened Natalie Shea with a $300 fine for defacing public property with graffiti. Her crime: drawing a blue flower in front of her family’s Park Slope home with sidewalk chalk. She was six years old.
The incident, which made
local and
national news at the time, captures the fraught role that sidewalks often play in US cities. These patches of pavement do more than carry pedestrians to their destinations: They’re also places for commerce, social interaction and childhood play, from chalking to learning how to ride a bike. Urbanist Jane Jacobs once likened the range of activities that city sidewalks attract to an “intricate ballet.”
In the new book
Sidewalk Nation: The Life and Law of America’s Most Overlooked Resource (Harvard University Press), author Michael Pollack explores the “tangled web of state and local regulation” that governs sidewalks, with cities often passing along responsibilities for tasks like clearing snow and keeping walkways safe. He paints a portrait of the American sidewalk a disorderly and often neglected network, filled with literal and metaphorical cracks that give rise to all sorts of conflict, from mundane clashes over maintenance to more consequential fights over accessibility and inequality.
Read the full story...Reprinted courtesy of
Linda Poon, Bloomberg
Prefatory Contract Language Cannot Be Used to Create an Ambiguity with Operative Provisions
May 12, 2026 —
David Adelstein - Florida Construction Legal UpdatesContract drafting and interpretation matters.
A case dealt with the potential conflict with prefatory language in an agreement compared with operative provisions in the agreement. The trial court held that the operative provisions control. I discussed this case
here where the appellate court reversed based on the prefatory language.
But, through a motion for rehearing, the appellate court reconsidered its position and affirmed the trial court based on the operative provisions, mainly that the prefatory language cannot be used to create an ambiguity with operative provisions. Consider this explanation in affirming the trial court:
Because the trial court correctly found that the initial language in the contract was prefatory and could not be used to create an ambiguity in the remainder of the contract, we affirm the final judgment.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.