Powering Data Centers in a Moving Regulatory Landscape: Positioning Deals Before FERC’s Next Move
April 27, 2026 —
Stephen J. Humes, Alicia M. McKnight & Andrew H. Jacobs - Gravel2Gavel Construction & Real Estate Law BlogThe explosive growth of data‑center load—driven by artificial intelligence, cloud computing and the expansion of digital infrastructure across industries—has forced U.S. energy regulators into unfamiliar territory. Nowhere is this more evident than at the Federal Energy Regulatory Commission (FERC), which is actively considering how large, concentrated loads can be powered without compromising grid reliability or shifting costs to other customers.
FERC has not yet issued a standalone rulemaking on data centers. But make no mistake, the regulatory framework is quietly and deliberately being built. For developers, hyperscalers, utilities and investors, the period before FERC finalizes its next round of decisions represents the critical window to crystallize advocacy and structure transactions in ways that anticipate regulatory change.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury and
Andrew H. Jacobs, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Jacobs may be contacted at andrew.jacobs@pillsburylaw.com
Read the full story...
New York Enacts First-in-the-Nation Statewide Data Center Moratorium
August 03, 2026 —
Joshua L. Sturtevant - SheppardAs of May 2026, nearly 12 gigawatts of data center load requests were in the New York Independent System Operator interconnection queue, with more than two-thirds of capacity requests entering the queue in 2025 alone. On July 14, 2026, in response to concerns over this rapid growth, Governor Kathy Hochul issued Executive Order No. 62 (the “Order”) imposing a temporary moratorium on data centers in New York State. Among the concerns cited in the Order are the cost burden on ratepayers associated with transmission upgrades required to accommodate large loads, potential environmental impacts, and large-scale water use.
The moratorium is intended to halt activities while the state government develops a comprehensive legal framework for data center development. While dozens of municipal and county-level moratoriums are in place throughout the U.S., and while the legislatures of several states, including Maine, have proposed moratoriums, the Order is the first statewide moratorium to be enacted nationally.
Read the full story...Reprinted courtesy of
Joshua L. Sturtevant, SheppardMr. Sturtevant may be contacted at
jsturtevant@sheppard.com
Ayushi Neogi Published in ADC Defense Comment on Arbitration in Evolving Plaintiff-Friendly Landscape
May 12, 2026 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani Senior Counsel Ayushi Neogi has authored an article in the Association of Defense Counsel of Northern California and Nevada’s Defense Comment magazine examining the shifting landscape of arbitration following the Ending Forced Arbitration Act.
Titled “Compelling Arbitration in a Post-Ending Forced Arbitration Act, Plaintiff-Friendly Landscape,” the article analyzes how recent legislative changes are reshaping arbitration strategy, particularly as employees gain greater ability to bypass arbitration in certain claims. Neogi provides practical insight into how courts are responding and what this means for defense counsel navigating increasingly complex and plaintiff-friendly environments.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Prefatory Contract Language Cannot Be Used to Create an Ambiguity with Operative Provisions
May 12, 2026 —
David Adelstein - Florida Construction Legal UpdatesContract drafting and interpretation matters.
A case dealt with the potential conflict with prefatory language in an agreement compared with operative provisions in the agreement. The trial court held that the operative provisions control. I discussed this case
here where the appellate court reversed based on the prefatory language.
But, through a motion for rehearing, the appellate court reconsidered its position and affirmed the trial court based on the operative provisions, mainly that the prefatory language cannot be used to create an ambiguity with operative provisions. Consider this explanation in affirming the trial court:
Because the trial court correctly found that the initial language in the contract was prefatory and could not be used to create an ambiguity in the remainder of the contract, we affirm the final judgment.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Yet Another Reason That Your Contract Matters
February 10, 2026 —
Christopher G. Hill - Construction Law MusingsI have discussed on several occasions the fact that
construction contracts matter. The words in contracts matter and, in Virginia (as well as other states), most provisions, if not all
will be enforced to the letter. Recently, the Western District of Virginia federal court ruled in a way that reminded me of another reason for a well-drafted contract.
In
Rockingham Precast, Inc. v. American Infrastructure – Maryland, Inc. the Western District of Virginia Court considered a motion to transfer the venue to Maryland filed by American Infrastructure. The plaintiff, Rockingham Precast, a Virginia-based company sued in Virginia. American Infrastructure conceded that VA could be a proper forum for the lawsuit but argued that the form was much too inconvenient and costly for the party and non-party witnesses and that the cost made the forum an unfair place to try the case.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Arbitration Provision Must Be Incorporated into a Bond for Surety to Elect Arbitration
March 03, 2026 —
David Adelstein - Florida Construction Legal Updates“Sureties cannot exercise unilateral election rights that are reserved for the principal of the underlying contract.” Anderson Service Corp. v. Old Republic Surety Company, 2026 WL 61436, *2 (Fla. 4th DCA 2026). This was the holding in a recent case dealing with arbitration.
In this case, a subcontractor entered into a contract with a contractor that gave the contractor the right to elect arbitration in Pennsylvania. A dispute arose and the subcontractor recorded a construction lien. The contractor transferred the lien to a lien transfer bond under Florida law. (The contractor was the principal of the lien transfer bond.) The lien transfer bond surety then moved to compel the subcontractor to arbitration based on the underlying subcontract. The trial court agreed to compel arbitration but this was reversed on appeal.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Indiana District Court Finds Crane Inspection Services Do Not Trigger “Professional Services” Exclusion in Liability Policy
February 17, 2026 —
Jason Taylor - Traub Lieberman Insurance Law BlogIn Crane 1 Holdco, Inc. et al. v. Continental Ins. Co., 23-cv-205 (N.D. Ind. Jan 12, 2026), the District Court for the Northern District of Indiana had occasion to interpret the scope and meaning of the term “professional services” in an excess liability policy exclusion. By way of background, Robert Coppage was crushed by a crane while at work. He was seriously injured and later received a significant settlement in a state court civil action against the company that inspected the crane, Crane1. Crane1 sought coverage for the settlement under a first layer excess policy issued by Continental Insurance Company, which included an exclusion for any “liability arising out of the actual or alleged rendering of, or failure to render, any professional services by the Insured or any other person for whose acts the Insured is legally responsible.” The underlying complaint alleged that Crane1 was negligent in its modification, services, maintenance, inspection, and/or repair of the crane.
Read the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Safeguarding Your Privileged Construction Information With a Clawback Agreement
June 08, 2026 —
Laura Fraher - Construction ExecutiveFor contractors and construction executives, a
dispute that escalates to litigation brings risks that go well beyond the jobsite. When a dispute escalates to litigation, the attorney-client privilege is a critical protection to safeguard your interests. Disclosing privileged material can undermine your litigation position and, in some cases, negatively impact your business. In the construction context, this often includes sensitive communications about project delays, defect investigations, safety incidents or payment disputes—materials that can significantly impact both liability and reputation.
During litigation, the discovery process requires the exchange of documents and data with your adversary. If privileged materials are disclosed to your adversary during discovery you risk the waiver of your privilege, which in plain terms means you lose the protection of the privilege and make the privileged information, and in some cases all other information related to the same subject matter, available to your adversary. It is critical that your attorney take steps to protect against the unintentional disclosure of privileged materials during discovery to avoid a waiver.
Reprinted courtesy of
Laura Fraher, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...Ms. Fraher may be contacted at
lfraher@barclaydamon.com